We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Nobody downloaded yet

SOLUTION TO PARK AND RIDE PROJECT COURSEWORK - Assignment Example

Comments (1) Cite this document
Summary
Part A
Based on the Project Logic Evaluation presented in Appendix B, complete the Network Analysis for the Park and Ride Project to determine the total duration of the project based on the ‘normal’ activity durations and to identify the activities that lie on the critical path(s)…
Download full paper
GRAB THE BEST PAPER
SOLUTION TO PARK AND RIDE PROJECT COURSEWORK
Read TextPreview

Extract of sample
SOLUTION TO PARK AND RIDE PROJECT COURSEWORK

Download file to see previous pages... The basic rule for numbering events is that the starting point of an activity is lower than the completion point. Meanwhile, the activities or tasks which need to be completed are represented by arrows. In Figure 1, the tasks indicated in Appendix B were replaced by activity codes using letters. Task duration in days is shown beside their respective codes as numbers in parenthesis. Table 1 presents the activity data for the project with the activity codes, description of each task, normal task duration, the early start (ES), early finish (EF), late start (LS) and late finish (LF) times based on normal duration. The ES and EF times were computed based on the analysis of the network using a forward pass. In a forward pass, computation is made from left to right. The earliest starting time of an activity is the earliest finish time of its predecessor. When an activity has no predecessor, such as for initial activity (or activities), the ES of this activity is 0. The earliest finish time is the sum of the early start time and the duration of the activity (Kerzner, 2009; De Marco, 2011). Meanwhile, the LS and LF times were calculated using a backward pass or a right to left computation. The late start of the final activity is taken as the late finish of this activity and from here the late start of the final activity is computed by subtracting the activity duration from the LS time. If there are two or more terminal activities, the highest LS time of these activities should be adopted as the LS time of the rest of the terminating activities (Kerzner, 2009; Demarco, 2011). Table 1 is presented below and the network diagram is shown as Figure 1 on page 4. Table 1. Activity Data for the Park and Ride Project Using ‘Normal’ Task Durations – Float Times Task Description Duration (in days) Early Start (ES) Early Finish (EF) Late Start (LS) Late Finish (LF) Total Float (TF) Free Float (FF) A Excavate Site 10 0 10 0 10 0 0 B Install Ground Drainage 5 10 15 15 20 5 5 C Install Piled Foundations 10 10 20 10 20 0 0 D Erect Steel Frame 10 20 30 20 30 0 0 E Pour In-situ Concrete Floors 9 30 39 30 39 0 0 F Install Electricity, Lighting and IT Cabling 10 39 49 39 49 0 0 G Electrical and Lighting Fit Out 8 49 57 51 59 2 2 H Fix IT Hardware and Screens 10 49 59 49 59 0 0 I Tar-macadam to Access Ramps and Parking 4 49 53 55 59 6 0 J Fix Automated Entrance Barriers 3 49 52 56 59 7 7 K Commission Services and IT Equipment 10 59 69 59 69 0 0 L Landscaping 10 53 63 59 69 6 6 1. The critical path based on the ‘normal’ activity durations There are three ways of determining if an activity is critical. First, from the tabulation of the ES, EF, LS and LF times, if the ES and EF times of an activity are identical to the LS and LF times, then this activity is critical. An examination of Table 1 revealed that seven activities are critical and these are highlighted in blue and bold font in the table. These are activities are: A, C, D, E, F, H, and K. Another way of determining which activities are critical is by computing the float or slack. Float or slack is the difference between the early schedule (ES, EF) and the late schedule (LS, LF). Tasks with zero (0) float are critical (Kendrick, 2010). As reflected in Table 1, the critical activities have 0 total float and 0 free float. To differentiate, total float is the amount of time (i.e. days, in this project) that an activity can ...Download file to see next pagesRead More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“SOLUTION TO PARK AND RIDE PROJECT COURSEWORK Assignment”, n.d.)
Retrieved de https://studentshare.org/management/1390275-solution-to-park-and-ride-project-coursework
(SOLUTION TO PARK AND RIDE PROJECT COURSEWORK Assignment)
https://studentshare.org/management/1390275-solution-to-park-and-ride-project-coursework.
“SOLUTION TO PARK AND RIDE PROJECT COURSEWORK Assignment”, n.d. https://studentshare.org/management/1390275-solution-to-park-and-ride-project-coursework.
  • Cited: 0 times
Comments (1)
Click to create a comment or rate a document
ha
hanetamara added comment 3 months ago
Student rated this paper as
The topic of "SOLUTION TO PARK AND RIDE PROJECT COURSEWORK" is quite often seen among the assignments in college. Still, this essay opens a brand new perspective of seeing the question. I’ll use the style for my own example.
CHECK THESE SAMPLES - THEY ALSO FIT YOUR TOPIC
Spatial City Park and Ride Transport Planning
The system is meant to have people park their cars, motorcycles and bicycles at a given place the take a ride in larger vehicle like a bus to complete their journey. The destinations include offices, market places, banks, schools, hospitals, residential areas, entertainment spots, leisure parks, airports, railway stations and city exit highways among others.
12 Pages(3000 words)Essay
Theme park report
It starts with a macro level view of the industry and the company followed by a discussion about its organization structure. A critical analysis of its structure helps in understanding the pros and cons of the current organization setup. This is followed by an analysis of the visible reasons of closure of the park.
10 Pages(2500 words)Assignment
Coursework
The two giants in the video gaming industry is the Sony computer entertainment, with their popular video gaming console ‘PlayStation’, and Nintendo Corporation Limited, famous for their ‘Game boy’ and ‘Nintendo Wii’. Both these two companies can be regarded as the immediate competitors as they both operate in the same geographical area and attracting similar consumer bases.
8 Pages(2000 words)Assignment
Technology solution
The second component had to do with the institutionalization of a customer relationship management plan that will focus on the use of new media. This part of the essay shall however concentrate on centralization of the sales and product offices. Components of Sales and Product IT Centralization Resources: people A well resourced human capital base shall be needed for the success implementation of the IT centralization process.
3 Pages(750 words)Assignment
LEARNING TO RIDE A BIKE
In fact, one organization, 350.org has been working to get people on their bikes in order to cut down on the atmosphere’s carbon content to around 350 parts per million. This would maintain the climate at what it has been for the previous 100 centuries; 24th September is the World Bike Day people should get out of their cars and ride on two wheels.
4 Pages(1000 words)Assignment
High Line Park NYC
But scholars like Jane Jacobs argued otherwise. According to her, urban planning must be done with full attention on and regard to the seemingly unorganized chaos as seen in an urban locality of residential areas. This approach can be attributed to the humanness of the city life instead of its much trumpeted need of orderliness.
5 Pages(1250 words)Assignment
Theme Park Management
Spread over 70 hectares and employing over 3000 people, the Europapark also has three hotels, a campsite and a 'tipi-village', all of which together can provide accommodation to almost 4,128 customers. The hotels are of special interest for companies to hold conferences, meetings, etc, as they provide incentive to the participants to bring their families along.
8 Pages(2000 words)Assignment
Retail Park
The availability of cheaper land on the outskirts of Medway would prove to be ideal in setting up a retail park, along with facilities for leisure activities such as children's playground, food court, bowling alley and so on. Having a retail park in the Medway area would mean that drive time to major shopping centers in the city could be avoided.
11 Pages(2750 words)Assignment
The first piece of coursework requires you to assess an ecommerce business solution for your chosen organisation
The company is renowned for its performances, in terms of financial, operational and strategic performances. Hennes & Mauritz (H&M) offers a wide range of products for men, women and children. The product portfolio includes apparels, footwear, accessories and cosmetics
6 Pages(1500 words)Assignment
National Park Assignment
The visitors are allowed to enter the national parks for under special conditions including for educational, inspirational, recreational, and cultural purposes. The
3 Pages(750 words)Assignment
Let us find you another Assignment on topic SOLUTION TO PARK AND RIDE PROJECT COURSEWORK for FREE!
Contact us:
+16312120006
Contact Us Now
FREE Mobile Apps:
  • About StudentShare
  • Testimonials
  • FAQ
  • Blog
  • Free Essays
  • New Essays
  • Essays
  • The Newest Essay Topics
  • Index samples by all dates
Join us:
Contact Us