Introduction

The four bridge abutments will be built in for the bridge and from exaction to filling up. The project will feature all the modern and ecological facilities and will ensure all the necessary utilities and appropriate connections. The following shows the diagram of the proposed bridge abutment

Work Breakdown Schedule (WBS)

The Work Breakdown Schedule (WBS) for the construction of bridge abutment showing deliverables, work packages and activities to be undertaken. This is shown below

Level 1

Level 2

Activity

Duration

Deliverable

1.0 Site preparation and materials

1.1

1

Site visits and preparation

Delivery of materials and equipment

2

2

Site house, store

Materials and equipment for abutment construction

2.0 two abutment

2.0

2.1

2.2

2.3

2.4

2.5

Construction eastern abutment

Excavation of the first two abutment

Making of structural form and rebar

Abutment foundation

concrete pile cup

abutment 1 wall

5

6

4

4

4

Eastern side of bridge abutment

3.0 Construction western abutment

3.0

3.1

3.2

3.3

3.4

3.5

Construction western abutment

Excavation the last two abutment

Abutment foundation

Making of structural form and rebar

concrete pile cup

abutment 1 wall

5

4

6

4

4

western side of bridge abutment

Close out

4.0

4.1

4.2

Backfilling and cleaning

Backfilling of first two abutment

Backfilling of last two abutment

3

3

Completion of the work

4.3

Cleaning up the area

2

The above Work Breakdown Schedule has decomposed the project into two levels, given output activity list and duration. These illustrations help to identify potential loopholes in the project. This bird-eye view of the project helps create reference points for various activities required in the project phases. This is followed by another best practice of ‘verifying the scope and getting the feedback’. Since timeliness is a crucial component of projects, verification of the scope is also critical in the progress of the project cycle.

Work Breakdown Structure

Thus verification can be done as each major task is completed in the case of a long project. However, for a small project which is not phased, it can be done after the completion of the whole project. To work on this, there should be good change management process and in case of changes the budgeting and schedule should be adjusted. Typical to this construction project is the following work breakdown structure.

Activity schedule and Resource estimates

This depends on the resources available; the project will be completed on January 10, 2016. Moreover, the project manager and project team will be expected to work for almost 10 hours each day so that the project can be completed in the expected period. The project manager will be expected to give guidelines on how each task will be carried out (Haughey, 2010). Each individual in the project team shall be assigned a specific task depending on his or her area of expertise. This will prevent any instances of conflict of interests or duties throughout the project. The project managers will be expected to supervise and direct every operation throughout the project. In case a problem occurs during the development period, the project managers should notify the sponsor immediately. These problems might include; reduction of the scope of the project, employing additional resources, or renegotiating the deadline when time becomes a problem

Activity

Duration

Resources

1.1

Site visits and preparation

2

Labor

1.2

Delivery of materials and equipment

1.1

2

Labor

2.0

Construction eastern abutment

2.1

Excavation of the first two abutment

1.2

4

Labor, crane Cat and Drill

2.2

Making of structural form and rebar

2.1

6

Labor

2.3

Abutment foundation

2.2

3

Labor

2.4

concrete pile cup

2.3

2

Labor

2.5

abutment 1 wall

2.4

4

Labor

3.0

Construction western abutment

3.1

Excavation the last two abutment

1.2

4

Labor, crane Cat and Drill

3.2

Abutment foundation

3.1

3

Labor

3.3

Making of structural form and rebar

3.2

6

Labor

3.4

concrete pile cup

3.3

2

Labor

3.5

abutment 1 wall

3.4

4

Labor

4.0

Close out

4.1

Backfilling of first two abutment

2.5

3

Labor ,Cat

4.2

Backfilling of last two abutment

3.5

3

Labor ,Cat

4.3

Cleaning up the area

4.1, 4.2

2

Labor

Manual precedence diagram

Activities:

  • Site visits and preparation
  • Delivery of materials and equipment
  • Excavation of the first two abutment
  • Abutment foundation
  • Making of structural form and rebar
  • concrete pile cup
  • abutment 1 wall
  • Excavation of the last two abutment
  • Abutment foundation
  • Making of structural form and rebar
  • concrete pile cup
  • abutment 1 wall
  • Backfilling of abutment
  • Cleaning up the area

Part 2 – 50 marks

Gantt chart

b) precedence diagram

c)

((15 marks)

d) FIVE possible ways to amend the programme to meet the required completion date

Reduce activity duration

Work during the weekends

Work during holiday period

Increase the working hours

Increase resources

References

Roger Bullivant. © Roger Bullivant Limited 2008. 25 Nov.2011 < http://www.roger-bullivant.co.uk/products/underpinning.html>

...Download file to see next pages Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(URGENTProject Management Example | Topics and Well Written Essays - 975 words, n.d.)
URGENTProject Management Example | Topics and Well Written Essays - 975 words. https://studentshare.org/engineering-and-construction/2054264-urgentproject-management
(URGENTProject Management Example | Topics and Well Written Essays - 975 Words)
URGENTProject Management Example | Topics and Well Written Essays - 975 Words. https://studentshare.org/engineering-and-construction/2054264-urgentproject-management.
“URGENTProject Management Example | Topics and Well Written Essays - 975 Words”. https://studentshare.org/engineering-and-construction/2054264-urgentproject-management.
  • Cited: 0 times

CHECK THESE SAMPLES OF URGENTProject Management

Current Practice in Project Management an empirical study written by Diana White and Joyce Fortune

The focus of the research was to explore the critical success factors of project management, tools, techniques, and methods used by project managers and effectiveness, limitations, and side effects of the methods employed by project managers.... … The research explores the dynamics of project management from the perspective of the project manager so that the research could capture the glance and taste of practical and ground realities regarding project management....
11 Pages (2750 words) Essay

Project management report for Zenith Company Inc

According to the research findings it can therefore be said that proper project management is important for any project to meet its objective and achieve success.... project management involves in-depth process of planning, execution or implementation, and monitoring and evaluation at every phase of implementation.... The management team at Zenith PM has decided to enhance the current business strategy by introducing a new approach on their core business model to improve business performance and success....
39 Pages (9750 words) Essay

Analysis of Current Practice in Project Managementan Empirical Study by Diana White

The title of the paper is ‘Current Practice in project management—an Empirical Study', and it was presented by Diana White who works in the Open University's Centre for Complexity and Change.... This paper was published in the year 2002 in the International Journal of project management: PERGAMON.... Lewis(2004), project management is “…the planning, scheduling and controlling the scarce resources to achieve desired results…[which] are defined in terms of four factors, called Cost, Schedule, Performance, and Scope”....
10 Pages (2500 words) Research Paper

Project Management Using the Lean Systems Project Management Methodology in the Versace Project

The author of this paper presents the project management using lean systems project management methodology.... project management deals with controlling, motivating organizing and planning resources so as to achieve the organization's objectives (Meredith, 2010).... project management, therefore, requires the managers and their teams to develop distinct technical skills and management strategies.... The lean systems management approach was chosen due to the fact that lean system methodology regards to project management that all tasks need to serve the purpose of the customer as efficiently as possible (Atkinson, 2006)....
10 Pages (2500 words) Case Study

Sustainable IT Services - Assessing the Impact of Green Computing Practices

Part 1 Task 1 In the article entitled ‘Sustainable IT Services: Assessing the Impact of Green Computing Practices', Harmon and Auseklis (1707) defines green computing as the practice which seeks to utilize computing resources in an efficient manner while seeking to maintain and increase overall performance....
8 Pages (2000 words) Research Paper

Effective Management Strategies in the UAE

project management Name of the Student: Name of the University: Date: GASCO project management Survey Report 2013 Table of Contents Executive Summary 4 Background of the Problem 4 Main Research Objective 5 The Methodology 5 The Sample 6 Limitations 6 Findings 6 Recommendations 13 Appendices 14 Reference List 24 Executive Summary With the advent of globalization business across the world are getting connected in one way or the other.... In order to makes themselves stand apart from their competitors and gain competitive advantage; businesses are adopting various project management strategies....
6 Pages (1500 words) Essay

Alignment with Corporate Strategy

As per PMBOK Guide, project management is the use of… Any project can not be accomplished without proper planning, organizing, monitoring and managing the project functions as per the projected needs (Mangano, 2008). ... Let's hope that ideas offered by all of us on how to implement latest project management principles and processes to better manage time and cost factors could help the our organization.... Our objective is to provide inputs on effectively managing new projects through our individual ideas on why project success rate is falling down while keeping the principles of project management in view....
5 Pages (1250 words) Case Study

Petroleum economcs and project management

The organisation of petroleum exporting countries (OPEC) was created in 1960 based on principles of ensuring the stability of prices in the oil market, obtaining stable revenues for oil producing nations and to provide a reliable and efficient supply of oil to the consuming… One of the major functions of OPEC is to ensure stability by making sure the prices are kept in a moderate range and avoiding extremes in the ever volatile oil market. ...
15 Pages (3750 words) Assignment
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Contact Us