StudentShare
Contact Us
Sign In / Sign Up for FREE
Search
Go to advanced search...
Free

Gantt Chart and Network Diagram - Essay Example

Cite this document
Summary
In the essay “Gantt Chart and Network Diagram,” the author analyzes effective tools for project management. With the development of software applications such as Microsoft Project, these tools are now in even more widespread use. The project plan in concern uses a Gantt chart to organize the tasks…
Download full paper File format: .doc, available for editing
GRAB THE BEST PAPER93% of users find it useful
Gantt Chart and Network Diagram
Read Text Preview

Extract of sample "Gantt Chart and Network Diagram"

The task assignments have overloaded certain resources. This is because, when setting predecessors, only adjacent tasks have been considered in certain cases. For example, some of the tasks to which the resource named Goran has been allocated on the same day are 75, 76, 109, and 110.

Task 76 has a dependency on task 75 and task 110 has a dependency on task 109. But, because the same resource is involved, there is a dependency between tasks 76 and 109 as well. Ignoring dependencies such as these have resulted in that resource been overloaded. Hence task assignments need to be reworked. The dependencies could be simplified if they were set using the summary task numbers instead of the detailed task numbers. Task 170, 'Test d_contactInfo table' has tasks 109, 110, and 111 as predecessors all of which are subtasks of task 108, the building of that table.

Predecessor could be set as 108, thereby, simplifying dependency management. There are several milestone tasks. They have been used to mark significant tasks which need to be completed before proceeding to later tasks. It is not prudent to deploy the system without validating it in the two migration environments. The validating activities, therefore, are marked as milestones and the Deploy task is set as dependent on the two validation tasks. Network DiagramThe network diagram appears very complex because of the setting of the dependencies to the lower-level tasks.

This complexity can be reduced if the dependencies are set to the higher-level summary tasks. Usually, in MS Project, the tasks that lie on the critical path are highlighted in red color in both Gantt chart and network diagram views. The testing of the dimension and fact tables is critical for the success of the system. Therefore, those testing tasks appear on the critical path, in red color, along with the migration and deploy activities. However, the fact that the critical path does not extend to the beginning of the network diagram should be analyzed carefully.

This could be due to a mistake in the setting of the predecessor activities. This observation is based on the idea that the critical path of a project is the path with the longest duration. Hence, it represents the shortest time in which a project can be completed. (Schwalbe, 2000). What this implies is that in a network diagram the critical path should extend from the beginning till the end of that network. The absence of this property in the critical path indicates the possibility of some missed dependencies.

Overall, it could be stated that the plan has been set up covering the full development cycle with a finer level of task breakdown. However, by doing the simplifications and validations mentioned above it is possible to ensure that the plan is manageable and traceable. (3 resources are shown as overloaded, which should be corrected by resource-leveling.

Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(Gantt Chart and Network Diagram Essay Example | Topics and Well Written Essays - 500 words - StudentShare, n.d.)
Gantt Chart and Network Diagram Essay Example | Topics and Well Written Essays - 500 words - StudentShare. https://studentshare.org/management/1524625-data-warehouse-gantt-chart-and-pert-chart
(Gantt Chart and Network Diagram Essay Example | Topics and Well Written Essays - 500 Words - StudentShare)
Gantt Chart and Network Diagram Essay Example | Topics and Well Written Essays - 500 Words - StudentShare. https://studentshare.org/management/1524625-data-warehouse-gantt-chart-and-pert-chart.
“Gantt Chart and Network Diagram Essay Example | Topics and Well Written Essays - 500 Words - StudentShare”. https://studentshare.org/management/1524625-data-warehouse-gantt-chart-and-pert-chart.
  • Cited: 0 times

CHECK THESE SAMPLES OF Gantt Chart and Network Diagram

Usability Heuristics for User Interface Design

hellip; Because the NWR organization needs the projects related to the network infrastructure on priority and as early as possible, therefore, the project management team should consider the fast-tracking technique to complete the project within time.... This assignment "Usability Heuristics for User Interface Design" discusses several aspects of the final product that would be tested to ensure that the website of the New World Resources website is working properly and finding out the potential bugs on the website....
7 Pages (1750 words) Assignment

Project Development Phase - Jonijanti Ltd, Tibob and Tibob Ltd

10 Pages (2500 words) Essay

Report of Construction Project Network Diagram

network diagram, Activity-on-Arrow method 3.... network diagram analysis 3.... In the context of this report, the project manager of Company A had initiated with his team the use of network diagram in order to acquire an accurate calculation of the whole duration of the project.... Float was also calculated using the network diagram in order to determine the duration of activity delay that the project can permit before the project becomes late....
3 Pages (750 words) Essay

Work Breakdown Structure - Microsoft Project

gantt chart Using Project Libre and Microsoft Project gantt chart is used to present the tasks of the project along with the starting date and the ending date of that particular task (Cleland, and Gareis, 2006).... Modern gantt chart has started to include the predecessor as well that shows the dependency of that particular task.... Both the software Microsoft Project as well as Project Libre allow the users to create the gantt chart....
5 Pages (1250 words) Essay

Program Management Services

ritical Path Method models the activities and events of a project as a network of activities depicted as nodes on the said network.... The longest path in the network is shown as the critical path.... Before working out a CPM network Chart, it is first of all necessary to list out the chronological series of events that are involved in the changing of wheels and has been listed as follows: ...
6 Pages (1500 words) Essay

The Advantages of Gantt Charts over PERT Diagrams

Research indicates that for many years, project networks has been developed using the PERT diagram despite being based on a stochastic process which may lead to inaccurate outcomes (Pinto & Jeffrey, pp 312-314).... However, with the development of Gantt charts, numerous advantages have been derived over the application of a PERT diagram in project scheduling.... This is because Gantt diagram not only provides a link between the activities and project schedule time but also provides an opportunity to now how the activities will be undertaken as well as the actual date when the project will begin till and the time it will be accomplished (Pinto & Jeffrey, pp 312)....
2 Pages (500 words) Assignment

The Unique Aspects of a Persons Behaviour

Leaders are the gifted or chosen individuals whose mandate is to guide groups of people with common goals and resources in the process of achieving their set objectives.... Therefore, the… traits making good leaders are the aspects of leaders' behaviours encompassing the personality, which leads to positive results in groups with resources and common goals....
8 Pages (2000 words) Essay

Difference between Gantt Chart and Network Diagram

This essay discusses Gantt Chart and Network Diagram which critical tools in project management.... The gantt chart is a graphical illustration of the calendar of events (activities) relating to the project.... They are used to schedule the activities to be performed....
5 Pages (1250 words) Assignment
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Contact Us