Project management Other Case Study
2 pages
(500 words)
, Download 2
, Case Study
According to the sequence of activities that form part of the plan of execution of the project and their respective durations, the AOA diagram needs to be made in order to identify the critical path and the critical activities. The activities can be arranged in the form of an AOA diagram as shown in the figure below: When the forward pass and backward pass is conducted on the activities, the critical paths get identified in the figure as follows: From the figure, it can be seen that activities 3, 6, 8, 9, 10, 12, 14, 15, 21, 24, 26, and 27 are on critical path as their total float is 0.