Nobody downloaded yet

When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an - Essay Example

Comments (0) Cite this document
Summary to essay on topic "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an"
What is important is that there is a meeting of the minds between the parties. Nevertheless, since the memory of man cannot be trusted or relied upon at all times, there are instances when contracts have to be in writing in order for the…
Download full paper
When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an
Read TextPreview

Extract of essay "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an"

Download file "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an" to see previous pages... [internet]). The compulsion for contracts to be in documented properly s more imperative in construction agreements because these usually involve significant or huge amounts of money, not to mention the usually lengthy period of construction and the efforts of all those involved in the project. Furthermore,
Let us write or edit the essay on your topic "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an" with a personal 20% discount.. Try it now
construction covenants normally have a lot of regularly common details that include specifications on materials, labor, time-frame from commencement to completion to turn-over or delivery, penalties in case of delay, stipulations regarding defects in construction or inferior quality in the works undertaken and on so many other aspects for which the terms and conditions must be meticulously addressed and monitored. It will be disastrous if the mistakes or flaws are discovered when the building has already started to rise and the concrete elements have already dried.
It may be noted though that even if no contract yet has been finalized for a building project, the builder and the client normally do some preparatory and preliminary transactions which already entail some jobs and some funds. While these initial steps do not yet constitute the whole terms and conditions of the entire formality, the petty inter-actions are enough evidence of the business relation between and among all the persons and entities concerned. Necessarily and as a matter of course, once the ultimate contract is perfected and consummated, these small pieces of complements can be incorporated therein or can be construed as being so incorporated. There are also incidents in which a letter of intent is first transmitted by one party to the other which serves as a proposal. Certain types of letters of intent have an accompanying acceptance or approval caption and blank space where the addressee may affix his signature which act is deemed as a badge of absolute and unconditional approval to everything that is set forth. The offer made in a letter of intent may also be ...Download file "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an" to see next pagesRead More
Cite this document "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an"
  • APA
  • MLA
  • CHICAGO
(“When work on a construction site has started long before a formal Essay”, n.d.)
When work on a construction site has started long before a formal Essay. Retrieved from https://studentshare.org/miscellaneous/1559921-when-work-on-a-construction-site-has-started-long-before-a-formal-contract-has-been-drawn-up-and-signed-the-parties-may-have-made-an-agreement-to-negotiate-or-the-employer-or-architect-may-have-written-a-letter-of-intent-to-the-contractor-explore-an
(When Work on a Construction Site Has Started Long before a Formal Essay)
When Work on a Construction Site Has Started Long before a Formal Essay. https://studentshare.org/miscellaneous/1559921-when-work-on-a-construction-site-has-started-long-before-a-formal-contract-has-been-drawn-up-and-signed-the-parties-may-have-made-an-agreement-to-negotiate-or-the-employer-or-architect-may-have-written-a-letter-of-intent-to-the-contractor-explore-an.
“When Work on a Construction Site Has Started Long before a Formal Essay”, n.d. https://studentshare.org/miscellaneous/1559921-when-work-on-a-construction-site-has-started-long-before-a-formal-contract-has-been-drawn-up-and-signed-the-parties-may-have-made-an-agreement-to-negotiate-or-the-employer-or-architect-may-have-written-a-letter-of-intent-to-the-contractor-explore-an.
  • Cited: 0 times
Comments (0)
Click to create a comment or rate a document
CHECK THESE SAMPLES - THEY ALSO FIT YOUR TOPIC "When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an"
Construction Delay Claims : How a Contractor can effectively achieve an extension of time or schedule adjustment for Employer/
or 2.9 Chapter Closing Comments CHAPTER 3 – TYPES OF DELAY AND DELAY ANALYSIS 3.1 Background 3.2 Significance of Delay Analysis 3.3 Types of Delay 3.3.1 Critical VS non-critical 3.3.2 Excusable versus non-excusable delay 3.3.3 Compensable versus Non-compensable delays   3.3.4 Concurrent delays 3.4 Measuring Delays with the help of Schedules 3.4.1 Measuring Delay with Contemporaneous Schedule 3.4.2 Measuring Delay with As-planned schedule 3.4.3 Measuring Delay with As-Built Information Schedule 3.4.4 Measuring Delay with Critical Path Method Schedule  3.5 Measuring Delay Using No Schedules 3.5.1 Use of Contemporaneous Documents for Sequence and Timing 3.6 Chapter Closing Comments CHAPTER
48 Pages(12000 words)Essay
Letters of Intent
Letters of intent are mainly used by the construction industry parties who may be under pressure to commence the preparatory works before a formal contract is established. For instance, the letter of intent may instruct the subcontractors to initiate the design process while waiting the signing of the legal contract documents.
8 Pages(2000 words)Essay
Pagiarism and Paraphrasing
A student may be considered to have plagiarized a scholarly work under three major circumstances with the first one being the direct transfer of passages into the student’s work without proper acknowledgment. Additionally, a student may plagiarize someone’s work by using ideas and opinions of another person’s without adequate acknowledgment.
5 Pages(1000 words)Essay
Liabilities of Contractor, Employer
In this case the repudiation of sub contract, the stopping of work by the contractor and termination of the contract by the employer were mentioned. Having a overall view of the situation, it seems that M is liable to E. Various laws regarding the contract and termination must be discussed before deciding the liability.
10 Pages(2500 words)Essay
Formal letter to prospective employer
The duties outlined in your Job Description offer me an opportunity both to utilise my skills gained on my course and in previous work experience, and to exapnd my field of expertises. I am interested in the research, design and promotion aspects, and in the chance to gain a further qualification.
3 Pages(750 words)Essay
Construction Management 'Contract Law'
Every contract has its own complexity in the agenda. The contract under current consideration much more so and has its own complexities. In order to understand and to clearly ensure that either of the parties have understood the complexities involved it is essential that a contract is drawn.
16 Pages(4000 words)Essay
Construction Contract Administration and Law
But the circumstances like this may arise and the legal system recognizes and guarantees remedies. The only thing is that situations like this may cause problems in the functioning of the University. If the contractor appointed by the University, fails to act as per the requisites or requirements of the University, the University will have to first intimate him as to the deviations against the agreement.
8 Pages(2000 words)Essay
Construction contracts
In terms of risk assessment, the NEC3 details the risks the Employer must assume and the FIDIC provides clarity in the form of risk prevention. Both the NEC3 and the FIDIC clarify the obligations of both the Employer and the Contractor
6 Pages(1500 words)Essay
Construction contract
According to the construction Act, ownership of the material transfers to the employer the moment those materials becomes part of the building, even if the employer had not completed the payment. Contractors are therefore encouraged to have a legal retention of title
3 Pages(750 words)Essay
Construction contract
These documents are legally drafted containing of the duties being carried out by the contractor and the employer. In other words, NEC is a branch of contracts that assists the implementation of sound project management principles along with defining legal relationships. It
10 Pages(2500 words)Essay
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Let us find you another Essay on topic When work on a construction site has started long before a formal contract has been drawn up and signed, the parties may have made an agreement to negotiate; or the employer or architect may have written a letter of intent to the contractor. Explore an for FREE!
Contact us:
+16312120006
Contact Us Now
FREE Mobile Apps:
  • About StudentShare
  • Testimonials
  • FAQ
  • Blog
  • Free Essays
  • New Essays
  • Essays
  • Miscellaneous
  • The Newest Essay Topics
  • Index samples by all dates
Join us:
Contact Us