Our website is a unique platform where students can share their papers in a matter of giving an example of the work to be done. If you find papers
matching your topic, you may use them only as an example of work. This is 100% legal. You may not submit downloaded papers as your own, that is cheating. Also you
should remember, that this work was alredy submitted once by a student who originally wrote it.
This report "Work Breakdown Structure for the Construction of the Bridge Abutment" focuses on a retaining structure normally designed and put up at the edge of a bride to act as support. They act as resistant as well as transfer excess weight that may be caused by the lateral earth pressure. …
Download full paperFile format: .doc, available for editing
Extract of sample "Work Breakdown Structure for the Construction of the Bridge Abutment"
Name of the student
Name of the institution
Date of admission
Report background
Project management is the discipline of carefully projecting or planning, organizing, motivating and controlling resources to achieve specific goals and meet specific success criteria. In order to achieve aims and objectives of project management, work breakdown is used and in most cases, other tools like gant charts are used to explain and give direction in project management (Richardson & Lee 2011). The present Project Managers are frequently finding it very valuable in the creation of Work Breakdown Structures (WBS) as they begin the process of project management. Project success may be attributed specifically to use of a WBS. This report gives the work breakdown in the construction of abutment (Hunt & Lyons 2010)
Building of abutment
An abutment is a retaining structure normally designed and put up at the edge of a bride to act as support. Abutments in most cases are necessary to act as resistant as well as transfer excess weight that may be caused by the lateral earth pressure. An abutment is composed of a stem wall, an end diaphragm, and wingwalls. A stem wall or diaphragm functions as a wall providing lateral support for fill material on which the roadway rests immediately adjacent to the bridge. Abutments shall generally be of the cast-in-place, reinforced concrete type and shall be founded on spread footings, drilled shafts or driven pile footings (Landva et al., 2008). With the proposal of having an underpass linking A45 Stonebridge Highway to the A46 Coventry Eastern Bypass at Toll bar End junction a retaining wall with abutments at both sides should be constructed in such a way that highway is able to withstand the pressure of the motorist plying the route especially next to the underpass structure. Abutments are used at the ends of bridges to retain the embankment and to carry the vertical and horizontal loads from the superstructure to the foundation. The design requirements for abutments are similar to those for retaining walls and for piers; each must be stable against overturning and sliding. Abutment foundations must also be designed to prevent differential settlement and excessive lateral movements. The figure below shows a sample of abutment constructed (Hunt & Lyons 2010).
Recommended abutment structure
Abutment structures are structural elements that are connected to the ground and are designed to withstand the material pressure of the earth or other loads that may be above it at a given time. They are in most cases a combination of steel, concrete, masonry stone, soil, blocks or even pieces of wood firmly fixed together. Following the surveillance findings as well as the public opinion, a number of issues as raised by the relevant bodies must be adequately taken into consideration prior to deciding on the most appropriate retaining structures to be put up built (Seed & Whitman 2010). Among the issues that need to be scrutinized is the type of soil, that is, whether the soil is sandy, clay or loamy. However, the constructing a standard abutment structure is very costly and thus adequate measures needs to be in place to manage the entire construction phase. It’s therefore advisable that adequate resources are of financial or labour must be sought in advance so as to manage the construction phase to the end. The loads especially the backfill load which will be as a result of the pressure exerted by the external materials such as trucks will be calculated at –rest lateral earth pressure before the construction commences.
Stability in determination of the critical reaction from the beam seat; It involves the calculation of the nominal loading on each 1m length of the abutment beam. Estimating the length of the back wall; this will depends on the recommended maximum height of the trucks and motor vehicles to use the underpass. Estimation of the footing; the footing heel and toe depends on the width of the highway to be constructed.
Work Breakdown Structure for the Construction of the Bridge Abutment
The WBD below gives the stages of the construction of abutment bridge:-
Estimation of the footing
Expected activity schedules
The estimation of required resources, three areas must be taken into consideration, these includes the inputs, tools and techniques as well as the anticipated output.
Input
Methods & Tools
Output
Enterprise Environmental requirements
Judgment of the Experts
Duration of each activity estimate
Firm process assets
Analogous estimation
Activity based updates
Alignment of the project scope
Parametric estimation
List of construction activities
Three-point estimates
Activity based updates
Reserve analysis
Activity resource requirements
Resource calendar
Project management plan
The duration estimates are often carried based on the idea that there are adequate resources to enable completion of the project in queue. The casual labors will be working 5 days in a week Determination of the limit States of the Bridge abutment
Activity
2/11/2015
16/11/2015
25/11/2015
9/12/2015
4/1/2016
11/1/2016
Labour Required
Determination of the critical reaction from the beam seat
100
Estimating the length of the back wall
70
Estimation of the footing
100
Back fill load calculation at “at-rest” lateral earth pressure
70
Determination of the limit States of the Bridge abutment
50
Setting up of the Abutment Structure
50
Precedence Diagram
This is a diagram showing nodes representing activities connected by arrows which indicates the dependencies. It normally works in such a way that an activity begins only after completion of the previous activity. For instance activity (1.1) has to be completed before the commencement of activity (1.2)
1.1 1.2 1.3
Path 1
R 2.1 2.2 2.3
Path 2
ES-Earliest Start time of an activity
EF-Earliest Finish time of an activity
LS-Latest Start time of an activity
LF-Latest Finish time of an activity
Therefore, Float will be as follows:-
Path 1
(Longest critical path duration-Shortest critical path duration)
(10 + 7 + 10)- (7+4+7) =9 days
Path 2
(Longest critical path duration-Shortest critical path duration)
(7+5+5)- (4+3+3) =7 day
PART 2
a) Gantt Chart (Attached-Gantt Chart-PM)
Activity
2/11/2015
16/11/2015
25/11/2015
9/12/2015
4/1/2016
11/1/2016
Labour Required
Determination of the critical reaction from the beam seat
100
Estimating the length of the back wall
70
Estimation of the footing
100
Back fill load calculation at “at-rest” lateral earth pressure
70
Determination of the limit States of the Bridge abutment
50
Setting up of the Abutment Structure
50
b) Precedence Diagram
1.1 1.2 1.3
Path 1
2.1 2.2 2.3
Path 2
c) New Completion Date (Attached-Gantt Chart-PM 2)
d) Five ways to Amend the Project (Attached-Gantt Chart-PM 2)
In the usage of the shortest time period to complete a given activity: The time taken in every activity will have to be reduced so as to have enough time for the succeeding activities. The available work force can be combined so as to have a maximum output in one activity before proceeding to the next activity, that is, Project Manager A and B both pool their teams together to have one activity acted upon at once. The project managers can outsource some activities such as transportation of materials to the construction site in order to enable them get ample time to work on the necessary activities. The team managers should hire or buy effective and enough working tools to enable the casual labors work with speed in order to complete the job within the shortest time possible
The project management should consider increasing the workforce based on the ground that the project owner is aware of the delay that the contractor was subjected to, prior to the project commencement.
Reference
Hunt, J. G., & Lyons, G. D. 2010. Modelling dual carriageway lane changing using neural networks. Transportation Research Part C: Emerging Technologies, 2(4), 231-245.
Landva, A. O., Valsangkar, A. J., & Pelkey, S. G. (2008). Lateral earth pressure at rest and compressibility of municipal solid waste. Canadian Geotechnical Journal, 37(6), 1157-1165.
Richardson, G. N., & Lee, K. L. 2011. Seismic design of reinforced earth walls. Journal of the geotechnical engineering division, 101(2), 167-188.
Seed, H. B., & Whitman, R. V. 2010. Design of earth retaining structures for dynamic loads. In Lateral Stresses in the Ground and Design of Earth-Retaining Structures (pp. 103-147). ASCE.
Read
More
Share:
CHECK THESE SAMPLES OF Work Breakdown Structure for the Construction of the Bridge Abutment
The report shall include mechanical and structural supporting data useful in making decisions on the design of the bridge.... The design of the bridge has to consider various elements such as the weight of the materials, foundation as well as the hydrology of the area.... The considerations in the overall design of the bridge should include the mode of transport commonly used by students.... the bridge is meant to serve the high school students....
Swelling can also be caused by the chemical attraction of water molecules to layers within the crystal structure of some clay minerals.... The ground is such a precious commodity for human society.... It provides the nutrients that nourish plants and trees which in turn nourishes the succeeding levels of the food pyramid....
One of the reasons that increase costs for maintenance of bridge constructions is damage to bearings at the abutment as well as the expansion joints and usually, this costs as compared to the costs of the construction of road bridges is usually higher for medium class and short bridges (Hirakawa, Minehiro, Hiroyuki & Tatsuoka 2014).... The "Project Management of the Abutment Bridge" paper describes work breakdown structure, design of the abutment bridge, design loads and load combinations, load and load combinations for the bridge design, and presents recommendations for amending the program....
The following shows the diagram of the proposed bridge abutmentWork Breakdown Schedule (WBS) The Work Breakdown Schedule (WBS) for the construction of bridge abutment showing deliverables, work packages and activities to be undertaken.... Typical to this construction project is the following work breakdown structure.... Construction eastern abutmentExcavation of the first two abutmentMaking of structural form and rebar Abutment foundationconcrete pile cupabutment 1 wall56444Eastern side of bridge abutment 3....
During the construction process, it is important to ensure that a strong foundation is built before the other structures are put in place (Vesilind, Peirce & Weiner, 2013).... The paper "construction Site Management" states that ensuring that well functioning and operational equipment is brought to the site in advance is vital in the process of construction management.... One of the constraints is that the Reid Highway traffic cannot be interrupted by construction tasks....
The writer of the paper 'work breakdown structure' states that work breakdown structure is a key project deliverable that organizes the team's work into manageable sections.... For proper planning and project management, work breakdown structure is very essential and necessary.... work breakdown structure (WBS), in project management and systems engineering, is a deliverable-oriented decomposition of a project into smaller components....
This coursework "construction of an Abutment" focuses on a retaining structure normally designed and put up at the edge of a bride to act as support.... With the proposal of having an underpass linking A45 Stonebridge Highway to the A46 Coventry Eastern Bypass at Tollbar End junction, a retaining wall with abutments at both sides should be constructed in such a way that highway is able to withstand the pressure of the motorists plying the route especially next to the underpass structure....
Dasenbrock et al (2013) state that the limit state, which is the inability of the abutments to function, should be taken into consideration too during the construction of the abutment stem (wall).... The abutment is a retaining structure normally designed and put up at the edge of a bride to act as support to the bridge.... A stem wall or diaphragm functions as a wall providing lateral support for fill material on which the roadway rests immediately adjacent to the bridge....
5 Pages(1250 words)Coursework
sponsored ads
Save Your Time for More Important Things
Let us write or edit the report on your topic
"Work Breakdown Structure for the Construction of the Bridge Abutment"
with a personal 20% discount.