Project Management - Essay Example

Comments (0) Cite this document
Summary
Project Management Name of the Author Author’s affiliation Author’s note with information about affiliation, research grants, how to contact.Task 1 Draw the network diagram Activity Time Required Immediate Predecessor Activities EST EFT LFT LST (Days) A 4 - 0 4 4 0 B 5 A 4 9 12 7 C 4 A 4 8 12 8 D 8 A 4 12 12 4 E 6 A 4 10 12 6 F 2 A 4 6 12 10 G 13 B,C,D,E,F 12 25 25 12 H 8 G 25 33 33 25 I 7 H 33 40 40 33 J 6 H 33 39 40 34 K 8 I,J 40 48 48 40 L 13 K 48 61 61 48 M 9 L 61 70 70 61 N 4 M 70 74 74 70 O 5 B 9 14 86 81 P 12 N 74 86 86 74 Q 2 O,P 86 88 88 86 1) Explain how you determined the timing of activities and total float The Earliest Start time (EST) is 0 day for the first activity i.e…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER92.1% of users find it useful
Project Management
Read TextPreview

Extract of sample
"Project Management"

Download file to see previous pages Earliest Finish Time (EFT) = Earliest Start Time (EST) + Duration Latest Start Time (LST) is calculated by adding float to LST of the critical activity in the group. Latest Start Time (LFT) = Latest Start Time (EST) of critical activity + total float Latest Finish Time (LFT) is calculated by adding duration to LST of the activity. Latest Finish Time (LFT) = Latest Start Time (LST) + Duration Total Float is calculated by subtracting The Earliest Start time (EST) and duration from Latest Finish Time (LFT). Total float = LFT - EST - duration 2) Explain how you determined the project duration and the critical path In order to calculate the project duration, we first need to identify critical path. A critical path is the one that holds series of dependable activities which as whole gives the longest time to complete the project and these activities within critical path are called critical activities. In other words, it is series of activities with “Zero total Float” (Newell, 2005). ...
Time Required Immediate Predecessor Activities EST EFT LFT LST (days) A 4 - 0 4 4 0 B 5 A 4 9 12 7 C 4 A 4 8 12 8 D 8 A 4 12 12 4 E 6 A 4 10 12 6 F 2 A 4 6 12 10 G 13 B,C,D,E,F 12 25 25 12 H 8 G 25 33 33 25 I 7 H 33 40 40 33 J 6 H 33 39 40 34 K 8 I,J 40 48 48 40 L 13 K 48 61 61 48 M 9 L 61 70 70 61 N 4 M 70 74 74 70 O 5 B 9 14 86 81 P 12 N 74 86 86 74 Q 2 O,P 86 88 88 86 PROJECT DURACTION 88 DAYS   Critical Path 3) If the project starts on the Monday 7 January 2013, what is the earliest date it can be completed using a 5 working day week? Assume no holidays. If the project starts on the Monday 7 January 2013 On the basis of 88 days of total project duration, the earliest date when the project can be completed is the 8th of May, 2013. The date is calculated by counting 88 days from 7 January, 2013 excluding Saturday and Sunday. 4) If the following happened what would be the effect on the duration of the whole project? a) Activity B is delayed 1 day. Activity B is not a critical activity and has total float of 3 days, 1 day delay during activity B will not affect the duration of the whole project. b) Activity P is delayed 1 day. As activity P it is a critical activity, a 1 day delay during activity P will increase the duration of the whole project by 1 day, thereby making it to 89 days. c) Activity O is delayed 2 day. Activity B is not a critical activity and has a total float of 72 days, 1 day delay during activity B will not affect the duration of the whole project. 5) Limitations of network diagrams The main limitation of a Network diagram is: do not clearly show time line for a project, it is difficult to update, do not lead to easy distribution and the tools can be expensive to acquire. TASK 2 Abstract The project management main goal is delivering a project ...Download file to see next pagesRead More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“Project Management Essay Example | Topics and Well Written Essays - 2500 words - 3”, n.d.)
Project Management Essay Example | Topics and Well Written Essays - 2500 words - 3. Retrieved from https://studentshare.org/management/1403383-project-management
(Project Management Essay Example | Topics and Well Written Essays - 2500 Words - 3)
Project Management Essay Example | Topics and Well Written Essays - 2500 Words - 3. https://studentshare.org/management/1403383-project-management.
“Project Management Essay Example | Topics and Well Written Essays - 2500 Words - 3”, n.d. https://studentshare.org/management/1403383-project-management.
  • Cited: 1 times
Comments (0)
Click to create a comment or rate a document
CHECK THESE SAMPLES - THEY ALSO FIT YOUR TOPIC
Project Management
...?Project Management Project management, as the implies is the management of any project. Management of a project includes several tasks that areranged right from the conception of the project’s idea till its culmination and delivery. Tasks included in the management of a project include but are not limited to assessment of risks before in the initial stage, identification of ways to mitigate those risks and preferably their conversion into opportunities, estimation of monetary, human and all other kinds of resources and their arrangement, acquiring...
6 Pages(1500 words)Essay
Project Management
...? Contents Introduction 3 Phases of a Project 5 Conceiving a Project 5 Planning Phase 5 Implementation Phase 6 Assessment and Delivery Phase 7 Risk Management in Projects 7 Types of Change 8 Nature of Managing an IT Project 10 Recommendations 10 Reasons for Failure of NHS IT Project 11 Conclusion 11 References 12 Project Management Introduction Managing projects is a tedious and painful business, because majority of them are supposed, to be completed within specified period, to achieve certain goals and objectives. All of the projects...
10 Pages(2500 words)Essay
Project management
...?Project Management: The Energy Generation Project This paper examines a project scenario from the viewpoints of organisational structure, procurement strategy and scheduling. It outlines an appropriate organisational structure and considers potential issues relating to people management within the project. It then discusses possible approaches to procurement, identifying and justifying a procurement strategy for the different phases of the project lifecycle, including consultant appointment processes and contract types. Finally, a detailed schedule for the duration of the project will be provided that is fit for the purpose of managing the pilot project. Organisational Structure Project Team Structure The project is to be managed... by a...
18 Pages(4500 words)Assignment
Project management
...? Project Management - A Project to Improve Multi-Agency Response to Road Traffic Collision through Joint Training and Exercises - Student Number Course Name and Number Name of Professor Date of Submission Number of Words: 1,250 Introduction Traffic collision or vehicular accidents increases the number of controllable deaths. On top of the increasing number of unnecessary deaths caused by traffic collision, inattention or disturbances that could affect the driver’s concentration while driving often leads to physical or mental injuries to themselves or other people around them (Johns, 2007). Several studies revealed that majority of traffic collision is caused by human factors related to...
5 Pages(1250 words)Coursework
Project management
...? REPORT Project Management Total word count: 2800 Keywords: Project Management Table of Contents Task Jonijanti Ltd 3 Task 2 - Tibob and Tibob Ltd 7 Project Background 7 Phase 1 – Project Conceptual Planning 8 Phase 2 – Project Planning (Project Development Phase) 8 Phase 3 – Implementation and Control 10 Phase 4- Evaluation of the Project 11 Project Manager Skills and competences 11 Conclusion 11 References and used Bibliography 13 Appendix 1 AON Network Diagram 15 Appendix 2 GANTT Chart 16 Task 1 - Jonijanti Ltd Total word count: 600 without the...
10 Pages(2500 words)Essay
Project management
...? One of the most important tasks a project manager has to comply with is to have good communication among the team players. “The ability to communicate effectively is necessary to carry out the thoughts and visions of an organization to the people” (Marketingdeviant, 2009). The project manager is the person responsible to deliver the project on a timely manner complying with all the deliverables of the project. Janis was selected as the project manager to build a new plant in Alabama. The company empowered Janis and they put Clark, Downs, and Pokorski at her disposal. Janis is in a position of power and she has to create an effective communication plan to ensure the success of the project. The first step in the communication plan... by...
3 Pages(750 words)Essay
Project Management
...?Project Management Section 2: Baselining Cost Variance for Kindergarten Planning Project The required tasks to complete the deliverable for the work package, kindergarten planning, are being planned and expected to be completed by April 27 July 2014 and use 584days of work. The following tables indicate the progress of the required tasks. Table 1: Cost Variance Kindergarten Planning Name of Task Cost (Total) Baseline Variance Actual Remaining Kindergarten Planning $20,148.00 $18,964.00 $1,184.00 $13,658.00 $6,490.00 User requirements $6,132.00 $6,540.00 ($408.00) $6,132.00 $0.00 Preparatory meeting $3,072.00 $2,560.00 $512.00 $3,072.00 $0.00 Staff training $5,084.00 $4,004.00 $1,080.00...
4 Pages(1000 words)Essay
Project Management
...of project success (Josler & Burger, 2005). Basically, the term project is used to describe a set of activities that are linked and they are directed towards the attainment of a certain goal (Hellriegel 2001). A project can also be described as a onetime activity with a definite start and finish. As such, through utilization of project management methodology, a project can be completed within the expected time frame, on budget as well meeting the expected standards that satisfy all the stakeholders who may be involved. In this case, the baseline of the project is to carry out a feasibility study to establish if the...
8 Pages(2000 words)Essay
Project management
...of new software to address green computing for internal use and potential sale to other organizations – IBM has developed a number of software to facilitate greener computing. This has not only reduced to amount of energy required but also reduce the need for hardware and the use of resources that would increase climate change. Task 2 Weighted Decision Matrix for Green Computing Project A weighted Decision Matrix is used to determine which of the four candidates for the position of Project Manager for the Green Computing Project would best fulfill the role. In addition to technical skill which is the least important of the five criteria chosen, communication skills;...
10 Pages(2500 words)Research Paper
Complex Project Management of Effective Project Management
...Part III Complex Project Management Part III Complex Project Management In a complex project, at least some of the goals and solutions may not be clearly identifiable and known at the project’s outset. As a result, project management models may not work and thus, adjustments should be made. In projects whose objectives are clearly defined but lack solutions in later parts, referred to as APM projects, the main issue is that even in situations where the solution is discovered, it may not deliver acceptable business value. This leads to the first step of dealing with...
6 Pages(1500 words)Assignment
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Let us find you another Essay on topic Project Management for FREE!
logo footer
Contact us:
+16312120006
Contact Us Now
FREE Mobile Apps:
  • StudentShare App Store
  • StudentShare Google play
  • About StudentShare
  • Testimonials
  • FAQ
  • Blog
  • Free Essays
  • New Essays
  • Essays
  • Miscellaneous
  • The Newest Essay Topics
  • Index samples by all dates
Join us:
Contact Us