The paper "Redevelopment of a Small Town and Facilities " is an outstanding example of a management research proposal. In the current times, most towns are striving to be self-sufficient in all their activities. That is done in an attempt to ensure that the town gains revenue from the tax gained from the local businesses…
Download full paperFile format: .doc, available for editing
Extract of sample "Redevelopment of a Small Town and Facilities"
Redevelopment of a small town and facilities Project framework Project Project management: redevelopment of a small town and facilities
Project description
The aim of the project is to develop a small town including its facilities. The redevelopment will aim at ensuring that the small town become self sustain in utilizing its resources and not depending on other towns in terms of technology and infrastructure.
Begin Date:
1st June 2014
End date
30th May 2015
Project content
The aim of the project is to redevelop the town and make it to have a brand new image
Deliverables and criteria for close out
Proper infrastructure, proper technological distribution, development of distribution channels for raw materials, and other required goods.
Project limits and exclusions
Time and availability of funds will be the limiting factors
Milestones:
Date
Key deliverables
01/06/2014- 30/06/2014
Formulation of a plan that will be utilized over the one year of redevelopment of the town. That will ensure that all factors are put into consideration.
01/07/2014- 31/07/2014
Formulation of a budget. The budget will ensure that there are enough funds for taking up the task of redevelopment.
01/08/2014-31/08/2014
Seeking of donors. The management of the small will look for donors who will help in the funding of the project. The donations should come from both the government and private businesses.
01/09/2014-30/09/2014
Floating of tenders. Tenders should be floated for the different activities that are intended to take place. Floating of the tenders will ensure that the town acquires the best experts at the lowest cost and best terms. After the bidding of the tenders, there should be vetting of the companies placing the tenders and that will lead to the awarding of the tenders to the best-suited company.
01/10/2014-28/02/2015
The companies that have been awarded the tenders should start working. The duration will ensure that there is a proper infrastructure, security system, up to date technological devises, and a proper supply chain system.
01/03/2015-30/04/2015
Carry out of an advertising campaign that is aimed at attracting investors. The investors will be asked to invest in the town by coming up with businesses that will lead to the development of the town. The advert will be followed by vetting of the investors to ensure that they are qualified, they have the required funds to invest in the town, and that they are willing to comply with the set rules of the town.
01/31/2015-30/05/2015
Evaluation of the progress of the project.
Project overview
In the current times, most towns are striving to be self sufficient in all its activities. That is done in an attempt to ensure that the town gains revenue from the tax gained from the local businesses. The residents of a town also prefer getting all their requirements in one area as opposed to shopping for different items in different towns. Because of that, most towns are aiming at developing their towns in a manner that will ensure that they are self-sufficient and a manner that will attract investors in the town. That will ensure that local residents will be more comfortable and the town will earn more revenue from its activities. That will enable the town to properly remunerate its staff and carry out other development projects. The project is about redeveloping a small town and its available facilities. The project will aim at ensuring that the infrastructure of the town is up to the required standards. That ensures that the transport system in the town will not hold back any possible investments. The project also aims at improving the technological level of the town. Technology will ensure efficiency of operations in the town. In that case, technological advancement is a necessity in the advancement of the town’s infrastructure. Since the project is on redevelopment of the town, it will take one year after which the rest of the developments will be left to the investors to carry out the rest of the developments.
Statement of scope for the project
Project objectives
The project on town redevelopment has a number of objectives. The objectives include the following;
1. To set up a technologically recognized town. The small town will be developed in a way that all the systems depend on technology. That will ensure that there is cost cutting those results from the use of technology.
2. To build a proper infrastructure system. The projects aim at ensuring that the town is served by a modern infrastructure system. The system will ensure that the exchange of goods and services is easy and convenient. That will also ensure that costs of moving goods is reduced and the companies in the town will be able to manage the costs.
3. To build the town to become a commercial zone. The redevelopment of the town will attract investors. That will ensure that people in the town earn employment opportunities from the local businesses and that will boost the economy of the town and the standard of living of the people found in the town.
Deliverables
In order to accomplish the set objectives, there has to be proper coordination of the various activities that are supposed to take place before the project becomes successful. The management of the town must ensure that they get donors who will be able to properly and conveniently make donations that will ensure that the objectives of the project are gained. That means that there has to be negotiations made with the donors. The negotiations will ensure that the town gets donors who are willing to see through the project. The management of the town should also ensure that they are able to get the best deals from the contractors. The contractor with the best deal should be awarded the contract. The terms will imply the convenience of working in the town in terms of compliance with the set rules on pollution and the payment period. The repayment period asked by the contractor should be convenient to the town’s management. The other deliverable is on the seeking of investors. The people or companies that are willing to invest in the town should be credible institutions that are interested in the well being of the town and the accomplishment of the long run good of the town which is to come up with a self sustained small town.
Milestones
The project will take place over a period of one year. After the one year, the other objectives of the town will be achieved by the work of the investors. The aim of the project is to come up with a concrete foundation that will enable the town to become self sustained. The activities are as shown below in table 1
Table 1: Project milestones
Date
Key deliverables
01/06/2014- 30/06/2014
Formulation of a plan that will be utilized over the one year of redevelopment of the town. That will ensure that all factors are put into consideration.
01/07/2014- 31/07/2014
Formulation of a budget. The budget will ensure that there are enough funds for taking up the task of redevelopment.
01/08/2014-31/08/2014
Seeking of donors. The, management of the small will look for donors who will help in the funding of the project. The donations should come from both the government and private businesses.
01/09/2014-30/09/2014
Floating of tenders. Tenders should be floated for the different activities that are intended to take place. Floating of the tenders will ensure that the town acquires the best experts at the lowest cost and best terms. After the bidding of the tenders, there should be vetting of the companies placing the tenders and that will lead to the awarding of the tenders to the best-suited company.
01/10/2014-28/02/2015
The companies that have been awarded the tenders should start working. The duration will ensure that there is a proper infrastructure, security system, up to date technological devises, and a proper supply chain system.
01/03/2015-30/04/2015
Carry out of an advertising campaign that is aimed at attracting investors. The investors will be asked to invest in the town by coming up with businesses that will lead to the development of the town. The advert will be followed by vetting of the investors to ensure that they are qualified, they have the required funds to invest in the town, and that they are willing to comply with the set rules of the town.
01/31/2015-30/05/2015
Evaluation of the progress of the project.
Technical requirements
The project will require the availability of contract agreements. The agreements will be between the town and the donors, contractors and investors. The contacts should be fair to ensure that there is no party that is affected by the terms of the contract unfairly. The other technical requirement is on establishing the technological platform. That will require the use of the internet and other modern methods of communications. Investment in technology will be a requirement that will ensure that the objectives of the project are achieved. The employees who will take part in the project will be fully competent to ensure that they give the best output that will make the objectives of the project feasible.
Limits and exclusions
The success of the project will be limited on the availability of funds. The funds from the donors will be the beginning of the success of the project. After the availability of the funds, the other limitation will be subject to the working of the employees. That means that the involved companies should ensure that the employees are properly motivated so that they can work efficiently. That means that there should be no conflicts among the employees and that will increase the level of efficiency of the employees. The working hours should be properly stated to ensure that the project moves according to the set time duration without any delays (Whitten, N. 2005).
Constraints and Priorities
Scope
The fist constraint is on the scope of the project. This is because the different projects activities are dependent on each other. That means that the success of a project is subject to the success of the previous activity. That means that the project managers should ensure that all activities in the project are successful so as to ensure that the entire project is successful.
Time
The project has been set on a one-year’s duration. That means that time is a limiting factor for the project. The contractors do not have luxury of time and all the set activities have to be carried out within the stipulated time period without any delays (Wood, et al 2005). The completion of the various activities before the set time is the best option because the other activities can take place without any hurry.
Costs
The cost of the various activities is also a limiting factor. This is because the set budget is subject of the current prices. That means that in case of any inflationary effects, the budget will increase and that may lead to the fall of the project. The costs should also be observed because the success of the project is subject of the availability of the funds from the donors. That means that the availability of funds will ensure the success of the project.
Quality
Quality of the work done by the contractors will determine the demand from the investors. The investors are the people who will bring money to the town. Therefore, the quality of work done should be perfect so as to attract a large number of investors. Most investors are usually after towns that have a potential of growth and they have good facilities that will help in the running of their activities. That means that the contractors should be professionals who should ensure quality of work done.
Priorities of the project
The priorities of the project are the activities that the project cannot become successful without their accomplishment. One of the priorities includes the availability of the funds. The project is very dependent on the availability of funds from the donors. That means that the project managers should make negotiations with the donors that will make them confident about the project and that will ensure that the project becomes successful. The other priority in the project is the utilization of time. Time is a factor that should be perfectly utilized to avoid any delays. The other priority is the quality of work done. The given priorities should be perfectly coordinated to ensure the success of the project.
Performance measurement evaluation
The project managers should ensure that evaluation of the project’s progress is carried out periodically (Fishman 1997).That will ensure that there is no overload of work that has not been carried out at the end of the contract. At the end of the project, the periodical evaluations should be compiled and that will yield to the final result of the evaluation. The evaluation should cater for factors such as the way the activities are coordinated and the quality of work done by the different contractors. The project manager should evaluate the various activities and make a comment on each of the projects. The evaluation will ensure that all the activities are properly executed and implemented. The evaluation should ensure that the contractors make a follow up on the various activities to ensure that all things are working perfectly.
Project closure
The closure of the project will be when the investors have been allocated with their various portions. That will happen when the project is finally handed to the investors from the project managers. The work of the investors will to ensure the achievement of the objective of making the town self sustained.
Bibliography
Fishman, C. 1997. “They Write the Right Stuff.” Fast Company. ..
Garmus, David, with David Herron. 1996. Measuring the Software Process: A Practical Guide to Functional Measurements. Upper Saddle River, NJ: Prentice-Hall Inc.
Gibbs, W. 2001. Taking Computers to Task Englewood Cliffs, NJ: Prentice-Hall.
Humphrey, W. 1999. Managing the Software Process. Addison-Wesley.
Johnson, J. 2002. Program Smarter, Not Harder: Get Mission-Critical Projects Right the First Time. New York, NY:McGraw-Hill, Inc.
Kendall, K. 1999. Systems Analysis and Design. Englewood Cliffs, NJ: Prentice Hall.
Purba, S. 2003. How to Manage a Successful Software Project: Methodologies, Techniques, Tools. New York: John Wiley.
Whitten, J. 2001. Systems Analysis and Design Methods. St. Louis: Times Mirror/Mosby College Publishing.
Whitten, N. 2005. Managing Software Development Projects.New York: John Wiley & Sons, inc.
Wood, Jane, with Denise Silver. 2005. Joint Application Development. New York, NY: John Wiley & Sons, Inc.
Read
More
Share:
CHECK THESE SAMPLES OF Redevelopment of a Small Town and Facilities
ral barriers to existing facilities, which must be “readily accessible” – that is, businesses must determine whether it could fulfill such removals given the project costs.... This is also in anticipation of the friction that might occur between advancing the rights of persons with disabilities and furthering the profit-making potential of business entities (ADA Update: A Primer for small Business 9).... This implies that small businesses which could not easily afford the requirements of the law may choose to adjust the dimensions depending on the size and floor area of its building, with the help of reliable civil engineers....
Other coastal countries and regions to which Namibia provides its transport facilities for business purposes include the region of Gauteng in South Africa; the Kunene and Cuando provinces in Angola; the Katanga province and Lubumbashi town in Congo.... Currently, Namibian transport sector faces challenges related to the “expansion, modernization, upgrading and maintenance of road, rail, air and maritime transport facilities”, affirms the National Planning Commission, Namibia (2004, p....
This small town, however, is tucked away from the glaring eyes of the world.... The facilities in the town have to grow proportionately to accommodate the increased population that would inhabit the town.... The author of this case study entitled "The Rhossili town Development" touches upon the enabling of the Rhossili town Council to develop Rhossili, rated as one the most beautiful places on earth, to one of the most desired tourist destinations in the world....
The clinic is a small one, with 15 rooms.... a small Persian woman, Judith, gave me a short tour around the clinic.... This term paper "Rehab facilities" is about the atmosphere of the rehabilitation center is so clean that the smell of the cleaning solution would remind one of a hospital....
The paper aims at elaborating the memorandum so as to quell any future conflicts that may arise from within all the quarters that access these facilities.... Both the facilities run a parallel program and they, therefore, are not competitions for each other.... The facilities manager is one of the key creations of memorandum.... It is understood that the two facilities exist independently yet mutually share the stated resources....
This paper provides an overview of the 8(a) program that specifically targets socially disadvantaged entrepreneurs running small businesses.... has, since a long time, actively promoted the socio-economic welfare of small businesses.... It is for this particular reason that the small Business Administration (SBA) was founded to ensure that small businesses have the business acumen and resources to survive and grow in the competitive marketplace....
Finally, it is believed that there would be greater demand for these kinds of activities in the future, given the fact that these provide all-around benefits and facilities in the United Kingdom.... The study examines the situation in the burgeoning dual use leisure facilities market in the United Kingdom, utilizing the locality area of Oxford-shire as an example.... This literature review focuses on the concept of dual-use leisure facilities in the UK and the effectiveness of the dual use of leisure facilities in the UK....
It is set to offer hotel and accommodation facilities to the tourists visiting Kenya.... It is set to offer hotel and accommodation facilities to the tourists visiting Kenya.... It is set to offer hotel and accommodation facilities to the tourists visiting Kenya.... The paper 'small Business Management - Kenya Hotels Ventures " is a good example of a management case study.... The paper 'small Business Management - Kenya Hotels Ventures " is a good example of a management case study....
12 Pages(3000 words)Case Study