It recognizes costs, scope of project, quality, risk and human resources to determine whether a project is meeting its intended objectives in these…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER91.5% of users find it useful
Earned Value Management
Read TextPreview

Extract of sample "Earned Value Management"

RUNNING HEADER: Earned Value Management System Earned Value Management System BY YOU YOUR SCHOOL INFO HERE HERE Earned Value Management System The EVMS (Earned Value Management System) is designed to create a window of realistic and legitimate aspects of project management. It recognizes costs, scope of project, quality, risk and human resources to determine whether a project is meeting its intended objectives in these areas. It is usually used in planning, execution and control factors related to the project to determine efficiencies and value of the project and its activities.
EVMS shows status in several different ways. It illustrates the planned value of a project along with the actual costs to determine status, or earned value, of the actual investment (Project Management Institute, 2005). The most vital component of EVMS is recognizing the real time investment occurring within the project compared to planned value and actual cost. This will illustrate whether the project is exceeding costs and whether it is behind schedule.
It is important to recognize that PV is also considered the Budgeted Cost of Work Scheduled, which is imperative for determining earned value. Projects have technical performance aspects (progress) that is related to budget and should be assessed in comparison to actual costs incurred. Planned budget of $180,000 with an actual cost of $200,000 would, without EVMS, be $20,000 over budget. However, EVMS might illustrate that the technical progress started earlier than expected, thus the project is now ahead of schedule and might be more apt to meet PV budget. This is why EVMS is linked directly to cost and performance.
My view is that EVMS is a more practical assessment of a project since it takes more into consideration than just costs. It recognizes expert progress based against time schedules, to make a more accurate assessment of project value or potential losses. It is a viable tool for assessing
projects because it takes time and talent into consideration (Goodpasture, 2004) along with recognition of costs, something needed for strategic project management in order to gain a broader picture of whether the project is meeting its intended budget and progress expectations.
References
Goodpasture, J.C. (2004). Quantitative Methods in Project Management. J. Ross Publishers
pp.172-178.
Project Management Institute. (2005). “Practice Standard for Earned Value Management”.
Retrieved August 21, 2012 from http://www.cflhd.gov/resources/pm/documents/PMHandbook/PMHBLinks/e%20Budgeting/Earned%20Value%20Analysis/EarnedValueMgmt.pdf Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“Earned Value Management Essay Example | Topics and Well Written Essays - 500 words”, n.d.)
Retrieved from https://studentshare.org/management/1601940-earned-value-management
(Earned Value Management Essay Example | Topics and Well Written Essays - 500 Words)
https://studentshare.org/management/1601940-earned-value-management.
“Earned Value Management Essay Example | Topics and Well Written Essays - 500 Words”, n.d. https://studentshare.org/management/1601940-earned-value-management.
  • Cited: 0 times
Comments (0)
Click to create a comment or rate a document

CHECK THESE SAMPLES OF Earned Value Management

Earned Value Management

...?Earned Value Management (EVM) Table of Contents Introduction 3 2.Management of a Project 3 3.Background of Earned Value Management (EVM) 5 4.Role of Earned Value Management (EVM) in Project Management 6 5.Earned Value Management (EVM) Techniques for Project Management 7 11.Conclusion 9 Reference 10 1. Introduction The complexities in the post-modern organisation have increased significantly due to a number of reasons. Globalisation is the prime factor that has caused to bring these...
6 Pages(1500 words)Coursework

Earned Value & Forecasting

...scheduled till the end of period 8 which is equal to $(868,000-955,000) i.e. - $87000. A negative schedule variance here implies that the project is behind schedule by the end of period 8. The Schedule Performance Index (SPI) is given by the ratio of budgeted cost of work performed to the budgeted cost of work scheduled i.e. (868,000/955,000) which is equal to .91. As the Schedule Performance Index is less than 1, it gain implies that the project is behind schedule. Table 1: Calculating Budgeted Cost of Work Performed (BCWP) / Earned Value (EV) Task Budgeted Total cost of each activity Actual Percentage of work completed at end of period 8 Budgeted cost of work performed at end of period 8 1.2.1 200000...
3 Pages(750 words)Essay

Value Management/ Value Engineering

....The system will also improve communications, team and customer relationship (Kendrick 2006, p.246). References Kelly, M. 2002, “Best Value in Construction”, edited by Kelly ,Blackwell publishing: New York,ISBN: 0-632-05611-8 Kendrick, T. 2006, “Results without Authority”, London, AMACOM Div American Mgmt Assn, Norton, B and Elligott,M.,1995, “Value Management in Construction”, Macmillan: London ISBN: 0-333-60626-4 Pinto, K. 2008, “Cost and Value Management in Projects”, John Wiley & Sons: , New York. Sham, D. 2008, “Earned Value Management Using Microsoft Office Project: A Guide for...
8 Pages(2000 words)Assignment

Earned Value Management

...EARNED VALUE MANAGEMENT The purpose of this paper is to provide a general idea of Earned Value Management (EVM). Only conveying a basic understandingof a tool that allows both government and contractor to visualize the technical, cost, schedule planning, performance, and progress of a contract, an agreement or promise to do work, which is enforceable by law. Using examples and expert opinions, this paper will briefly explore the positive and negative aspects of Earned Value Management. Precisely speaking, Earned Value Management is a project management technique for making an educated guess as to how a project is doing in terms of its budget and schedule. It compares the work finished with the estimates made at the beginning... of the...
3 Pages(750 words)Assignment

Management . Hidden value book

...Management Hidden Value Book PSS PSS Introduction PSS Medical is in the distribution of medical supplies which is a highly competitive field. Yet, it has managed to grow and out maneuver other companies in its field.. They have had a 5 year growth rate in revenues of 53% in an environment where normal is 30%. Return on equity, return on assets and profit margin were all more than twice the industry average. Their overall growth rate is 60% per year which is essentially unheard of in the industry. This paper will look at some specific things about this company even though on the surface it appears to be the same. Managing People The difference here begins with the CEO who...
4 Pages(1000 words)Essay

Earned Value Management

...Xxxxxxxxxx Xxxxxxxxxx Xxxxxxxxxxx 29 October Earned Value ManagementCompanies and Organizations throughout the world undertake various types of projects. The projects can vary in size and level of urgency. But it is imperative for any company to expect timely completion of its projects and that too within the budgets allotted. But experience tells us that projects hardly run in a smooth course. There are ups and downs and possibly many vicissitudes before any result is achieved (Wirick, 7). In such a scenario it becomes important to monitor the progress of the project and make corrections whenever necessary. There are various tools to track the progress and efficiency of any project. One of them is...
4 Pages(1000 words)Essay

Earned value management

...Earned Value Management Earned value analysis measures the progress of a project at any given time; it analyzes the budget, forecasts the date of completion and its final cost. It also analyzes variances as the project continues. Earned value analysis gives a comparison between the planned work and what has been completed with an aim of determining if the schedule, cost, and work done are in line with the designed plan. Work is considered to be earned after completion. It is used as a tool of management since it ensures that work is well planned in advance. Earned value management therefore helps one to know whether the cost will be greater or less than the estimate and even the time of completion of the task at hand. Work should... be...
2 Pages(500 words)Coursework

Duchamp, Segal, Rauschenberg, Warhol, Oldenburg, Lichtenstein

4 Pages(1000 words)Assignment

Earned Value Management in Multi-Projects and Programmes

...Earned Value Management in Multi-Projects and Programs Earned Value Management in Multi-Projects and Programs Introduction Earned value management is a technique and project management that measures project performance and how it is progressing in an objective manner. It is also a method that puts together the amounts of the project management triangle. They comprise of schedule, costs and scope. In an integrated system, it is able to provide accurate predictions and data on the problems of project management. This is an essential...
7 Pages(1750 words)Essay

Earned media

...MARKETING ESSAY Earned media are used by a large number of companies to promote their brand. The best and most favorite thing about earned media is that its cost free. Earned media can help promote a project by taking in the most little effort. (Ransom, 2012) There are several ways in which earned media can be used effectively. On Facebook, a page of the product can be made. In this way, people will get to know more about the product and how great it works. Moreover, there can be quizzes functioned by the product. People will find it interesting to share it on their profiles. These quizzes can reflect about their personalities, so their friends will be looking at them...
1 Pages(250 words)Essay
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.

Let us find you another Essay on topic Earned Value Management for FREE!

Contact Us