Nobody downloaded yet

SOLUTION TO PARK AND RIDE PROJECT COURSEWORK - Assignment Example

Comments (1) Cite this document
Summary
Part A
Based on the Project Logic Evaluation presented in Appendix B, complete the Network Analysis for the Park and Ride Project to determine the total duration of the project based on the ‘normal’ activity durations and to identify the activities that lie on the critical path(s)…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER92.9% of users find it useful
SOLUTION TO PARK AND RIDE PROJECT COURSEWORK
Read TextPreview

Extract of sample
"SOLUTION TO PARK AND RIDE PROJECT COURSEWORK"

Download file to see previous pages The basic rule for numbering events is that the starting point of an activity is lower than the completion point. Meanwhile, the activities or tasks which need to be completed are represented by arrows. In Figure 1, the tasks indicated in Appendix B were replaced by activity codes using letters. Task duration in days is shown beside their respective codes as numbers in parenthesis. Table 1 presents the activity data for the project with the activity codes, description of each task, normal task duration, the early start (ES), early finish (EF), late start (LS) and late finish (LF) times based on normal duration. The ES and EF times were computed based on the analysis of the network using a forward pass. In a forward pass, computation is made from left to right. The earliest starting time of an activity is the earliest finish time of its predecessor. When an activity has no predecessor, such as for initial activity (or activities), the ES of this activity is 0. The earliest finish time is the sum of the early start time and the duration of the activity (Kerzner, 2009; De Marco, 2011). Meanwhile, the LS and LF times were calculated using a backward pass or a right to left computation. The late start of the final activity is taken as the late finish of this activity and from here the late start of the final activity is computed by subtracting the activity duration from the LS time. If there are two or more terminal activities, the highest LS time of these activities should be adopted as the LS time of the rest of the terminating activities (Kerzner, 2009; Demarco, 2011). Table 1 is presented below and the network diagram is shown as Figure 1 on page 4. Table 1. Activity Data for the Park and Ride Project Using ‘Normal’ Task Durations – Float Times Task Description Duration (in days) Early Start (ES) Early Finish (EF) Late Start (LS) Late Finish (LF) Total Float (TF) Free Float (FF) A Excavate Site 10 0 10 0 10 0 0 B Install Ground Drainage 5 10 15 15 20 5 5 C Install Piled Foundations 10 10 20 10 20 0 0 D Erect Steel Frame 10 20 30 20 30 0 0 E Pour In-situ Concrete Floors 9 30 39 30 39 0 0 F Install Electricity, Lighting and IT Cabling 10 39 49 39 49 0 0 G Electrical and Lighting Fit Out 8 49 57 51 59 2 2 H Fix IT Hardware and Screens 10 49 59 49 59 0 0 I Tar-macadam to Access Ramps and Parking 4 49 53 55 59 6 0 J Fix Automated Entrance Barriers 3 49 52 56 59 7 7 K Commission Services and IT Equipment 10 59 69 59 69 0 0 L Landscaping 10 53 63 59 69 6 6 1. The critical path based on the ‘normal’ activity durations There are three ways of determining if an activity is critical. First, from the tabulation of the ES, EF, LS and LF times, if the ES and EF times of an activity are identical to the LS and LF times, then this activity is critical. An examination of Table 1 revealed that seven activities are critical and these are highlighted in blue and bold font in the table. These are activities are: A, C, D, E, F, H, and K. Another way of determining which activities are critical is by computing the float or slack. Float or slack is the difference between the early schedule (ES, EF) and the late schedule (LS, LF). Tasks with zero (0) float are critical (Kendrick, 2010). As reflected in Table 1, the critical activities have 0 total float and 0 free float. To differentiate, total float is the amount of time (i.e. days, in this project) that an activity can ...Download file to see next pagesRead More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“SOLUTION TO PARK AND RIDE PROJECT COURSEWORK Assignment”, n.d.)
Retrieved de https://studentshare.org/management/1390275-solution-to-park-and-ride-project-coursework
(SOLUTION TO PARK AND RIDE PROJECT COURSEWORK Assignment)
https://studentshare.org/management/1390275-solution-to-park-and-ride-project-coursework.
“SOLUTION TO PARK AND RIDE PROJECT COURSEWORK Assignment”, n.d. https://studentshare.org/management/1390275-solution-to-park-and-ride-project-coursework.
  • Cited: 0 times
Comments (1)
Click to create a comment or rate a document
ha
hanetamara added comment 8 months ago
Student rated this paper as
The topic of "SOLUTION TO PARK AND RIDE PROJECT COURSEWORK" is quite often seen among the assignments in college. Still, this essay opens a brand new perspective of seeing the question. I’ll use the style for my own example.
CHECK THESE SAMPLES - THEY ALSO FIT YOUR TOPIC
Spatial City Park and Ride Transport Planning
...?Q2 Spatial Park and Ride Transport Planning Spatial planning calls for taking into due consideration the amount of space available and themany functions this space is supposed to serve. One of the areas of consideration is Park and Ride transport system. The system is meant to have people park their cars, motorcycles and bicycles at a given place the take a ride in larger vehicle like a bus to complete their journey. The destinations include offices, market places, banks, schools, hospitals, residential areas, entertainment spots, leisure parks, airports, railway stations and city exit highways among others. The...
12 Pages(3000 words)Essay
Project Management Skills Task Coursework
...?Outline Introduction 2. Tools Analysis a. Gantt Chart b. Logic Network c. PERT Chart d. Product Breakdown Structure e. Work Breakdown Structure 3. Additional tools 4. Risk Management 5. Overview 6. Conclusion Introduction IT project management is often regarded as the most significant part of proper business management. Therefore, IT solutions are required for proper work of the industries and departments, and the faultless work of these solutions can be maintained by timely updates, servicing, and safety regulations. The aim of this report is to analyze the project management tools applied for upgrading the OS on the computers within an organization, and define the...
14 Pages(3500 words)Essay
Police Ride
...Police Ride-Along Experience: Summary and Application of Procedural Precedent Abstract I completed a police ride-along experience on March 3, 2012 as per class instructions. I was assigned to a patrol officer named Officer Brian Franz for a four-hour shift. During this period of time there were three incidents, two traffic violations and an alleged gang-rape of two young girls. The last incident caused my shift to be extended by an hour while procedure was followed, and as Officer Franz had to wait for clearance to leave the scene, I had to remain with him. During the ride-along I questioned Officer Franz about various aspects of being a police officer as well as police procedures from...
18 Pages(4500 words)Assignment
Industry Project: Solution Articles
...? Solutions Articles http www.raeng.org.uk/education/vps/pdf/Engineering_a_low_carbon_built_environment.pdf This journal presents a summary of the sector of construction engineering physics and classifies openings for progressions that will profit people all together, in addition to managers, institutions of learning, skilled engineering establishments and particularly professionals who are pursuing careers with construction engineering physics as the foundation. The journal provides essential proposals for Government course of action, industry and academic study guidelines and proficient progression in the field to attain the ability degrees required to convey crowd market low carbon structures. This journal entails the report... for the...
5 Pages(1250 words)Article
Project Development and Control Coursework
...?Project Development and Control work 0. Executive Summary The report proposes an advertising campaign for herbal skin-care product for the women section of the society. The advertising campaign will be emphasized on three goals, i.e. to generate awareness by informing the targeted customer group, persuading them to the ultimate purchase by developing trust amid the audiences and ultimately rewarding competitive advantages to the company. When addressing these aspects, the areas covered in this report include the strategies which are intended to be implemented through the advertising campaign in respect to management of stakeholders, risk management, resource obtainment, scheduling as well as monitoring and controlling...
6 Pages(1500 words)Essay
Project Management Individual Coursework Assignment
...?PROJECT MANAGEMENT SUPER PRISON PROJECT INTRODUCTION Project management is the discipline of management that has gained the growing importance sincepast two decades. Simply stating project management refers to the planning project, resource organizing, stakeholders’ coordinating to achieve the simple to complex and diverse set of goal within planned resources. Project usually complete; however, the successful completion of the project is when the goal is achieved without discrepancy within defined goal and resources. Hence, scientific mechanisms are defined to aid the project managers to achieve the goal...
8 Pages(2000 words)Essay
Project Management Module Coursework
...that is Person: Days Ratio. The cost information could be obtained from the use of the standards and measurements sections. We can ensure that costs are in line with the estimates by making frequent comparisons with the actual costs with the estimates. The aspects of standard costing could also be established with respects to costs, recoveries and efficiency studies. Question 1C: The choice for selection of project manager is being considered, In this connection, it is necessary to appoint a person with IT background, since it is nowadays, a crucial aspect of project management, and IT is very much necessary for application in industry situations. Moreover, it is also seen that effective business...
5 Pages(1250 words)Essay
Capstone Project Scenario Solution
... With the advancement of science and technology, the lives of humans have also become advanced and importantly comfortable. Comfortable in the sense, our physical body and mental mind can be safeguarded from various threats using science and technology. This is greatly visible in the field of medicine. From formulated tablets to computerized equipment, many inventions, discoveries and also innovations have arisen in the medical industry. And one of the important ones is the MRI scan, which can scan the whole human body and can diagnose any injuries, abnormalities etc. This paper will discuss from the point of view of an administrator, who intends to start a mobile MRI scan service and also analyzes its opportunities, challenges... With the...
7 Pages(1750 words)Essay
PROJECT MANAGEMENT: COURSEWORK
...similarly. A clash is a conflict or an impossible condition which occurs in the project. There could be multiple reasons for the clash. Either this could be because of over usage of resources or insufficient cost being defined for a task. While assigning the resources, we encountered clashes in the resource usage. This is because a resource assigned to a task was also assigned to another task in the same time frame. Since the amount of resource at present is fixed and the schedule has also been defined, this created clash and the system warned us about this. This is shown in the screenshot below: In order to resolve the clash, we could adopt two ways (as suggested by MS Project): Either change the...
12 Pages(3000 words)Term Paper
Project management coursework
... to ensure that it is working as per the desired standards as well as scrutinizing for any variances from the actual goal. The project manager also acts as a leader and checks for any conflicts that might arise during the project process and tries to resolve the same by proper resolution techniques (Merchant and Stede, 2012). The project manager makes use of steering committees for the purpose of resolving conflicts that might surface in course of the project. These committees offer solution for mitigating conflicts, thereby bringing the project back on the adherence of governance standards and overall organizational goal. In absence of any audit and evaluation mechanism for NPfIT programme, there was no way to question failures... ...
6 Pages(1500 words)Coursework
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Let us find you another Assignment on topic SOLUTION TO PARK AND RIDE PROJECT COURSEWORK for FREE!
Contact Us