Each activity requires more time for its better execution. So I did not recommend cutting down the project execution time to some small deadline. But there are only two activities from which cut few time, these are Produce technical manuals and Train sales representatives. By cutting down the time of each we can have 7 days from Produce technical manuals, and 3 days from Train sales representative’s activity. So we have saved 10 days. Overall project duration 1 year and 2 months approximately and we have save 10 days.
The main areas of concentration in this project as I have accessed are the analyses of the currently available model, electrical, hardware and software Design. The development of the efficient marketing plan is also area of concentration. In this report I have discussed the main project activities regarding the marketing of new project of computer development. I have discussed the project management activities like WBS, OBS and CPA. I have tried to make this project plan in such a way that it becomes a