The paper “The Handicap International Project Management Plan” is a valuable example of a management business plan. The entire report will illustrate the detailed plan of the project from the viewpoint of a project manager…
Download full paperFile format: .doc, available for editing
Extract of sample "The Handicap International Project Management"
The Handicap International INTRODUCTION 1 Purpose of Project Management Plan The entire report will illustrate the detailed plan of the project from the viewpoint of a project manager. The function of the organization is to help the victims of cluster munitions and anti-personnel mines plan is to deal with the mission of the organization and achieving the organizational objective with effectiveness. Along with this the organization also provides help and support services to the handicap children and adults. This project aims at conducting a campaign for the betterment of the autistic children of Canada. The purpose of the present project is to provide proper support and assistance to the autistic children of Canada. The proposed audience of the Handicap International PMP is all project stakeholders including the senior leadership, the project team and project sponsor (Handicap International, N.d.).
2 Executive Summary of Project Charter
Handicap International provides educational services along with assessment and diagnosis services, speech therapy, computer and physical education, music education as well as education on home economics. Also, auditory integration rehabilitation as well as counseling and relevant support services to the parents of the autistic students falls within the service offering of the organization. In the case of promoting the services offered by the Handicap International, the offline advertising tactic needs to be implemented. It can be said in a more precise manner that the offline advertising will be more effective in this particular case. For the purpose of value propagation, the organization should focus on putting up advertising displays in various locations of New Brunswick and the Atlantic provinces which are the main target markets. Also, standing displays will be provided in front of various clinics and treatment centers which provide specialty cares and other relevant treatments associated with reducing the impact of autism among the young children. This report discusses all the relevant aspects like resources, costs, time frame, marketing, human resource and other facets required for planning a project.
2.1 Assumptions/Constraints
The constraints in the autism project states that the fluctuating market situation can affect the operations and progress of the project. Moreover the weather conditions can also affect the same.
3 Scope Management
3.1 Work Breakdown Structure
3.2 Deployment Plan
The deployment plan will include planning the activities, arranging for the activities, performing all the HR related functions, arranging for funds and sponsors, planning the advertising and promotional activities, framing the budget for the program, comparing with the competitor’s activities and looking for areas for improvement.
4 Schedule/Time Management
The implementation schedule is a very important part of any campaign as it helps in a great way to implement the various factors of the business plan in a timely manner. The time factor plays a major role in the case of implementing a campaign plan, as it helps in reducing the incidents of overshooting the cost. Generally, the implementation schedule is often drawn while following five necessary steps. The first step is to identify and list down the activities that are required to be performed before the process of actual starting of the business process. The second step is to determine the level of interdependence the activities have with each other and as a result, the amount of delay that might happen because of the interdependence. The third step is to identify the activities which can be performed in a simultaneous fashion. The next step is to identify the time needed to complete each activity while the final step is to determine the resources needed to complete each of the activities (Tulsian and Pandey, 2002, p. 4.16). The implementation schedule for the Handicap International’s autistic support program is given below:
Activities
Weeks
1
2
3
4
5
Conducting the industry Overview
Deciding on the locations of the campaign
Designing the campaign
Conducting the market analysis
Designing the marketing plan
Designing the human resource development plan
Designing the operations plan
Deciding the management hierarchy
Studying the market risks
Designing the financial plan
Identifying the risks
4.1 Milestones
The table below lists the milestones for this project, along with their estimated completion timeframe.
Milestones
Estimated Completion Timeframe
Planning activities
Must finish within two weeks after the approval of the project plan
Planning for sponsorships
Must finish within two weeks of planning the project
Planning for marketing activities
Must finish within two weeks of planning the project
Planning for HR activities
Must finish within two weeks of planning the project
Planning for financial activities
Must finish within two weeks of planning the project
Execution and supervision
Must start from the planning activities and must end with the execution of the activities
4.2 Project Schedule
Current Date
2/16/2014
Title
MSProj11
Project Start
2/17/2014 8:00:00 AM
Project Finish
3/7/2014 5:00:00 PM
4.2.1 Dependencies
The dependencies related to the project are the market conditions, political environment and natural environment of the locality where the campaign should be carried out.
5 Cost/Budget Management
5.1 Expense Forecast
Every business incurs certain expenses which may be routine expense (such as employee expense), capital expenditure (such as purchase of plant and machinery), daily expenses (working capital requirement), and so on. Expenses forecasting is a part of periodical budgeting and is mainly prepared by the finance manager of the organization. The important parts of expense forecasting are expense inputs such as employee training and development program, cost of packaging, freight and transportation expenses, travelling allowance of the employees, and so on. Using the various inputs, the managers will be able to forecast future expenditures using expense forecasting reports. The details of assumptions are illustrated in the following sections.
5.2 Start-up Cost
Uses of Cash
in $
% of Debt
Sources of Cash
Signage
5,258
2
Supplies
21,032
8
Office Equipment
18,403
7
Leaseholds
23,661
9
Washer / Dryers
3,943
1.5
Fixtures
6,572
2.5
Drop-off Bin
2,629
1
Hangers
2,629
1
Telephone
5,258
2
Cash Register
10,516
4
Safe
26,290
10
Security System
26,290
10
Debit / Scanner
31,548
12
Project Manager
65,725
25
2 Months Costs
13,145
5
Total
262,898
100
Total Debt
262898
5.3 Capital Investment
Depreciable Life (Years)
5
ITEMS
2013
2014
2015
2016
2017
Start Asset
$112,657.00
Annual Capital Addition
$0.00
$3,000.00
$5,000.00
$5,000.00
$5,000.00
Total Assets
$112,657.00
$115,657.00
$120,657.00
$125,657.00
$130,657.00
Depreciation
$22,531.40
$22,531.40
$22,531.40
$22,531.40
$22,531.40
$600.00
$600.00
$600.00
$600.00
$1,000.00
$1,000.00
$1,000.00
$1,000.00
$1,000.00
$1,000.00
Annual Depreciation
$22,531.40
$23,131.40
$24,131.40
$25,131.40
$26,131.40
Cumulative Depreciation
$22,531.40
$45,662.80
$69,794.20
$94,925.60
$121,057.00
Start Balance
$112,657.00
$93,125.60
$74,994.20
$55,862.80
$35,731.40
End Balance
$90,125.60
$69,994.20
$50,862.80
$30,731.40
$9,600.00
5.4 Debt Schedule
Initial Debt
262898
Interest cost
12%
Loan Amortization Table
Items
2013
2014
2015
2016
2017
Start Balance
$262,898.00
$262,898.00
$197,173.50
$131,449.00
$65,724.50
Principal payment
$0.00
$65,724.50
$65,724.50
$65,724.50
$65,724.50
End balance
$262,898.00
$197,173.50
$131,449.00
$65,724.50
$0.00
Interest cost
$31,548
$23,661
$15,774
$7,887
$0
5.5 Key Assumptions
Monthly
Annually
Phone
1,791
21,491
Internet
80
960
Advertising
2.5%
Monthly
Annually
Utilities
590
7,080
Sq Feet
Cost per Sq Feet
Annual Lease Costs
Lease
8,059
19.00
153,124
Monthly
Annually
Bank Charges
1,500
18,000
Security
8,955
107,456
Insurance
1,500
18,000
Office Expenses
18,805
225,657
Disposal Expenses
895
10,746
Assumptions
Items
Growth Rates
Income/Revenue:
% Change
Subsidies received
13.2%
Donations & Subsidies Capital Items
12.7%
Program fee
9.1%
Interest Received
1.6%
Dividends received
34.8%
Fundraising Activities
12.9%
Membership fee
36.3%
Rent received
19.0%
Levies
38.7%
Professional workshop
3.2%
Sundry income
15.7%
Expenditure:
% Change
Adult Services
11.7%
Childrens Services
6.4%
Fundraising General
-7.5%
Membership
9.5%
Outreach services
11.3%
Administration
20.0%
Training
6.2%
Depreciation & Amortization
3.3%
6 Quality Management
Quality may be guaranteed through investigations, audits, formal testing and documentation of deformities in an imperfection following framework to guarantee imperfections are altered, retested and shut. A few activities may decide to utilize a traceability matrix to figure out if discriminating prerequisites have been met.
7 Human Resource Management
The human resource of the organization belong to educated and specialized backgrounds who are experts in dealing with children having autism and these people offer the quality service to the organization. However the diversity among the team members often cause conflicts and disputes and thus the management works hard towards imparting a diversity training to its employees.
8 Communications Management
8.1 Communication Matrix
Stakeholder
Messages
Vehicles
Frequency
Communicators
Feedback Mechanisms
The sponsors, autistic children, the parents
To make the children feel that they are no lesser than others
Most of the promotion was done by the means of placards, road-shows, pamphlets, online awareness ads and emails.
The frequency of the ads on roads were conducted on a daily basis throughout the planning week and the other forms of ads are very frequent
The organization’s representatives
The feedback forms were distributed to the stakeholders in person and via online media
8. Risk Management
1 Market Risk
An important risk for the organization is the market risk. Talking in an elaborate manner, it can be stated that the market risk for a company arises when there are already a large number of competitors present in the same market. Also, the presence of hostile kind of external factor based influences also increases the market based risks for the business. Also, it has to be considered, that the organization, during the initial days will be dependent on funds raised through various grants provided by the government. For the government to continue providing grants, it is important for the regional economy to grow in a steady manner since it will help in generating positive revenue from the activities. In case, the economy of the region goes into a depression, it will acts as a negative external influence for the autism campaign. The economic down turn of the region will impact the government revenue generation capacity from its diverse activities and will automatically result in the process of adoption of spending cuts. The adoption of spending cuts will lead to the process of curtailing of sponsorship of government backed grants which will naturally impact the start-up venture ability to fund its operations in the nascent stage.
8.2 Management Risk
Since this is a new campaign, it is important to state that the operational processes of the autism program as well as its management structure will be very much flexible in nature. It needs to be stated that the autism program by Handicap International is managed by three co founders who are from management backgrounds. As a result, the ownership of the responsibilities of the various processes of the company needs to be shared by the cofounders in a very equal and dynamic manner. Trying to follow a very rigid management structure while handling the day to day operations of the autism program will lead to increase in difficulty in regards to smooth execution of the various processes. This will automatically trigger the rise of management based risk.
Another factor that needs to be discussed in regards to the management risk is the recruitment and engagement of inept managers who have a high tendency to provide resistance in regards to changing business processes. It needs to taken into account that the changing business processes are very much applicable in the case of a start-up venture where every process is tried and tested in regards to its success factor before formally implementing it and accepting it on a permanent nature. The presence of hostile managers in the management team of the autism program will lead to boosting up the resistance in regards to experimentation of business processes and thereby raise the management risk as well.
8.3 Low inflow of students
Another significant risk for the Handicap International’s autism campaign is the fact of low inflow of students. The low inflow of students is a very strong risk factor for a new campaign since it will affect the financial performance of the organization. Explaining in a simpler manner, it has to be stated that the enrolment of new students will help in the process of getting subscription for the services of educational as well as special nature offered by the campaign. The low numbers of student inflow will significantly impact the amount of student enrolment in a negative manner. The low student enrolment will directly impact the generation of essential operating finances because of the fall in subscription of educational and special services offered by the organization to the autistic children living in the regions of New Brunswick and the Canadian Atlantic provinces.
Apart from the market risk, management risk as well as risk associated with low inflow of students, there are other risks that are present for a venture. One of the most important among them is the risk associated with natural calamities like earthquakes and floods. Talking in regards to the risk of natural calamity from earthquakes, it has to be highlighted that the entire region of Canada is located in a zone of high seismic activities and tectonic plate movements (Natural Resources Canada, 2013). This makes the risks from natural calamity like earthquakes very much valid in nature. In talking about the risk of natural calamity from floods, the presence of multiple flood plains and river valleys along with harsh weather, soil erosion make the region of New Brunswick highly vulnerable (getprepared.gc.ca, 2013). As a result, the natural calamity factor of floods makes up for a very much of a viable risk for the newly started autism program.
9 References
getprepared.gc.ca. 2013. Floods. Available at http://www.getprepared.gc.ca/cnt/hzd/flds-eng.aspx
Natural Resources Canada. 2013. Earthquake zones in Eastern Canada. Available at http://www.earthquakescanada.nrcan.gc.ca/zones/eastcan-eng.php
Tulsian, P.C., and Pandey, V. 2002 Business Organisation and Management. India: Dorling Kindersley Pvt. Ltd.
Handicap International. N.d. The Canadian Section. Available at http://handicap-international.ca/en/who-we-are/the-canadian-association
Read
More
Share:
CHECK THESE SAMPLES OF The Handicap International Project Management Plan
This paper aims to explore possibilities and status of project financing and public-private-partnership programs in India.... It examines the risks and barriers that may hinder investments in the potential Indian market, and further explains the structure of project finance.... The findings suggest that perceptions of political and legal nature, corruption, and economic risk can hinder project finance and foreign investments in the Indian market....
be supported by senior management in the process and through the decision makin... "Client briefing is considered to be one of the most important stages in the life of a project .... (Smith 2002) The research resulted in indicating that client briefing at the strategic level had the most potential for cost savings in the project.... Understanding the project priorities and business objectives 2.... Being client oriented rather than focusing too much on the details of the project to the detriment of the broader issues and objectives....
he expansion of the staff also needs to be done, by employing more professionals, to keep up the expansion plan and also to introduce more specialisation in the varied departments of the business.... isk management is another area of working that needs concentration.... The project has a case study of Sheffield Isus, a shop set in Sheffield which deals with the selling of Sheffield-speciality products....
The paper "Educational Issues and Special Education Needs" describes that one of the most significant points to note about integration in England and Wales is the growing acceptance of integration as a matter of school reform, as opposed to the accumulation of individual programs.... .... ... ... Policies are affected by past practices, budgetary considerations and specific local factors....
The paper "Politics in Information Technology " states that .... ... ... By looking at information technology in the perspective of cultural practices, I have realized how it benefits; especially regrind issues such as in regulating, societal, communal and financial practices.... In the event of migrating from analogue to digital, society excludes particular groups; this is illustrated in the case of the Amazon Kindle....
In the paper 'project Hope and the Board' the author looks at project Hope, a human service organization formed to provide equal health opportunities for people around the world with special focus on children's health.... Since its inception, the project has strived to provide medical services.... The author states that the objective of project Hope is to educate community health volunteers and health professionals, distribute supplies and medicines, support health facilities, and fight diseases like Diabetes, HIV/AIDS, and TB....
The case study "Non-IT Managers managing IT Projects " states that project management is an approach of planning, organizing & managing resources to achieve flourishing goals & objectives of the specific projects.... project management: While the focus of IT in recent years has been towards intuitive, ease-of-use, end user-friendly technology, underlying systems are getting extremely complicated more so its development & management.... project management constitutes of Professional & Social Responsibility, knowledge areas & process groups (Mulcahy, 2005)....
among others are organizational design and communication management.... The following sections will examine the Sydney Theatre Company's organizational design, communication management, adaptability, and sustainability.... Even a simple task such as passing a message along to all employees becomes very difficult for the management since at no given moment is it possible to have all the members of staff available.... Even though workers at the management level are not unionized this is not a serious challenge....
20 Pages(5000 words)Case Study
sponsored ads
Save Your Time for More Important Things
Let us write or edit the business plan on your topic
"The Handicap International Project Management Plan"
with a personal 20% discount.