The writer of the paper “Building of Recreational Vehicle” states that the physical and developmental projects are executed with the utilization of necessary raw materials with the combination of human resources and financial inputs. Project planning is an essential component for the start of the project…
Download full paper File format: .doc, available for editing
GRAB THE BEST PAPER97.2% of users find it useful

Extract of sample "Building of Recreational Vehicle"

Title: Project Management - Case study number 2 Name: ID: Dated: May 31, 2009. Executive summary: The project is designed to build a Recreational Vehicle (RV) and a boat garage on the property of Mr. and Mrs. David Laurence with a total cost of £37,000 in duration of 120 days. The successful execution of the project will result in the creation of Recreational Vehicle (RV) as in compliance with the new city ordinance regarding the RV and boat parking. The designing of the product is with the help of prefabricated parts as per international standard in the existing home. The other utilities are already present at the project's sight; therefore, the same will be used in the project for the synthesis of major deliverables as in the shape of garage structure and all other physical attached components. The project will start as on May 20, 2009 and will be completed in a short period of four months. The activities of the project are formulated in the shape of Gnat Chart and their review will be accomplished as in accordance with the activity-on-node technique basis. All the sub-activities as designed for the completion of the project will be reviewed as on regular basis and all the activities are expected to deliver their due share for the timely completion of the project. The review and analysis of the project will serve as a guiding principle for making necessary amendments in the activities chart as designed for the project will help in the execution of the project as on regular basis. Work break down structure is designed exactly for 120 days or 17 weeks and the execution with the adoption of critical are the key elements which played a significant role in the completion of the project within the given time period. The activities as formulated for the execution of the project are completed with the utilization of the required inputs as on optimum basis and with the involvement of the managerial skills, the desired results will be achieved as in the shape of physical structures for the project. Introduction: The developmental projects are executed with the utilization of four major types of the resources as are used as input for the completion of the project within a given time period. These four major types include human resources as in the shape of project manager, technical personals and other allied human resources for the completion of the tasks, technical resources as in the shape of tools, instruments and moulds, financial resources as in the shape of money and the system along with necessary rules and regulations for the successful completion of the project. The project as to establish a Recreational Vehicle and boat garage on the property of Mr. and Mrs. David Laurence is executed in compliance with the new city ordinance regarding RV and boat parking the execution of the project will exactly be in accordance with the physical dimensions as per the relevant provisions of the city ordinance and to deliver the product in a timely manner. The project will be completed with in the financial limit as £37,000 and in the given time period that is 4 months from the starting data as May 20, 2009. The project is divided into 7 major components as project planning selection of the site work and laying down the foundation, framing, exterior dimensions, interior dimensions, ground work as to install the components and finally submission of the project document along with the necessary material for its acceptance by the concerned city department. The execution of the project will be completed with the observance of the critical path analysis, designing of the activities as on the basis of Gnat chart, monitoring and review and finally, the preparation of a report to the concerned authorities for its final approval. The project will be monitored as on the basis of the Gnat chart and with the help of the completed tasks as on regular and weekly basis. Any deviation from the approved activity chart will be reported to the top management for its rectification and necessary amendments in the overall execution plan of the project. The project will deliver its output within the stipulated timeframe and the project will also serve as a prototype for its replication in future, too. Work Breakdown Structure: The project for the construction of a Recreational Vehicle (RV) and a boat garage is consisting of the following key components; the names of the components along with their duration are as under: Serial # Component/ Activity Duration a. Planning and preparation of the project document along with the selection of project team 2 weeks b. The execution of the project at the site of the project 2 weeks c. Framing 3 weeks d. Exterior framing 4 weeks e. Interior framing 4 weeks f. Ground work 4 weeks g. Preparation of the final report and its submission to the concerned authorities and acceptance of the report 3 weeks Critical pathway analysis: The project as designed for the construction of a Recreational Vehicle along with the boat garage will be completed with the observance of the following critical pathway: The details of the work based structures along with their durations are the same as given in the above table. The project will follow a critical pathway as indicated with the help of the arrows starting from "a" and ending at "g". Each step will serve as a mile stone and will be used during the review and analysis of the project. Any deviation will be checked and rectified as on timely basis. Gnat Chart: The project will be executed in a total 17 weeks duration starting from May 20, 2009 and will end on September 17, 2009 with the help of the following Gnat Chart. All the activities will be performed on weekly basis with the utilization of available resources both financial and human and at any cost the project will not exceed the prescribed limits as in terms of finances as well as the time limits. All the necessary physical structures including doors and windows with all other accessories will be installed for the successful implementation of the project. The detailed activities are given in the above table and the Gnat Chart for the project is as under with the activity number "d" and "e" will be executed as on simultaneous basis and all other activities will move in dove tailed manner. The chart is as under: weeks activity a activity b activity c activity d activity e activity f Activity g 1   2   3   4   5   6   7   8     9     10     11     12   13   14   15     16   17   Comments: The project for the construction of a Recreational Vehicle along with a garage boat is constructed as a legal requirement as enforced by the relevant city department. The construction will be completed under the supervision of a project manager who will be the focus person for the project and will serve as a bridge between the top management and the executing team for the project. Observance of the physical dimensions along with the utilization of all necessary inputs will be installed as per work based structure for the project and the conclusion of the given period that is 4 months; the project will be in a position to deliver its deliverables as in an effective manner. Conclusion: The physical and de3velopmental projects are executed with the utilization of necessary raw materials with the combination of human resources and financial inputs. Project planning with all its details is an essential component for the start of the project. Work based structure and Gnat Chart are the essential component for the analysis and review of the project. Timely completion of all the tasks will result in the delivery of the deliverables as required in the project. The development of a Recreational Vehicle with boat garage will be constructed as through the implementation of the work based structure and with the utilization of the necessary financial tools and completion of the project within the given time period will serve as a signal that all the estimates were calculated with pre size configurations and with all the relevant data for their utilization in the project. References: 1. Harold Kerzner (2003). Project Management: A Systems Approach to Planning, Scheduling, and Controlling (8th Ed. Ed.) Wiley. ISBN 0-471-22577-0. 2. Richard H. Thayer, Edward Yourdon (2000). Software Engineering Project Management (2nd Ed. Ed.). Wiley-IEEE Computer Society Press. ISBN 0-8186-8000-8. 3. Fleming, Quentin (2005). Earned Value Project Management (Third Edition Ed.). Project Management Institute. ISBN 1-930699-89-1. Appendix A – Work Breakdown Structure WBS list for the Lawrence RV Garage project is reported bellow. Use MS Project to create a Task Sheet. WBS Task name 0 Laurence recreational vehicle garage 1 Project management 1.1 Finalise plans and develop estimates 1.2 Sign contract and notice to proceed 1.3 Apply for permits 1.4 Execute and control project 1.4.1 Track progress 1.4.2 Weekly status meeting 2 Site work and foundation 2.1 Clear and grub lot 2.2 Install temporary power service 2.3 Install underground utilities 2.4 Excavate for foundations 2.5 Install forms and rebar 2.6 Pour concrete for foundation and slab 2.7 Cure concrete 2.8 Strip forms 2.9 Perform foundation / slab inspection 2.99 Foundation complete 3 Framing 3.1 Install mudsills 3.2 Frame walls 3.3 Frame corners 3.4 Install roof trusses 3.5 Complete roof framing 3.6 Conduct framing inspection 3.99 Framing Complete 4 Exterior 4.1 Install wall sheathing 4.2 Install roof decking 4.3 Install felt, flashing and shingles 4.4 Hang exterior doors 4.5 Install windows 4.6 Wrap exterior 4.7 Apply brown coat 4.8 Cure brown coat 7 days 4.9 Apply finish coat 4.99 Exterior complete 5 Interior 5.1 Finish rough-in plumbing 5.2 Rough-in electrical 5.3 Rough-in HVAC 5.4 Rough-in communication (phone, cable, computer, alarm) 5.5 Utility inspections 5.6 Place wall insulation 5.7 Place ceiling insulation 5.8 Install drywall on walls 5.9 Install drywall on ceilings 5.10 Tape and float drywall 5.11 Prime all wall and ceilings 5.12 Paint all walls and ceilings 5.13 Install bath and storage cabinets 5.14 Complete plumbing 5.15 Complete electrical 5.16 Complete communication (phone, cable, computer, alarm) 5.17 Complete HVAC 5.99 Interior complete 6 Ground work 6.1 Grade for driveway and sidewalk 6.2 Setup driveway and sidewalk forms 6.3 Lay out driveway rebar 6.4 Pour concrete driveway and sidewalks 6.5 Cure concrete 6.6 Remove forms 6.99 Ground complete 7 Final acceptance 7.1 Complete final inspection for certificate of occupancy 7.2 Cleanup for occupancy 7.3 Perform final walk-through inspection 7.4 Complete punch list items 7.99 Project complete Read More

CHECK THESE SAMPLES OF Building of Recreational Vehicle

Yamaha Business Strategy Analysis

However, the units of musical instruments and vehicle engines each have specific qualities that provide a different level of growth within the company.... Two of the segments which define this are the musical instruments and the vehicle engines that are defined by Yamaha.... The components that are a part of the Yamaha segments will then be defined with strategies which should be approached to ensure continuous growth and success within the company while ensuring that there is the ability to create a stronger development of the musical products and the vehicle engines....
41 Pages (10250 words) Research Paper

Social and Physical Benefits of Parks and Recreation Space

Research Questions This study was aimed at answering the following questions; 1) What is the role of recreational parks in urban neighborhoods in the area of study?... 2) Is there optimum utilization of recreational parks in the area?... r, is not always the case in the country because many parks continue to suffer from lack of essential recreational facilities or over-emphasis on the natural environment at the expense of modern park facilities for sports and other modern forms of recreation (Godbey et al....
23 Pages (5750 words) Research Paper

Unmanned aerial vehicls

A smaller robotic UAV known as micro aerial vehicle (MAV) is now popularly used because of the low-cost in building and the variety of uses they can be applied, from military to civil applications.... Unmanned aerial vehicles act like ‘homing pigeons' where they are designed to perform certain tasks and come back to their homes at a specified time....
6 Pages (1500 words) Essay

Economics of Policy Issues

The author of the paper titled the "Economics of Policy Issues" proves when road pricing is implemented, the prices for road users will go up.... Hence, fewer people will use the road, which in turn will reduce traffic congestion and other road problems.... .... ... ... Apart from the taxes, people should also be made aware of the traffic congestion and its solutions by airing public service ads on TV and radio networks....
16 Pages (4000 words) Essay

Differences between Office Building and Supermarket Building

Access to supermarket parking spaces should make it easy to unload and load goods to and from the vehicle.... The load-bearing capacity of large supermarkets may be similar to office buildings if the latter includes vehicle parking as part of its substructure.... In the essay 'Differences between Office building and Supermarket building,' the author looks at a building's function, which strongly influences its design and construction....
4 Pages (1000 words) Essay

Modern City Planning

This report "Modern City Planning" presents modern city planning that has transformed the physical and feel of cities around the globe.... This is because it has helped decongest cities, which has eased the flow of traffic in the cities.... It has helped in ensuring that there are enough social amenities....
5 Pages (1250 words) Report

Creating a Public Recreation Program

he quality and importance of recreational instruments should rely on the impact these recreational programs make on the community and its participants and also on the level of their satisfaction with such recreation possibilities (Milton & Patton, 2011).... to different recreational opportunities that should be provided by the local and state powers (Oregon State University, 2010).... However, due to different obstacles, such as the fiscal restraints of local and state authorities, people are not able to use recreational possibilities and feel positive physical benefits for them....
8 Pages (2000 words) Essay

Camp Mountain Eco-Retirement Centre - Concept Planning

?? building communities that encourage interaction and support among residents and businesses.... ?? Adopting eco-friendly designs and choosing appropriate building materials, with an emphasis on recycling and on reducing energy costs (Queensland Government.... The paper 'Camp Mountain Eco-Retirement Centre - Concept Planning" is a good example of a management case study....
16 Pages (4000 words) Case Study
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Contact Us