Our website is a unique platform where students can share their papers in a matter of giving an example of the work to be done. If you find papers
matching your topic, you may use them only as an example of work. This is 100% legal. You may not submit downloaded papers as your own, that is cheating. Also you
should remember, that this work was alredy submitted once by a student who originally wrote it.
The paper "The US Contract Law" highlights that in the contract between Span and C-S, it was agreed that Span a software company would supply C-S with software and expertise in overhauling infrastructure and making working conditions at C-S IT enabled…
Download full paperFile format: .doc, available for editing
Memo: US Contract Law
Introduction:
In the contract between Span and C-S, it was agreed that Span a software company would supply C-S with software and expertise in overhauling infrastructure and making working conditions at C-S IT enabled. Keeping this in mind, a contract for supply was signed, where ordinary requirement changes were agreed to. Problems have since cropped up given the changes in the system and user requirements, which according to Span are out of the ordinary, and should allow for changes due to contingencies. The two major problems are that of deadlines and of quality, both of which have taken a beating due to the conditions as hurriedly laid out in the contract.
Case
The following memo will make a study of the risk and opportunities that will characterize the deal and its future, from the perspective of this project manager. The three major issues which arise as a result of this mess-up are those of:
1. Breach of contract under substantial performance of contract
2. Breach of contract under internal escalation procedure of disputes
3. Breach of contract under communications and reporting
The law
Where the substantial performance rule is concerned, American courts have, over the years laid special emphasis on the element of good faith. Where there have been intentional deviations from the terms of the contract the “good faith” has been found to be lacking [Shell v Schmidt, 164 Cal. App.2d 350]. Again the modern law, which is also understood as being the less dogmatic approach to the problem lays the issues of quality and the escalation of procedures as a test of essentiality, i.e. where the contract has not been exactly performed according to its terms the question is asked whether the breach so fundamental as to go the root of the contract. When one party breaches a sales or lease contract, the UCC provides the injured party with a variety of pre-litigation and litigation remedies. These remedies are designed to place the injured party in as good a position as if the breaching party’s contractual obligations were fully performed [UCC 1-106(1), 2A-401(1)].
Again in accordance with the law of contracts, a seller or lessor is under a duty to deliver conforming goods. If the goods or tender of delivery fails in any respect to conform to the contract, the buyer or lessee may opt either (1) to reject the whole shipment, (2) to accept the whole shipment, or (3) to reject part and accept part of the shipment. This option is referred to as the perfect tender rule [UCC 2-601, 2A-509]. If a buyer accepts nonconforming goods, the buyer may seek remedies against the seller. There are broad tests for severance of a contract that the decision of contract discharge could be assigned on (Blum, 2007). A discharge relates to the process of bringing a valid and enforceable contract to an end. This would just mean that the contract needs to be legal in its standing for its termination to be termed as a discharge of the contract. A contract may be discharged or terminated by:
1. The performance of the contract
2. agreement between parties
3. a breach of the contract (actual or anticipated)
4. operation of the law
5. a frustrating event
Risks
The general rule is that a party will only be discharged from the obligations under a contract if complete performance has taken place. This means in turn that the performance needs to be exactly in line with the terms of the contract. Partial performance is insufficient and may result in a party being treated as having done nothing at all. in Cutter v Powell (1795) (KB), the plaintiff’s husband signed on as second mate on the defendant’s ship on a voyage from the West Indies to England (Blum, 2007). Minor flaws in the contract execution scheme are not usually held punishable by law u7nder the principle of de minimis (Shipton Anderson and Co v Weil Brothers and Co (1912) (KB)) the court held that a purchaser could not reject a consignment of wheat which was 55 pounds over the required 4950 tonnes. In theory, a contract may stipulate that performance is to be completed in stages or segments. If so, performance of less than the entire contract whole may be insufficient to confer partial rights on the performing party (Cheeseman, 2010).
According to the law, in cases where buyer gets a quantity of goods that is lesser than the one that he paid for, by way of quality or quantity, the buyer is entitled to reject the goods. If the buyer accepts the goods that are thus delivered, the idea is that there must be a payment paid back in keeping with the rates of the contract (Cheeseman, 2010). In cases where the seller is able to deliver the goods to the buyer a quantity of goods larger than he contracted to sell, the buyer may accept the goods included in the contract and reject the rest, or he may reject the whole. Also, in keeping with the law of contracts, given the fact that in cases where delivery is to be made at a distant l0ocation, the buyer must, unless otherwise agreed, take on the risk of deterioration in the goods necessarily incident to the course of transit (Cheeseman, 2010).
The two basic considerations to be kept in mind in this case would therefore be:
1. Whether or not the defects and the delays in contract execution by Span are essential going to the very roots of the contract; and
2. If these delays are in fact essential, then were they caused by the more than ordinary changes in the requirements of the contract?
The first risk in this case would be that of contract rescission, which would happen in case C-S, chooses to stand by its stand of not accepting the implementation of the contract as it has been executed so far. In this scenario, C-S has the choice of treating the contract as being still in force and suing for damages for past and future breaches, or they might elect to treat the contract as being discharged. If they choose the first course, they would remain liable on the contract whereas in the second alternative the contract is terminated for the future which means that the hirer would be relieved of their obligation to pay the price. However, in such a scenario, they would not be precluded for suing for recovery of damages with respect to the breach that has led to the discharge of the contract.
The second risk comes from the fact that in accordance of s2-306 [UCC] there is provision for rescinded contracts if the output, requirements undergo changes during the course of project implementation. S2-306 states that (LeRoy and Jentz, 2008): “A term which measures the quantity by the output of the seller or the requirements of the buyer means such actual output or requirements as may occur in good faith, except that no quantity unreasonably disproportionate to any stated estimate or in the absence of a stated estimate to any normal or otherwise comparable prior output or requirements may be tendered or demanded”. In the context of this case therefore, Span is well within its rights to argue that the problem of the contract were given birth due to the fact that ultimate reality of contract execution was markedly different from the initially expressed and contract related outline of effort expected. They could also attribute the loss of quality to this very problem.
Opportunity:
In the context of this case, the opportunity arises from the fact that only 40 per cent of the contract has been negotiated till date and a majority of it is yet to be implemented. This gives both the companies to reassess the situation and realign the contract in keeping with the demands of the project, by way of cost and time escalations.
Alternative option
The alternative option would in this case be that of international arbitration. These needs to be a part of the initial contract providing that dispute that may arise in the future, will usually be set out at the end of the contract and, as a matter if good practice should be preceded-or-followed by a choice of law clause (McIlwrath and Savage, 2010). Since the arbitration clause is only one of the many clauses in a given contract, it would seem reasonable to assume the fact that the law chosen by the parties to govern the contract will also be the ones to govern the arbitration clause.
References:
McIlwrath, M., and Savage, J., (2010). International Arbitration and Mediation: A Practical Guide. Kluwer Law International. Pp21-30. Retrieved December 20, 2010
Cheeseman, H. R., (2010). Business Law: Legal Environment, Online Commerce, Business Ethics, and International Issues, Seventh Edition
Blum, B. A., (2007). Contracts: examples & explanations. Aspen Publishers. Pp57-60.
LeRoy, M. R., and Jentz, G., (2009). Fundamentals of Business Law: Excerpted Cases. Cengage Learning. < http://books.google.co.in/books?id=afP8TGYQfNsC&pg=PA695&lpg=PA695&dq=A+term+which+measures+the+quantity+by+the+output+of+the+seller+or+the+requirements+of+the+buyer+means+such+actual+output+or+requirements+as+may+occur+in+good+faith,+except+that+no+quantity+unreasonably+disproportionate+to+any+stated+estimate+or+in+the+absence+of+a+stated+estimate+to+any+normal+or+otherwise+comparable+prior+output+or+requirements+may+be+tendered+or+demanded&source=bl&ots=5Y6dF9vZai&sig=RhUq0iaYPiqmT_M0y6CZ_kcR5KU&hl=en&ei=4pAPTZCKFpOssAPax7iwAg&sa=X&oi=book_result&ct=result&resnum=2&ved=0CB8Q6AEwAQ#v=onepage&q=A%20term%20which%20measures%20the%20quantity%20by%20the%20output%20of%20the%20seller%20or%20the%20requirements%20of%20the%20buyer%20means%20such%20actual%20output%20or%20requirements%20as%20may%20occur%20in%20good%20faith%2C%20except%20that%20no%20quantity%20unreasonably%20disproportionate%20to%20any%20stated%20estimate%20or%20in%20the%20absence%20of%20a%20stated%20estimate%20to%20any%20normal%20or%20otherwise%20comparable%20prior%20output%20or%20requirements%20may%20be%20tendered%20or%20demanded&f=false>
Read
More
As the paper "contract law as Execution of Promises" tells, all agreement and contract must be developed by a free accord between parties capable to make a contract for a legal consideration and with a legal object and are not hereby particularly acknowledged to be invalid.... Step 3: Application of law to the FactIn the context of the case study, the above aspects of a legal contract were missing.... In the provided case scenario, the major legal issue recognized is aspects of a legal contract....
In addition, it is considered to be the heart of the common law system.... The most potential benefit of the doctrine of precedent is that it promotes uniformity within the law.... The author explains the case where the hotel management has no responsibility for the money and other valuables....
fter having paid a substantial amount and not satisfied with the work, they terminated their contract with TL nine months later during Easter 2004.... Some weeks before terminating the contract with TL, the Davenports had engaged Monavon, following an introduction from Mr.... When the contract with TL ended on a sour note, Mr....
USA contract law Essay The Restatement 2nd defines contract as, 'a promise or a set of promises for the breach of which the law gives a remedy, or the performance of which the law in some way recognizes as a duty.... The contract law is governed by the provisions of the UCC and the Restatement of Contracts.... In contract law, a mistake can be used to invalidate the agreement.... Since these mistakes can be used as 'excuses' to invalidate a contract, the provision of 'objective standard of agreement' becomes important in contract law....
The law of contract designate an objective standard of agreement with which both parties involved must comply.... is recognized as articulating this in the terms of how it's most commonly understood by law practitioners today in the case Smith v Hughes.... The law of contract designate an objective standard of agreement with which both parties involved must comply.... is recognized as articulating this in the terms of how it's most commonly understood by law practitioners today in the case Smith v Hughes....
This paper 'contract law: Cunningham vs.... Driscoll' seeks to explore legal concepts in contract law.... Cunningham and Driscoll entered into a contract of sale of soybeans a total price of $ 22000.... Cunningham has sued for breach of contract but Driscoll argues for summary judgment.... A contract that either does not involve land, is enforceable within a year, is not a contract of guarantee, is not a promise that involves 'consideration of marriage' and is not for the sale of goods worth at least $ 500 dollars does not necessarily have to be in writing (Clarkson, et al....
By looking at these common laws, the author of this paper under the title "Business and contract law in the USA" identifies the facts of law, and principles that the courts interpreted and used for purposes of solving the disputes under consideration.... a contract is a pact amongst two or more individuals, and it creates a give-and-take relationship, which is recognizable by law.... For a contract to gain the protection of the law, it must satisfy the element of offer, acceptance, purpose to create a legal representation, and there must be a consideration....
The article 'contract law in the USA' focuses on contractual liability and remedies.... The case Taylor versus Caldwell highlights controversial elements pertaining to whom should absorb losses in the event that a situation arises causing the performance of the contract to be impossible.... Moreover, the objective of impossibility implies that neither party could have fulfilled their obligations with regard to the contract.... Specifically noted in the contract were the charges of hiring the Hall: a cost of 100 pounds per day....
17 Pages(4250 words)Article
sponsored ads
Save Your Time for More Important Things
Let us write or edit the research proposal on your topic
"The US Contract Law"
with a personal 20% discount.