The paper "Dredging in Ports and Harbor Construction" is a perfect example of a report on engineering and construction. This report looks at the application of dredging in ports and harbor construction…
Download full paperFile format: .doc, available for editing
Extract of sample "Dredging in Ports and Harbor Construction"
Abstract
This report looks at application of dredging in ports and harbor construction. The methods discussed dredging: pontoon-mounted grabbing; pontoon-mounted (or shoreline) dragline; pontoon-mounted pumping; self-propelled trailing suction dredging; blasting and bucket dredging. The advantages and advantages associated by these methods have also been discussed
Key word: Dredging, ports, harbours, technique
Introduction
Dredging is undertaken in ports and harbours where there the access channels, harbor docks and swinging basins are created or the existing ones are deepened, widened are enlarged (Jan De Nul Group, 2012). Enlargement of ports and harbours are of economic importance since the expanding world trade makes inevitable for ports and harbours to increase their capacity. This is addressed through deepening harbor basins and channels which are already in place or the facilities are just created altogether. The increase in need o transport raw materials such as coal, iron ore and oil and gases there is need for construction of specialized harbours (ABP Research, 1999).
Making an accurate estimate of volumes that are to be dredged is important in assessment of dredging works. Having accurate estimates of volume of materials to be handled is important in choosing the appropriate dredging plant, in estimating production, time of execution and the cost of project.
The materials that are to be dealt with during dredging need to be characterized. Characterization involve evaluation of physical, biological and chemical properties of the sediment so as to determine the appropriate dredging methods to be used, beneficial use that the materials can be put to and the disposal options available and likely environmental impact (Erftemeijer, 2006).
Dredging methods
Dredging may be suitable the following materials: cohesionless materials such as sand or granular materials which are loosely cemented together; clayey materials which are highly cohesive; silt mad originating from the inside of port areas and rocks of wide rage of hardness (USACE, 1983). The dredging techniques which may be put to use depending on deposit type are:
pontoon-mounted grabbing;
pontoon-mounted (or shoreline) dragline;
pontoon-mounted pumping;
self-propelled trailing suction dredging;
Pontoon-mounted grabbing
A pontoon –mounted grabbing may be a grab dredge which has self-propelled vessels with on board hoppers with one or more cranes being mounted on the deck. Another type is the pontoon dredger which has a barge-mounted crane which is propelled by a tug aided by hopper barges. The operations in a grab dredger involve lowering, closing and raising of a single grab by use a wire rope.
Grab dredger advantages are:
it is flexible in applications in maintenance activities in all marine sediments where a variety of grabs may be feasible
may be used with desired efficiency to a depth of 35m beyond which there is impediment of free-fall effects of grab that lowers efficiency of grab
it is very suitable when dredging is being undertaken along quays and in harbor basin corners.
On the other hand the this technique has a shortcoming causing obstruction in see traffic when stationary in navigation channels in addition to leaving irregular bottom topography
Dragline
In this method an open steel bucket is dragged on the sea bed up to the point it will fill up. The bucket is then lifted up after being filled up and the load dumped in a barge or on the shore. The use of this method is predominant in North America (PIANC., 1977). The method has a shortcoming of much of the dredged materials being spilled resulting to high level of turbidity. Most of functions performed by dragline have been taken over by backhoes because of the ability to perform with much higher efficiency.
Pontoon-mounted pumping
This technique involves a large submersible pump being suspended from a pontoon and dunked into the ocean bed. The slurry which consists of about 11% of sand on weight basis is pumped through floating pipes. (Erftemeijer, 2006). Where slurries have extremely sand particles which are extremely fine , the discharge pipe velocity would be expected to be beyond 1.5m/s while where coarser sand are involved the speed should range between 3 and 4m/s (ABP Research,1999). The ability of handling larger outputs is advantage using pontoon pumping. The pumps used may also have cutter blades to take care of sea grass and winds (Erftemeijer, 2006). This method is incorporated with air lift is very suitable in dredging areas rich in archaeological remains.
This method is associated with the following shortcomings
the operation are interfered with where rough seas are involved as the pump is made to loose contact with the bed
there is a narrow range of sediments that can be dredged efficiently
the result of use of this method is an irregular sea bed
obstruction is caused where the equipment is stationary in navigation channel
Trailing suction
This method find application where large volumes of sediment which are cohesionless. This dredger consists of a hopper vessel which has a trailing arm that is suspended at the side and is dragged at the sea bed. The vessel moves forward at a speed of about 6knots with a computerized hydraulic system being used to ensure swell and tidal variations is compensated for automatically. Powerful pumps are used to draw the mixture of water and sand passing them through a chain of decanters with solid deposition into internal hoppers which have a carrying capacity ranging from 2000 to beyond 25000m3 with the decanted seawater which is relatively clear being dumped overboard (Vellinga, 1984). If no intermediated pumps are used the maximum possible depth of dredging is around 25m while incorporating one or two intermediate pumps there can be increase in the depth to between 80 and 120m. There is full automation of the process with dredging running 24-hour non-stop (Vellinga, 1984). The clean dredged material may be dumped offshore while unclean material is pumped onshore through pipes which are laid ashore so as to be used in reclamation
The advantages of this method are: there is little interference with operations of ports; exhibits versatility by being able to handle both cohesive and cohesionless sediments. The other advantage is that it is possible for dredged load being pumped ashore as reclamation and it also exhibit versatility in size depending on the size of the project. On the other hand the disadvantage of this method is t lack of precision in the final dredged depth thus calling for over dredging and the cost of mobilization may also be high.
Blasting
In situation where the areas being dealt with have thick layers of rock or there are isolated rocks out crops then blasting may be the best option. Blasting involves drilling holes into sea bed which are closely spaced; the holes are filled with explosives then fired. The drilling of the holes done from above water surface or directly at sea bed. The hydraulic power for operating the machines is supplied a power park located at the shore and it is connected either through a floating or a submerged line. Blasting involve engagement of specialist subcontractors. This method is regarded as being a quick method that can be used where the rocks are of small amount very hard rock (Vellinga, 1984). The current practice involves use of rock-cutter suction dredgers or bucket dredgers in the excavation of large quantities of hard rock (Jan De Nul Group, 2012).
The disadvantages associated with blasting are:
for removal of blast materials grabbing must accompany blasting
it causes obstruction unless done at sea bed
This results to indiscriminate loss of sea life
May involve considerably high mobilization cost
Bucket dredging
The bucket dredger also referred to as ladder dredger is compost of endless bucket chain that scraps the sea bed as the dredger traverses the area being dredged by user of a series of anchor ropes. This method has highly been replaced with cutter-suction dredgers, but some are still in operation up to date. The maximum depth of dredging is about 25 metres with a possibility of 34metres where the largest dredgers of this type are considered with the buckets used have a capacity of 50 litres to 1000litres (ABP Research, 1999).
Advantages associated with this method are
The method is applicable in dredging a level bottom topography
They are applicable in situation involving narrow and restricted areas
There is versatility in dealing with a range of sediments
The side loaded usually will be filled high solids-to-water ratio
The disadvantages of the method are
It will result into obstruction when stationary in navigation channel
This method is interfered with in situations where the seas are rough
Bucket dredging is associated with high noise level and thus they may not be allowed to work at night when the area is in urban setting.
Conclusion
From this paper it has been seen that dredging involves several techniques which can be chosen depending on various factors including the amount of work to be undertaken, the type of material to be dealt with; the need for environment conservation and location of the area as far as human habitation is concerned.
Reference
ABP Research, (1999). Good practice guidelines for ports and harbours operating within or near UK European marine sites. English Nature, UK Marine SACs Project, 20 pp.
Adger, W.N. et al. (2005). Social-ecological resilience to coastal disasters. Science 309: 1036–1039.
Erftemeijer, P.L.A. and R.R. Lewis III, 2006. Environmental impacts of dredging on seagrasses: a review. Marine Pollution Bulletin 52: 1553-1572.
Jan De Nul Group (2012). Dredging and marine works. Australia
PIANC. (1977). Final Report of the International Commission for the Study of the Environmental Effects of Dredging and Disposal of Dredged Materials. Annex to Bulletin No. 27. Brussels, Belgium.
USACE, 1983. Dredging and dredged material disposal. Engineering and Design. U.S. Army Corps of Engineers, Engineer Manual EM 1110-2-5025..
Vellinga T. (1984). Dredging and disposal of contaminated dredged material. Dredging and
Port Construction, Vol. XI, No 12.
Read
More
Share:
CHECK THESE SAMPLES OF Dredging in Ports and Harbor Construction
These pieces of construction not only add to the visual imagery of a geographical location, but also bear testimony to the imagination, craftsmanship and engineering accomplishment of mankind, as represented by the Sydney Harbour.... This unique piece of construction and sheer engineering marvel has contributed to the development and flourishing of human civilizations, since time immemorial.... This paper on the Sydney Harbour Bridge, aims to discuss the various factors critical to this unique and historical piece of construction, such as the history behind its construction, the various materials used, the materials used for its construction; the various equipments used; the availability and use of labour force used during construction; the civilizations and culture that flourished in that era etc....
Apart from the initiative of dredging in the Port Philip Bay with the purpose of expanding the capacity of the Port of Melbourne, another initiative is also taken into concern which includes the expansion of the Port of Hastings.... ‘Melbourne ports-Our Future': Mission or Purpose The mission of the organisation named 'Melbourne ports - Our Future', is to present an appropriate decision in relation to expanding the capacity of the ports of Melbourne....
As such, seaport and harbor planning processes must take into account the roles of the seaport industry and the manner in which how and personnel are supposed to move into and out of the port.... In the planning and design of Seaport and harbor areas, it is of necessity to have roadway systems that will be able to support heavy truck traffic with viable access to interstate highways, including rail system that is capable of catering both to regional and national needs....
This work called "The Dhamra Port" describes the Dhamra port site in Bhadrak district, its rich natural wealth.... The author takes into account the port's long and controversial history, the changes during its development, various impacts on biodiversity of the port site and surroundings, and on marine diversity – turtles, dolphins....
The term paper "Whether Savannah Harbour Expansion Project Is Worth the Shot" discusses the possibilities of the Savannah harbor Deepening Project that is expected to be completed by 2014 and is expected to be achieved following the expansion of the Panama Canal.... Expansion of the Savannah harbor will have numerous impacts on the aquatic organisms through reduction of the dissolved oxygen required for survival of the aquatic organisms, destruction of their habitats while others will be killed by the equipments used in the dredging....
With this concern, the expansion through dredging in the Port Philip Bay is likely to impose a substantial impact upon the environment along with generating various difficulties in terms of technologies and manpower (EnviCom Working Group 100, n.... Concerning the economic area of the policy theory concerning the expansion of the Ports of Melbourne, it can be stated that a port can be described as a site or a position nearby seashore which comprises one or more than one harbor in which the ships can transfer people or cargo from one particular land to another....
The material in this review will be used by ABP in its project expansion and construction plans for consultations and discussions.... These strategies can be adopted by ABP in its construction projects to avert the catastrophic impacts of climate change.... This work called "Carbon Emissions and Journey Times from ABP to London Bridge" describes the key risk identified related to engineering functions and project development goals for the port to London Bridge....
"Understand Building construction" paper states that failure mode and effect analysis is a method for analyzing the reliability of a system so that necessary actions can be made to prevent the problem from happening.... Trade jurisdiction: - this is a trade as is defined by the Board so as to define 'parts of the construction-industry' for the registration....
12 Pages(3000 words)Assignment
sponsored ads
Save Your Time for More Important Things
Let us write or edit the report on your topic
"Dredging in Ports and Harbor Construction"
with a personal 20% discount.