Nobody downloaded yet

Construction Adjudication Law - Legal problem - Coursework Example

Comments (0) Cite this document
Summary
PART A Construction Adjudication Law – Legal Problem This report is a legal advise for two parties in a construction adjudication dispute. In the facts of the case, Prestige Development Plc (PDP) and Paramount Construction Limited (PCL) entered a building contract for the construction of a waterfront apartment in south England…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER91.3% of users find it useful
Construction Adjudication Law - Legal problem
Read TextPreview

Extract of sample "Construction Adjudication Law - Legal problem"

Download file to see previous pages The architects in question who did the preliminary design had the obligation to check the ground conditions and foundation requirements. PCL bears a partial responsibility for the design flaw. The matter is referred to adjudication under clause 9.2 of the JCT Design and Building Contract. There were a number of issues with the adjudication process and this include a reliable information that the CEO of PDP and the Adjudicator went for a weekend in a country hotel where they were overhead discussing things related to the case. From the case study, there is the need for the following things and matters to be examined in relation to the relevant rules about: 1. The scope of the Adjudicator's obligations and whether it was met or not. 2. The independence of the Adjudicator. 3. The impartiality of the Adjudicator's processes in dealing with the case 4. The ability of the case to be escalated to a court dispute. Scope of Adjudication The main issue of contention is to define the actual question and the actual point of law that the adjudicator of the case at hand was supposed to handle. This is in response to the accusation of the CEO of PDP that the adjudicator addressed the wrong question. ...
ication of the relevant provision, it can be said that the obligation of the Adjudicator in this case is to identify the procedure that was used by the contracting party and which party deserves to be held responsible for the damage. In other words, the Adjudicator has to examine the contract between PDP and PCL and identify who is responsible for the determination of the soil condition and the point in the contract that it went wrong. The evidence of both parties were to be examined and a conclusion could be drawn. However, in this case, it is apparent that the Adjudicator did not spend too much time studying those documents. Rather, he examined just two variables, the architects and PCL's relative positions. He did not go deep into the contract, neither did he set out a fair procedure. Hence, it can be concluded that he did not operate within the scope of the contract. Independence of the Adjudicator The Adjudicator happened to be the brother-in-law of the MD of PCL. This shows clearly that they had an informal relationship that could have implications for the independence of the Adjudicator. The Adjudicator, as a professional, has codes of ethics in the profession he belongs to, whether he is a legal professional or a construction expert. Every adjudicator needs to be independent and be seen to be independent in his decisions and procedures3. In a landmark ruling in a construction arbitration case in France, which is part of European Union Law, it was stated that “An Arbitrator should not have any commercial or other similar connection with either party which may give rise to suspicion in the mind of a reasonable person that he may be biased”4. The implication is that there should be no relationship that exists between an adjudicator and any of the parties that ...Download file to see next pagesRead More
Tags
Cite this document
  • APA
  • MLA
  • CHICAGO
(“Construction Adjudication Law - Legal problem Coursework”, n.d.)
Retrieved from https://studentshare.org/law/1404286-construction-adjudication-law
(Construction Adjudication Law - Legal Problem Coursework)
https://studentshare.org/law/1404286-construction-adjudication-law.
“Construction Adjudication Law - Legal Problem Coursework”, n.d. https://studentshare.org/law/1404286-construction-adjudication-law.
  • Cited: 0 times
Comments (0)
Click to create a comment or rate a document

CHECK THESE SAMPLES OF Construction Adjudication Law - Legal problem

Construction Law

...? NEC Assignment 2 The NEC Engineering and Construction Contract (ECC) developed by the of Civil Engineers is a guideline for creating documents in the engineering and construction industry related to tenders, awarding and conducting contracts. It comprises of some standard contracts, based on these principles: encouraging co-operation between parties to the contract, suitability for various commercial projects (Eggleston, 2006). This scenario is about a contract related to the design and construction of the Tiger House for the Chinese consulate. The contractor has apparently sublet the building of a steel framed glazed structure to a subcontractor; this arrangement is known as the...
8 Pages(2000 words)Essay

Construction Law

...of Procurement - Communications and Contractual Relationships. [Online] Available at: HYPERLINK "http://www.caribbeanconstruction.com/index.php?option=com_content&view=article&id=361&Itemid=5" http://www.caribbeanconstruction.com/index.php?option=com_content&view=article&id=361&Itemid=5 [Accessed 12 April 2012]. Chappell, D., 2007. Understanding JCT Standard Building Contracts. 8th ed. London: Routledge. Constable, A. & Chambers, K., 2009. The JCT Contract in a Cold Climate. [Online] King’s College Construction Law Association Available at: HYPERLINK "http://www.kccla.org.uk/pdfs/JCT%20Contract%20in%20a%20Cold%20Climate%201_Notes.pdf"...
5 Pages(1250 words)Essay

Construction Law

...by Innocent’s architects to call for changes and review. Finally, this section will deal with the dampness problem that was discovered after the contract was rectified. Question (A) In this section, the position of Innocent in relation to their architects's findings are examined in relation to the principles of contract law, breach of contract and the common law doctrine of temporary disconformity. Rules The terms of a contract can be express by incorporation by the terms of reference or implied by relevant legal rues. Exclusion clauses cannot be applied in cases of negligence and major activities that are not done in good faith1. In this broad and general framework, the...
14 Pages(3500 words)Essay

Construction Contract Law

...manifests that the dispute can be determined either by legal proceedings, by arbitration or by any agreement among the parties. The said provisions give the right to either party to facilitate the adjudicator to take the initiative in ascertaining the facts of the law which may be relevant to the case. In that order, the adjudicator's decision is binding until it is finally determined by litigation, arbitration or agreement, and by itself, expedites the proceeding in the settlement of the dispute. Pre-Action Protocol for Construction and Engineering Disputes One more significant rule which will be of help in the enforcement of the contracting...
12 Pages(3000 words)Case Study

Construction Legal Studies

...Construction Legal Studies A construction on site should be managed effectively in order to avoid possible issues and problems. This particular case demands even more management and organizational requirement during construction due to its controversial nature. Endeavour Tower, a modern five-story "block of flats" is to be erected amidst a house, gardens, and other historical attractions. A lovely home with a centuries' old garden and modern, glass-fronted building leaves many people already on edge. This is not the "typical" construction project involving only the vested parties but it also involves many others who are concerned about the project's degradation of England's historical, architectural... to...
8 Pages(2000 words)Essay

Construction Law

...in a particular case in order to determine whether the breach of the contract was a sufficiently substantial cause of the claimant’s loss.5 Therefore the party that violates the contract is liable only if the breach was in effect the “effective cause” of his loss.6 An action for losses caused by a breach of contract will not be effective if there was merely the opportunity or occasion for loss created but actual loss cannot be effectively established.7 This decision shows how the element of ambiguity and confusion that already exists in case law makes legal actions in construction contracts difficult and contentious to pursue. However, the new protocol does not alleviate such...
9 Pages(2250 words)Essay

Construction Law

...on in the workplace or at least what their employees are up to.16 An action for losses caused by a breach of contract will not be effective if there was merely the opportunity or occasion for loss created but actual loss cannot be effectively established.17 This decision shows how the element of ambiguity and confusion that already exists in case law makes legal actions in construction contracts difficult and contentious to pursue. Falling from heights is another risk factor that exists in the construction industry and this was analyzed in detail in a report prepared by Bomel Ltd.18 However, as the authors of this study point out, risk index does not have much meaning...
8 Pages(2000 words)Essay

Legal Problem

...in legal terminology as “extreme carelessness regarding an obvious defect or problem.” (Stewart, Warner, Portman, 2008, p. 228) Now such acts of “extreme carelessness”, according to jurisprudential rational, incorporates intention of an individual to commit such act and such element of intentional commission of reckless act are specified in legal terminology as mens rea. Paul Bergman, Sara J. Berman, Sara J. Berman-Barrett explains mens rea as, “Mens rea is Latin for “guilty mind”. The mens rea concept expresses a belief that people should be punished … only when they have acted with an intent or purpose that makes them morally blameworthy.” (Bergman, Berman, Berman-Barrett, 2008, p....
3 Pages(750 words)Essay

Construction Law

...Construction Law Word Count: 2285 I. Introduction As the global economy is living through its worst crisis for about 90 years many changes are happening. Priorities change, accepted norms are being questioned, globalization which was thus far a given is now debated again, protectionism is starting to appear in the most unexpected of places (US, EU construction industry etc.). Chief among those is the organizational structure that can best utilize precious limited resources to maximize the return on the organization’s performance in construction. Furthermore, success potential can be enhanced by the combination of a sound choice of structure, adequate planning for its...
8 Pages(2000 words)Assignment

Construction Legal Procedures

...Construction Legal Procedures Construction Legal Procedures Introduction Construction Legal procedures are sets of rules and regulations followed by individuals or organizations handle issues relating to building and other relevant fields. In actuality, construction laws are an admixture of contract law, planning law, commercial law and legislations relating to tort (Moran and Stover, 1993, pp.1-14). The laws deal with a long array of legal matters such as contract, negligence, guarantees and sureties, tendering and bonds and bonding. All the financial institutions, civil engineers, construction workforce and architects are governed by construction law to fulfill their obligations. At the turn of 1983, the United Kingdom witnessed... :...
6 Pages(1500 words)Essay
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.

Let us find you another Coursework on topic Construction Adjudication Law - Legal problem for FREE!

Contact Us