Nobody downloaded yet

SIM335 Managing Projects - Essay Example

Comments (0) Cite this document
Summary
Task 1: Question 1: The network diagram for the activities involved in order to manufacture some of the new varieties of desired products will be given in the following figures: Question 2: The timing of all the activities is dependent upon which path is adopted by the engineers from the prescribed network diagram…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER92.6% of users find it useful
SIM335 Managing Projects
Read TextPreview

Extract of sample "SIM335 Managing Projects"

Download file to see previous pages The direct relationship between the activities was found where ‘Finish to Start’ approach was adopted as per the requirements mentioned before the diagram was to be designed. Determining the total float on the other end means the total amount of time for which the task can be delayed and which does not negatively affect the project whatsoever the conditions are. The formula for the total float is given as follows: Total Float = Late Start – Early Start This means that subtracting the time of the activity which was recorded in case of the early start as well as the late start will provide us the total float that can be recorded in the activities undergoing, but that will not affect the process in negative way. Question 3: The duration of the project as well as the critical path are related to each other in an important sense, i.e. the shortest duration of time that is needed to finish all activities in a task to enhance the efficiency scale. According to the network diagram given above, the shortest duration of the project will be 72 days, and therefore that will be defining the critical path. The critical path of the diagram will not be an easy task as the whole task is based on the ES and EF basis except two points, i.e. end of activity 2 and end of activity 8. The critical path will follow the track from A > F > G > H > I > K > L > M > N > O > P > Q. Question 4: The critical path shows it will take 72 days for the task to complete, and that is shortest possible time in which a process can complete. Now if the project will start on 16th January, 2012, on Monday, then it will take 14 weeks and 2 days in the completion of the project. Calculating weeks from the starting date, the project must end on the second day, i.e. Tuesday of the 15th week after the project has started on 16th January. The second day of 15th week becomes Tuesday 1st May, 2012. This will be the earliest date when the project will be completed. Question 5: If activity B delays for 2 days then that will not make any change in to the final duration of the project, as activity B and F are going on the same time period, rather activity F is going on for 4 more days than the activity B and also activity F is included in the critical path and therefore there will not be any effect on the duration of the project. The delay of 2 days in activity P will straightaway affect the whole duration of the project because it is directly dependent as well as independent activity and any change in duration of this activity will change the duration of the whole project. Therefore, this will result in the delay of 2 days in the duration of project and now it will take total 74 days to complete the project, and it will now finish on Thursday 3 May, 2012. The delay in activity O of 1 day will also follow the same case as was happened in activity P case, but with 1 day delay in the project completion. Therefore the project will now be over on 2nd May, 2012 on Wednesday. Question 6: The main limitations in the network diagram are as follows: The toolbar cannot help the elements to be created through the use of dragging and dropping. It is not possible to transfer the elements to the work management view from the ...Download file to see next pagesRead More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“SIM335 Managing Projects Essay Example | Topics and Well Written Essays - 2500 words”, n.d.)
Retrieved from https://studentshare.org/management/1394122-sim335-managing-projects
(SIM335 Managing Projects Essay Example | Topics and Well Written Essays - 2500 Words)
https://studentshare.org/management/1394122-sim335-managing-projects.
“SIM335 Managing Projects Essay Example | Topics and Well Written Essays - 2500 Words”, n.d. https://studentshare.org/management/1394122-sim335-managing-projects.
  • Cited: 0 times
Comments (0)
Click to create a comment or rate a document

CHECK THESE SAMPLES OF SIM335 Managing Projects

SIM335 Managing Projects

...? Managing Projects Insert Managing Projects Introduction Project management is the art of professional organization of all components of a certain project irrespective of whether the target is to launch a new service or a brand for a particular product. A project is usually a fundamental part of business operations. In the end, it is a temporary task that has a beginning and an ending. Before drawing a network analysis diagram, it is important to know; the start activity, the end activity, which activity or activities precede a certain activity. Any concurrent activities, which activity follows which?...
10 Pages(2500 words)Essay

Managing Projects

...? MANAGING PROJECTS ASSIGNMENT NO TASK By XYZ ID: 000000 Management of Projects TABLE OF CONTENTS Section Title Page 1. Network diagram (using activity on node the node) 1 2. Timings of the Activities and Total Float 2 3. Project Duration and Critical Path 3 4. Project Completion Date 4 5. Effects on Project Duration with Activity Delays 5 5.1 Activity B is delayed by one day 6 5.2 Activity P is delayed by one day 7 5.3 Activity O is delayed three days 8 6. Purpose of Network Diagrams 9 LIST OF FIGURES Figure Title Page 1. Network Diagram (Activity on Node) 1 2. Network Diagram (Activity B is delayed by one day) 6 3....
11 Pages(2750 words)Essay

Marriott: Getting Down to Business with the Business Travelers

3 Pages(750 words)Case Study

Managing projects

...? Project Management Table of Contents SECTION I 4 Principles of Project Management 4 Success Failure Criteria 5 Benefits of Managing Projects 5 SECTION II 6 Project Initiation Document 6 Project Planning 6 Risk Assessment 7 Communication of Project Plan 7 SECTION III 8 Project Implementation 8 Project Monitoring 8 Contingency Plan 9 SECTION IV 9 Project Evaluation 9 Report to Stakeholders 10 Recommendations 10 References 12 SECTION I Principles of Project Management Project...
6 Pages(1500 words)Essay

Managing Successful Projects

...? Managing successful projects Supervisor; April 23, Managing successful projects Answers to question Standard approaches for managing projects, my preferred approach, and rationale for choosing the approach There are many standard approaches for managing projects and these have been developed at both national and international levels. The “Project Management Body of Knowledge,” also known as the PMBOK, is one of the standard approaches to project management (Zarafani 2011, p. 38). The America’s Project Management Institute developed the approach more than two decades ago but its latest version was published in 2008. The project management approach outlines more than 40 processes that are necessary for project management and group... the...
6 Pages(1500 words)Assignment

Managing Projects

...? Managing Project Table of Contents Table of Contents 2 Task 4 Reference List 8 Appendices 9 Appendix Assumptions 9 Introduction 14 Project Plan 15 Feasibility Study 15 Skill and Competency Audit for Project Manager 17 Project Life Cycle 18 Project Initiation 18 Project Planning 20 Project Execution and Closure 21 Conclusion 22 Reference List-2 23 Appendices 24 Appendix 1- Stakeholder Analysis 24 Appendix 2: Path for Leisure Facility Project 25 Appendix 3: Work Breakdown Structure for Leisure Facility Project 26 Appendix 4: Budgeting for Leisure Facility...
12 Pages(3000 words)Term Paper

Human intellectual curiosity

26 Pages(6500 words)Essay

Managing projects

...PROJECT MANAGEMENT Introduction Almost everybody is engaged in one or more projects directly or indirectly in his/her life. It can vary from doing apersonal project such as obtaining a Degree to the construction of big industrial projects such as Dams and Bridges. Projects have been carried out since the beginning of civilization. Every project involves a set of interrelated activities and has a definite beginning and end. Since every project has many aspects to look after for the attainment of project objective, the need for its proper management was seriously felt long back. The need was further compounded when business community started thinking of introducing project management for business purposes. Consequently, a new body... of...
12 Pages(3000 words)Essay

Managing Projects

... a span of 1 year. In the absence of statistical facts from Jones Ltd, this report will be based on the fundamental principle of goal-oriented project management, which demands for implementation of all processes of administration and leadership (Lock, 2007). Project’s Life cycle The Jones Ltd’s project of buying and selling/distributing computers would have similar lifecycle depicted in the diagram below: Market research Purchase of Computers Sales/Distribution Project’s Life Cycle... ...
8 Pages(2000 words)Essay

Managing Projects

...Managing Projects By Q The principles of projects, The Commitment Principle An equitable obligation amid the provider of assets and the project supply team must exist afore a practical plan exists. The project procurement team is accountable for developing appropriate policies, tactics and controls for applying the required skills and effort to convert those assets into the prerequisite deliverables. (Patzak&Rattay, 2011). The Success Principle The procedures for project achievement, in terms of both process and merchandise, must be defined at the commencement of the project as a foundation for project administration decision making and post-project assessment. Short of arrangement on the project’s triumph criteria... , it will not be...
11 Pages(2750 words)Assignment
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.

Let us find you another Essay on topic SIM335 Managing Projects for FREE!

Contact Us