A network diagram is a clear and concise graphical representation of the project schedule and illustrates the project activities and the sequence in which they happen. Network diagrams are an important tool to monitor and track the project from start to its completion. There are…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER92.4% of users find it useful
Project Schedule
Read TextPreview

Extract of sample "Project Schedule"

Part Precedence Relationship A network diagram is a clear and concise graphical representation of the project schedule and illustrates the project activities and the sequence in which they happen. Network diagrams are an important tool to monitor and track the project from start to its completion. There are two types of network diagrams, Precedence Diagramming Method (PDM) and Arrow Diagramming Method (ADM). In Precedence Diagramming Method, nodes are used to represent the activities while arrows are used to show interdependencies among activities. While in Arrow Diagramming Method, arrows are used to represent activities while nodes show relationship and dependences among different activities. Following are few types of dependencies that are used on Precedence Diagramming Method (Sanghera 2008):-
Finish to Start – An acitivity must finish before the next can start
Finish to Finish – An activity must finish before the next activity can finish
Start to Start - An activity must start before the next activity can start
Start to Finish - An activity must start before the next activity can finish
The precedence relationship between the activities in Part 1 is explained below.
Initiating Phase Task 1 and Task 2 start at the same time and have start to start dependency.
Requirement Gathering Phase Task 1 and Task 2 must be finished before the Task 3 is started. Thus these tasks have a finish to start relationship. Similarly, Task 3 must be finished before Task 4 and Task 5, again indicating a finish to start relationship.
Design Phase Task 4 and Task 5 must be finished before Task 6, indicating a finish to start relationship. Task 7 can start immediately after Task 5 has been finished. Thus it has a finish to start relationship with Task 5 and start to start relationship with Task 6.
Development and Testing Phase Task 8 and Task 9 must be started after Task 7 is finished. Thus these have a finish to start relationship. Similarly, Task 10 can start when Task 7 has been finished. Also Task 10 precedes Task 12. All showing a finish to start relationship.
Documentation Phase Task 13 has a finish to finish relationship with Task 8 and Task 12.
Deployment and Testing Phase Task 14 must be started after completion of Task 18. Also Task 12 and Task 14 must be completed prior to starting the Task 15. Also Task 13 and Task 15 must be finished before Task 16 is started. Task 17 must start when Task 12 is finished and Task 8 must be finished before Task 18 is started. All the tasks indicate a finish to start relationship.
Project Schedule is shown on the next page in form of Project Network Diagram. The red lines indicated the project critical path while blue lines show dependencies on non-critical paths. The total duration of the project is 192 days.
Part 2 : Reducing the Project Schedule by One Month
Project Management Institute (2008) defines crashing in its PMBOK as a specific technique for project schedule compression performed, after analyzing and identifying the best compromise between project time and cost, to achieve schedule compression for greatest extent and least increment in cost. For example, if the project has a negative float i.e., estimated completion date is after the desired date; then would you as a project manager asking for more time or you would look for alternate options of schedule compression. In more simplistic manner, Crashing actually finds the answer to questions that if time is to be reduced what can cause least increase in cost? By definition, this always results in higher cost, thus trading time for money. In crashing, it is always appreciated to find the best option or set of options with least negative impact on the project.
Mulcahy and Diethelm (2011) insist that project crashing is always associated with the activities on the critical path because it is the sequence of activities with the longest duration that actually determines the project completion time. Thus introducing such activities on critical path that may result in maximum compression of the project time with minimal increase in the project cost would lead the project to crashing by accomplishing the project activities on a faster pace than before. However, it is not true for all activities since it would yield best results with activities that are compressible and if not then may result in increased risk or unwarranted high costs. Therefore, it is better to identify the critical activities or those activities that exhibit the best ratios of incremental cost to reduced time.
Based on the customer’s request for compressing the project schedule by 30days prior to current completion date, following activities were considered for reducing the time duration.
Task ID
Task Name
Original Duration
Duration after Resource Addition
No of Additional Resources
Cost per Resource per Day
Total Cost per Day
9
Manufacturing of the shell of the machine
40
30
(Reduce by 10 days)
4
500
2000
10
Assembling of the electronic components of the machine
10
10
(No Reduction)
1
700
0
11
Testing of the circuit for accuracy of responses
40
30
(Reduce by 10 Days)
3
300
900
12
Testing of the manufactured machine and calibration to standards
15
5
(Reduce by 10 Days)
1
200
200
Total Additional Cost
3100
With this, change in project schedule and duration is shown on next page. With reducing the duration of Task 9, Task 10 and Task 12 each by 10 days, the overall duration of the project has been reduced to 162 days from 192 days ( a total reduction of 30 days).
References
Mulcahy, R., & Diethelm, L. (2011). Pmp exam prep. (7 ed.). Pennsylvania: RMC Publications Inc.
Project Management Institute (2008). A guide to the project management body of knowledge. (4th ed.). Newtown Square: Project Management Institute, Inc.
Sanghera, P. (2008) Fundamentals of Effective Program Management: A Process Approach Based on the Global Standard. Florida: Jossey Rose Publications. Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“Project Schedule Assignment Example | Topics and Well Written Essays - 500 words”, n.d.)
Retrieved from https://studentshare.org/management/1621099-project-schedule
(Project Schedule Assignment Example | Topics and Well Written Essays - 500 Words)
https://studentshare.org/management/1621099-project-schedule.
“Project Schedule Assignment Example | Topics and Well Written Essays - 500 Words”, n.d. https://studentshare.org/management/1621099-project-schedule.
  • Cited: 0 times
Comments (0)
Click to create a comment or rate a document

CHECK THESE SAMPLES OF Project Schedule

Project plan/Schedule

...? Introduction The method and plan used in project management determine the success or failure of the project (Fox, 2008). As such, this paper seeks to develop a project plan that can adopted by a social service agency that has applied for and received funding for a special project to counsel male drug addicts between 18 and 24 years of age, and to secure full-time employment for each client (or part-time employment for clients who were still in school). The paper starts by outlining major issues related to the concept of project management and how each factor contributes to the success or failure of the project. Project...
8 Pages(2000 words)Assignment

Depreciation Schedule

...Depreciation Methods Introduction There are several ways of computing the depreciation of assets acquired by the company. Two of the depreciation computations include the straight line method and the double -declining method. The following computations will show how these two methods are mathematically done. The depreciation procedures are based on United States Generally Accepted Accounting Principles (Tie, 2005). Body The above excel computation shows that depreciation expense for year 1 is $300. Under the straight line method, the annual depreciation is fixed at $300 per year. The accumulated depreciation is arrived at by adding the current year's depreciation and the all the prior years' depreciation. The book value... Methods...
2 Pages(500 words)Research Paper

A Frenetic Workday Schedule

...A Frenetic Workday Schedule The typical American today goes through a frenetic workday schedule involving brutal working hours and too short vacations. Aggravating this lifestyle is the constant anxiety that surfaced in the wake of September 11. These two factors have led to insomnia becoming a glaring trademark of an overworked and overwrought American society. It was reported that in 2005, 120,000 new insomnia patients were registered in the U.S. (Brandweek Magazine. “Marketers of the Year 2006: Lunesta’s Tim Healey and Jay Popli”); the IMS reported 42 million prescriptions were issued for sleeplessness in 2005 (a 60 per cent increase over 2004 {The New York Times. “Record Sales of Sleeping Pills...
2 Pages(500 words)Article

Project management

...Describe impact of quality initiatives on the project schedule? Quality issues are a major deliverable of any project based concern. The inception ofquality to the project’s value addition activities ensures that the outcomes are either as wanted or even better. While theoretically it seems that initiating quality activities boost the overall deliverability of the project, this may not always be true. When projects are being carried out, the initiation of new quality and value addition activities often tend to redefine the overall project scope. This kind of redefinition has two direct impacts on the project – increasing the amount of previous resource allocation, as well as boosting the costs of the project. For most projects... , it is...
1 Pages(250 words)Essay

Develope a project schedule

...Project Schedule This section presents a quick review of the activity list that was presented earlier. The first, group of list has been categorized as initiation of the project. Together, the various activities here set the pace for the main project to begin. As of this stage, nothing tangible or concrete regarding the project will be done. Rather, a series of negotiations that concern the success of the project. The major activity under the initiation shall be a feasibility study, which shall be a confirmation of the merits and possibility of achieving the set goals. The next group of lists comes under the planning of the...
2 Pages(500 words)Essay

Work Schedule

...WORK SCHEDULE Executive summary The Acme Mexico store is planning to open in the near future. A lengthy and vigorous hiring and training process will take place when it is opened. In order to staff these positions efficiently and effectively there are a variety of considerations that must be taken into account. This will have to coincide with the Mexican labor laws, Mexican Culture, employees contracts and direct and indirect costs (Ronen, 2001). Some of this cost includes full time and part time wages , training expenses, employee housing expenses, employee retirement insurance and overtime costs. Given this consideration, it is imperative to come up with a low cost customer service employee daily assignment schedule. The aim... of this...
2 Pages(500 words)Assignment

Cash flow schedule

...The Freedonia Bauxite Terminal Project Content Introduction 2 Tender Sum 2 Cash Flow Schedule 3 Cumulative Cash Flow Schedule 4 Revised Tender Sum 5 Revised Cash Flow Schedule 5 Cumulative Cash Flow Schedule 6 References 7 Appendix 1 8 - 14 Appendix 2 15 -22 Introduction This paper looks at the amount tendered or the contract value, cash flow schedule and cumulative cash flow schedule of the Freedonia Bauxite Terminal Project. The project is expected to last for 24 months and the assumption is that work on...
4 Pages(1000 words)Assignment

Project Management Capstone - Schedule, Budget, and Controls

...Schedule, Budget and Controls Schedule, Budget and Controls Scheduling and budgeting is a very important in implementation a strategy for an organization. In addition, control is paramount for the success of any schedule or budget. In this essay, I determine the tools that would work best for me in developing your schedule and budget. I also identify the simple methods for monitoring and controlling the schedule and budget. Finally, I identify the specific tools that you are proposing to use for this project. Tools to be used in Schedule and Budget Development Given that preparation of a...
4 Pages(1000 words)Assignment

Project Management: Project Portfolio. Project: Planning a wedding in the Bahamas: project charter, schedule of tasks, statement of work, communications plan, work breakdown structure, milestone list

...a wedding at the Atlantis Resort Beach within 6 months of the time period. Management has divided main objective into small objectives to achieve this objective that includes: Schedule tasks and allocate them to appropriate people Setting milestone for each task to timely complete every task Prepare work breakdown structure Monitoring and maintaining statement of work Embrace effective communication plan and maintain quality standards throughout POTENTIAL MANAGEMENT ISSUES: There can be many issues that could manipulate the performance of the project team. These problems could also affect the project’s budget and deadlines (Heagney, 2011). The potential management issues can be: Using...
8 Pages(2000 words)Term Paper

Schedule Recovery

...Schedule Recovery Q What strategy would you use to address the delayed flight? Answer: Out of the several strategies in flight schedule recovery, aircraft swapping would be the best alternative for delayed flight WA 1269 under the given circumstances. Q.2 Why did you choose this strategy? Answer: Since the airline uses two aircrafts- the Boeing 737- 700s, aircraft A and aircraft B, for the network flight schedule, the two aircraft are hence identical. The effect of this swapping results in no passenger disruption of flight WA 1269 and 20- minute delay for flight WA 1270 as it will arrive in PHX at 1500h local time instead of the scheduled 1440h. But this is of less cost...
2 Pages(500 words)Essay
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.

Let us find you another Assignment on topic Project Schedule for FREE!

Contact Us