The paper "Development of Residential House" highlights that the project is going to analyze the prevailing activities involves in the development of my friend residential house, in regards to his tight budget that he believes will be able to complete the project effectively and of high quality…
Download full paperFile format: .doc, available for editing
Extract of sample "Development of Residential House"
Project development Management Development of residential House Introduction A development management project is a predominant report that conveys a beginning and an end activity that goes in hand with the prevailing budget availed. When developing a project an aspect of cost and quality should be considered highly hence enabling an event or activity be completed on time and effectively. However, this project is going to analyze the prevailing activities involves in the development of my friend residential house, in regards to his tight budget that he believes will be able to complete the project effectively and of high quality.
A project however, should be clearly defined with consistent plans which curb an aspect of failure in the deployment of the project and its span (Ghantt, 45-51).
This report however, is going to analyze the scope of this project, its objectives, constraints, what the management talks about stakeholder, risk prevailed, resources needed, monitoring activities and schedule as well as the quality of the house that will be in a construction process. This will be covered from the time project starts to its end in regards to my friends given tight budget. However, we know that the project will encounter limitations that come around as hindrances due to timeframe and availability of materials that will make this project successful. Also change in the pricing may affect the effective completion of the residential house since this may affect the total budget of the project in regards to additive that prevail a limitation aspect.
Project scope
The scope of this project will therefore include an aspect of skills behind architectural activities on planning and development of the house, the knowledge of the stakeholders behind the project and the expectations as well as the needs that my friends expect for me to meet to adhere with his budget (Schmitz, 22-29).
Objective of the project
The objective of this project is to ensure that the development of this residential house is completed within a given timeframe. The work therefore is supposed to be completed on time and according to the budget availed by my friend.
Project Constraints
This is the general execution materials as well as resources that are needed for this project to be completed successfully. The project however looks forward to deal with budget constraint that at times leads to exceed in the estimated budget, delivery constraint that usually depends on the internal and external operation due to timeframe availed. However, Transportation also is one of the constraints that engage an aspect of materials being delivered late as well as this may be affected by weather conditions evident on the time of work progression.
Management stakeholder on the project
The development of this residential work is working under a tight budget of 200,000 US dollars. This is an incline observation that is considered on the purpose of material purchase, payments of workers, and payment of the structure planning as well as the payment of other amenities like foods among others.
Milestone of the project
This is the entire stages that this project should meet for its completion. However, duration is the best resolution as far as the milestone aspect is concerned. The date that the project is supposed to start, the completion date and the deployment date however, are the distinct backbone of this milestone project. This work therefore should be done in a lifespan of one month hence; the project starting from the tenth of August up to tenth of September the year 2014. The deployment date which is meant for orientation of the completed work to my friend should be done on eleventh of April year 2013, after the completion of the development of this residential house as part of the project planning.
The resources of the project
Resources are the main materials that are needed to complete the entire project up to its cause. This development of residential house will therefore need ballasts, sand, nails, iron sheets, iron bars, workers and other amenities. This are the resources availed to complete this project at high quality standards.
The Budget of the project
The project is however, under tight budget of 200,000 US dollars. The budget will be availed as follows in the table below.
Total budget availed = $ 200,000.00
Item
Cost ($)
Ballast
60,000.00
Sand
45,000.00
Nails
2,500.00
Iron Sheets
45,000.00
Iron Bar
17,500.00
Workers
10,000.00
Other amenities
5,000.00
TOTAL
185,000.00
According to the above contingency planning, we realize that a debit sum of money remains. This is however, to cover any risks availed in the process of the residual construction and this contingency of 15,000 US dollars will be there to cover the available risk, should the materials increase in pricing or any other additive that may come across without the knowledge of the exact budget.
Project Risk Management
This is unforeseen event in the prevailing project that affects the entire work of a given project for this case the development of my friend residential house, hence; posing negative as well as positive influence towards the completion facet (Sully, 13-18). This project however, will try to trace all the unseen risks that prevail in the assessment period which will be done at deployment level. The project risk management will ensure that these risk are dealt with and any prevailing issue has been avoided to create a room efficiency in the work done
Risk evaluation to stakeholder’s analysis
This evaluation will be ascertained in regards to risk events, the profitability and the general impact it has over the whole period of the development of this residential house.
Event
Impact
Profit Margin
Availability of expertise like architectural personnel for Planning
Medium
Low
The suppliers of the materials such as sand, Ballast
High
Medium
The availability of the workers
High
Low
Prevailing weather condition that affects the availability of workers and also the acquisition of desirable materials
Medium
High
From the above evaluation we found that if the workers fail to come at work then the timeframe that will take for the work to be completed will need an adjustment, one of the prevailing risks in this project. We learn that the priority of materials not being delivered on time will affect the whole process hence; nothing will be availed in the line of work.
Stakeholder Analysis
From the general review of stakeholder, it initiates an aspect any individual group that has interest over the success towards the prevailing project. The product and services being delivered should therefore be propelled by the viability and effective result from the group that is behind the proclaimed project. The stakeholders in this project therefore include; The architectural reform that is in need for project planning, the workers to maintain the general casual work, the sponsor who is my friend for the purpose of initiating capital and the suppliers who are the main contributors in the supply of materials for the development.
The quality prevailed and the monitoring activities
This work has to be done in the stipulated time to provide room for deployment and ascertain if there is anything to be corrected before giving my friend an opportunity to look over the completed individual residential house. However, it is advisable and convincible to install proper monitoring essence which eliminates any aspect of poor quality in the project. Poor quality may come as a result of the use of low standards materials provided, lack of the workers engagement and concentration as well as lack of acquisition standards laid down by the architectural planning department in the development of this residential house. If all this prevailing policies and activities are of more concerned during the development of this project, then this project will be of high quality one of the aspects that this project entails to conquer in the all processes involved.
Communication plan
Communication plans involves effective coordination and this should be availed each and every week to ensure that everything goes well. This however, will ensure that I have taken all the contact phone number of the suppliers and the workers so that should any problem arise am able to communicate with them in time.
Product Importance to sponsors
This development project therefore has importance to the sponsor in that the project has to avail the following. The project has to portray momentous and be completed successful and it is upon me to find the cheaper supplier to cut down the cost of the entire work.
Conclusion
In conclusion, when developing a project an aspect of cost and quality should be considered highly hence enabling an event or activity is completed on time and effectively. However, this project is going to analyze the prevailing activities involves in the development of my friend residential house, in regards to his tight budget that he believes will be able to complete the project effectively and of high quality(Gerry, 32-49).
A project however, should be clearly defined with consistent plans which curb an aspect of failure in the deployment of the project and its span.
This report however, is going to analyze the scope of this project, its objectives, constraints, what the management talks about stakeholder, risk prevailed, resources needed, monitoring activities and schedule as well as the quality of the house that will be in a construction process. This will be covered from the time project starts to its end in regards to my friends given tight budget. The scope of this project will therefore include an aspect of skills behind architectural activities on planning and development of the house, the knowledge of the stakeholders behind the project and the expectations as well as the needs that my friends expect for me to meet to adhere with his budget (Friedman, 84-92).
However, we know that the project will encounter limitations that come around as hindrances due to timeframe and availability of materials that will make this project successful. Also change in the pricing may affect the effective completion of the residential house since this may affect the total budget of the project in regards to additive that prevail a limitation aspect.
Moreover, this project was in line of ensuring that the development of this residential house is completed within a given timeframe. The work therefore is supposed to be completed on time and according to the budget availed by my friend. This however, shows that this activity is affected in many ways. This is through; different Constraints, risks ascertained and evaluation analysis that works hand in hand with the tight budget provided.
References
Alexander, Carol. Risk Management and Analysis, Measuring and Modelling Financial Risk (Wiley Series in Financial Engineering) (Volume 1) [Hardcover]. United Kingdom: Wiley. 1999.
Friedman, Avi. Sustainable Residential Development: Planning and Design for Green Neighborhoods [Paperback]. United Kingdom: McGraw-Hill Professional. 2007.
Ghantt, Thomas. Project Risk Management: Using Failure Mode Effect Analysis for Project Management [Kindle Edition]. USA: Plumbline Publishing Group.2012.
Gerry, Johnson. Exploring strategy text and cases (9th edition). United Kingdom: Prentice hall. 2011
Kerzner, Harold. Project management a system approach to planning scheduling and controlling, (10th edition). USA: Pelican publisher. 2009.
Kerzner, Harold. Project Management: A Systems Approach to Planning, Scheduling, and Controlling [Hardcover]. United Kingdom: Wiley. 2013.
Layton, Mark. Agile Project Management For Dummies [Paperback]. USA: Prentice hall. 2010.
Munoz, Nicole. 7 Figure Marketing Blueprint - Module 9: Strategy Development. New Jersey: Nicole Munoz publisher. 2012.
Pinto, Karin. Project Management: Achieving Competitive Advantage. 2nd Ed. New Jersey: Pearson Education Ltd. 2010.
Sully, Susan. Coming Home: The Southern Vernacular House [Hardcover]. New York: Rizzoli. 2012.
Schmitz, Adrienne. Multifamily Housing Development Handbook (Development Handbook series) [Hardcover]. USA: Urban Land Institute. 2000.
Schwaber, Ken. Agile Project Management with Scrum (Microsoft Professional) [Paperback]. United Kingdom: Microsoft Press.2004.
APPENDIX
WORK BREAKDOWN STRUCTURE
DEVELOPMENT OF RESIDENTIAL HOUSE
Gantt chart
Read
More
Share:
CHECK THESE SAMPLES OF Development of Residential House
However, this changed with the increased pressure to adopt the neo-liberalization economic practices that encouraged privatization of most public corporations and led to the emergence of specialized construction companies, which revolutionized the housing sector and resulted in the development of unique, well-designed, and constructed houses and business premises (Lowe, 2011).... It has been in operation since 1958 and is largely acclaimed with the development of the UK residential property sector (Lowe, 2011)....
The development of West Torrens Council area, as a proposed residential area must be maximized.... The development plan policies would allow the development of the area to have open spaces requirements, parking areas to have a very satisfactory design solutions, and at the same time having financial imperative of maximizing the potential of the site.... 0 metersThe house that faces the east side have a 5.... In order to maintain the character of the house, a single storey dwelling would be perfect for the site character...
With this backdrop, people seek to stay in houses which give them complete residential satisfaction by way of good neighborly relations, peaceful surroundings, serene environment, suitable facilities, and good administration of residential complexes.... When one runs out of residential satisfaction with regard to any of these issues, he or she may opt to move out of it in search of better residential satisfaction.... Depending on individual tastes and preferences, aspirations and satisfaction levels change but most house owners or tenants prefer to seek better houses to get full residential satisfaction in all respects whenever their aspirations are not met within their existing homes....
The idea is to first point out the variables that have a significant relation with the house prices in Hong Kong, so as to certify the actually operating variables behind the same.... The study found that the two prime causes behind rising house prices in the nation were a high per capita income and the high growth in the population of the nation.... The present study deals with the ways that the government of Hong Kong used to revive the private residential housing sector of the nation and the extent to which they attained success in the same....
The rise in sales of the company reflected strong market condition, which in turn contributed towards the development of the economy.... he vision of Barratt Development Plc is to lead in the house building industry by concentrating on The company has its operation in all parts of Britain, where it has established 27 divisions by delivering around 14,838 new homes per year.... lanning regulation and Tax: The supply of the private housing is ascertained with the help of house price along with underlying determinants....
As such, the need to market potential residential properties that can be turned into something that can generate huge income is of primary interest to those involved in the real estate business.... This is due to the fact that the nation exhibits a rapid level of economic growth and its high population will positively impact the residential real estate business.... In the future, this growth will positively impact the residential real estate business....
Examples of residential buildings include single-family houses, multi-family houses, duplex, town houses, condominiums as well as hostels.... Different types of residential buildings 2.... Multi-family homesThese are the least common types of residential buildings; these types of homes are basically a home turned into two or more homes.... Furthermore, the fire behaves differently in relation to the development of a residential building....
This case study "Standards that Regulate Overlooking in residential Areas" sheds some light on the standards that regulate overlooking in residential areas.... Section one does not require a permit, section two requires a permit, and section three prohibits the use of the land for any other use not mentioned in section one or three, the zone in which the proposed housing property is to be developed is in a residential zone.... residential housing development in Victoria is controlled by residential development and provisions tools....
6 Pages(1500 words)Case Study