This coursework "Construction of an Abutment" focuses on a retaining structure normally designed and put up at the edge of a bride to act as support. They are often necessary to act as resistant as well as transfer excess weight that may be caused by the lateral earth pressure…
Download full paperFile format: .doc, available for editing
NAME OF THE STUDENT
DATE OF ADMISSION
NAME OF THE INSTITUTION
UNIT CODE
PROJECT MANAGEMENT
CONSTRUCTION OF AN ABUTMENT
An abutment is a retaining structure normally designed and put up at the edge of a bride to act as support. They often necessary to act as resistant as well as transfer excess weight that may be caused by the lateral earth pressure (Goel & Chopra 2007).
Ideally, due to the ongoing projects at Toll Bar End, an abutment with a double pile foundation will be the most appropriate one considering the fact that the area has an A45 Stonebridge highway that is westbound between Toll bar and Stivichall and needs widening as from the Northern Kerb line.
With the proposal of having an underpass linking A45 Stonebridge Highway to the A46 Coventry Eastern Bypass at Toll bar End junction, according to Ahmed & Rajaratnam (2000), a retaining wall with abutments at both sides should be constructed in such a way that highway is able to withstand the pressure of the motorists plying the route especially next to the underpass structure.
Components of such an abutment includes:-
The Back wall:-These are vertical walls that support sprouting from the abutment seats and act as support for the expansion joints of the bridge (Bratley & Schrage 2011)
The Footing heel & Toe
The Stem
The beam seat
Bridge Abutment Design
Checking of the Stability
Determination of the critical reaction from the beam seat; It involves the calculation of the nominal loading on each 1m length of the abutment beam
Estimating the length of the back wall; this will depends on the recommended maximum height of the trucks and motor vehicles to use the underpass
Estimation of the footing; the footing heel and toe depends on the width of the highway to be constructed
Retaining wall and the beam seat design
The loads especially the backfill load which will be as a result of the pressure exerted by the external materials such as trucks will be calculated at –rest lateral earth pressure before the construction commences
As stated by Thomopoulos (2011), the limit state, which is the inability for the abutments to function, should be taken into consideration too during the construction of the abutment stem (wall). The limit state can either be an ultimate limit state or serviceability limit state. The ultimate limit state is whereby an abutment experiences distress and structural damage as a result of sliding, overall instability or overturning. On the other hand, serviceability limit state is encountered when the abutment is unable to perform its intended design purpose fully due to too much deformation or deteriorations which may be caused by vibration, cracking or the lateral movement pressures.
Setting up of the abutment structure
Work Breakdown Structure for the Construction of the Bridge Abutment
The construction phase will be implementation as indicated in the Work Breakdown Structure (WBS) below:-
Estimation of the footing
Activity Schedule and Duration & Labour Resource estimation
The construction of the bridge abutment in the A45 Stonebridge Highway will require a number of resources including casual labour, equipment and material supplies to be used in the process
In estimation of required resources, three areas must be taken into consideration, these includes the inputs, tools and techniques as well as the anticipated output.
Input
Methods & Tools
Output
Enterprise Environmental requirements
Judgment of the Experts
Duration of each activity estimate
Firm process assets
Analogous estimation
Activity based updates
Alignment of the project scope
Parametric estimation
List of construction activities
Three-point estimates
Activity based updates
Reserve analysis
Activity resource requirements
Resource calendar
Project management plan
Ideally, duration estimates are often carried based on the fact that there are adequate resources to enable completion of the project in que
For instance, in the construction of the bridge apartment in the A45 Stonebridge Highway, all the necessary resources have been mobilized hence the project is expected to take 10 hours in every working day. The casual labors will be working 5 days in a week Determination of the limit States of the Bridge abutment
Current Activity
Previous Activity
Duration
Labour
Earliest Started Date
Determination of the critical reaction from the beam seat
10
100
02/11/2015
Estimating the length of the back wall
Estimation of the footing
Determination of the critical reaction from the beam seat
Estimating the length of the back wall
7
10
70
100
16/11/2015
25/11/2015
Back fill load calculation at “at-rest” lateral earth pressure
Estimation of the footing
7
70
09/12/2015
Determination of the limit States of the Bridge abutment
Back fill load calculation at “at-rest” lateral earth pressure
5
50
04/01/2016
Setting up of the Abutment Structure
Determination of the limit States of the Bridge abutment
5
50
11/01/2016
Precedence Diagram
This is a diagram showing nodes representing activities connected by arrows which indicates the dependencies. It normally works in such a way that an activity begins only after completion of the previous activity. For instance activity (1.1) has to be completed before the commencement of activity (1.2)
1.1 1.2 1.3
Path 1
R 2.1 2.2 2.3
Path 2
ES-Earliest Start time of an activity
EF-Earliest Finish time of an activity
LS-Latest Start time of an activity
LF-Latest Finish time of an activity
Therefore, Float will be as follows:-
Path 1
(Longest critical path duration-Shortest critical path duration)
(10 + 7 + 10)- (7+4+7) =9 days
Path 2
(Longest critical path duration-Shortest critical path duration)
(7+5+5)- (4+3+3) =7 days
PART 2
a) Gantt Chart (Attached-Gantt Chart-PM)
b) Precedence Diagram
Current Activity
Previous Activity
Duration
Labour
Earliest Started Date
Determination of the critical reaction from the beam seat
10
100
02/11/2015
Estimating the length of the back wall
Estimation of the footing
Determination of the critical reaction from the beam seat
Estimating the length of the back wall
7
10
70
100
16/11/2015
25/11/2015
Back fill load calculation at “at-rest” lateral earth pressure
Estimation of the footing
7
70
09/12/2015
Determination of the limit States of the Bridge abutment
Back fill load calculation at “at-rest” lateral earth pressure
5
50
01/01/2016
Setting up of the Abutment Structure
Determination of the limit States of the Bridge abutment
5
50
08/01/2016
1.1 1.2 1.3
Path 1
2.1 2.2 2.3
Path 2
c) New Completion Date (Attached-Gantt Chart-PM 2)
d) Five ways to Amend the Project (Attached-Gantt Chart-PM 2)
Usage of the shortest time period to complete a given activity: The time taken in every activity will have to be reduced so as to have enough time for the succeeding activities
The available work force can be combined so as to have a maximum output in one activity before proceeding to the next activity, that is, Project Manager A and B both pool their teams together to have one activity acted upon at once.
The project managers can outsource some activities such as transportation of materials to the construction site in order to enable them get ample time to work on the necessary activities
The team managers should hire or buy effective and enough working tools to enable the casual labors work with speed in order to complete the job within the shortest time possible
The project management should consider increasing the workforce based on the ground that the project owner is aware of the delay that the contractor was subjected to, prior to the project commencement.
\
BIBLIOGRAPHY
Ahmed, F., & Rajaratnam, N. (2000). Observations on flow around bridge abutment. Journal of engineering mechanics, 126(1), 51-59.
Bratley, P., Fox, B. L., & Schrage, L. E. (2011). A guide to simulation. Springer Science & Business Media.
Clark, W. (1952). The Gantt Chart. London.
Goel, R. K., & Chopra, A. K. (2007). Evaluation of bridge abutment capacity and stiffness during earthquakes. Earthquake Spectra, 13(1), 1-23.
Golany, B., & Shtub, A. Work Breakdown Structure. Handbook of Industrial Engineering: Technology and Operations Management, Third Edition, 1263-1280.
Hartley, H. O., & Wortham, A. W. (1966). A statistical theory for PERT critical path analysis. Management Science, 12(10), B-469.
Maloney, J. (2012). Work Breakdown Structure.
Maylor, H. (2001). Beyond the Gantt chart: Project management moving on. European Management Journal, 19(1), 92-100.
Meyringer, M. (2006). U.S. Patent No. 7,050,056. Washington, DC: U.S. Patent and Trademark Office.
Thomopoulos, N. T. (2011). Mixed model line balancing with smoothed station assignments. Management science, 16(9), 593-603.
Read
More
Share:
CHECK THESE SAMPLES OF Construction of an Abutment
This is because the concrete slabs cannot pass on top of the construction at this point.... This is because the concrete slabs cannot pass on top of the construction at this point.... There will be the risk of the bridge construction falling.... The pier is strong and can support the movement of all equipment and construction materials.... In the decision to pass the slabs through the old pier, the construction company can use larger stronger transport means such as Lorries....
The author of this essay "London Millennium Footbridge" touches upon the construction of a bridge in London.... This can also simplify the maintenance after the construction and allows easy execution of the construction phase.... It is stated that the London Millennium Footbridge is a steel suspension bridge which has been constructed to be used by pedestrians for crossing the River Thames in London....
The paper "Modern Bridge Construction Technologies" indicates the bridge designers look for the location and site parameters before designing and construction of a bridge, develop soil testing and rock formation, choose a specific foundation technique to build a strong and safe bridge.... The construction of flyovers to allow the traffic pass over at several layers is a fine example of bridges, that can be seen currently almost everywhere.... A few logs thrown across a small stream is the simplest form of the bridge construction....
One of the reasons that increase costs for maintenance of bridge constructions is damage to bearings at the abutment as well as the expansion joints and usually, this costs as compared to the costs of the construction of road bridges is usually higher for medium class and short bridges (Hirakawa, Minehiro, Hiroyuki & Tatsuoka 2014).... The "Project Management of the abutment Bridge" paper describes work breakdown structure, design of the abutment bridge, design loads and load combinations, load and load combinations for the bridge design, and presents recommendations for amending the program....
The following shows the diagram of the proposed bridge abutmentWork Breakdown Schedule (WBS) The Work Breakdown Schedule (WBS) for the construction of bridge abutment showing deliverables, work packages and activities to be undertaken.... 1Site visits and preparation Delivery of materials and equipment 22Site house, store Materials and equipment for abutment construction 2.... Construction eastern abutmentExcavation of the first two abutmentMaking of structural form and rebar abutment foundationconcrete pile cupabutment 1 wall56444Eastern side of bridge abutment 3....
The report is on the construction of footpath bridge project over highway No.... The construction of the footpath bridge is as a result of increased cases of road carnage in the busy highway.... The construction of the footpath bridge will provide sustainable crossing and safety to pedestrians and make it easier for access to social amenities that are situated along the highway.... The paper 'Pre-construction Report of Pedestrian Foot Bridge' is an earnest variant of an engineering and construction case study....
an abutment can be defined as a retaining structure normally designed and put up at the edge of a bride to act as support.... As results of ongoing construction at Toll Bar End, an abutment with a double-pile foundation will be the most appropriate one considering the fact that the area has an A45 Stonebridge highway that is westbound between Tollbar and Stivichall and needs widening as from the Northern Kerb line....
This coursework "Factors to Consider When Designing an abutment Bridge" provides an outline of typical construction methods and plants likely to be used for the main roadwork's, structures including bridges and ways to reduce the project time through manipulation of various variables.... an abutment includes an end diaphragm, a stem wall and wing walls.... referably, due to the ongoing projects at Toll Bar End, an abutment with a double-pile foundation will be the most appropriate one considering the fact that the area has an A45 Stonebridge highway that is westbound between Tollbar and Stivichall and needs widening as from the Northern Kerb line (Dasenbrock et al....