StudentShare
Contact Us
Sign In / Sign Up for FREE
Search
Go to advanced search...
Free

Cost of Software Estimation - Coursework Example

Cite this document
Summary
The paper "Cost of Software Estimation" highlights that determination of function points begins with the estimation of the external interface files, external queries, external inputs, external outputs, and logical internal tables.  Eternal inputs are basically the data entry screens…
Download full paper File format: .doc, available for editing
GRAB THE BEST PAPER92.1% of users find it useful
Cost of Software Estimation
Read Text Preview

Extract of sample "Cost of Software Estimation"

of affiliation: Estimating software cost is a fundamental step in software development process. This part of the process determines if carrying on with the project is worthy or not. Every software project development aims at developing a system that will meet all the pre stated requirements within the least possible cost. In the recent days, researchers have identified poor costing and scheduling of software development projects as the leading cause of failures in majority of the projects (Sommerville, 2007). This study placed poor estimation of software cost before other causes that included political, technical or development team problems. Additionally, this study found out that only a few software companies had a good understanding regarding this matter, with only a small, percentage taking it as a science and not merely an art. This work details a step by step approach to estimation of software cost and schedules. The Estimating Lifecycle In the initial stage, the program developers require to build an in-depth knowledge on the software cost estimating limitations at the macro level. As we will see in the next diagram, accuracy of cost estimate is frequently determined by the present software development stage. Early uncertainty in the estimation process is largely founded on variances in the input parameters to the estimate while later uncertainties to the variance of the models used. At the start i.e. the concept level, developers may get a definition of the project which is unclear. Here, it is possible to recognize the general purpose of the new software despite the limited knowledge on the requirements. Typically, for an experienced estimator, the estimates at this point will depict an accuracy of ± 50% when using informal methods such as group consensus or historical comparisons (Londeix, 2008). Macro Lifecycles 50 25 10 Typical Cost Estimating Accuracies Once the requirements have been understood to a convincing level, preparation of function-oriented estimate begins. Here, an experienced estimator will come up with estimates depicting an accuracy of ± 25% when using the methods outlined above. On completing the detailed design, the developers roll in the final stage which entails preparation of the implementation –oriented estimate. This estimate frequently depicts an accuracy of ±10 %. In all these, the key point is recognizing the significance of periodic re-estimates although the project lifecycle, a factor that will enhance identification of problems in the early stages and allow corrective actions to be taken (Trendowicz, 2013). Estimating Program Volume Program volume is the other factor considered when coming up with the costing of prospect software. While coming up with an estimate of the project volume, developers can choose the use the SLOC, or number of source line codes. SLOC refers to a human written line of code which typically is neither a comment or a blank line. Here, caution is taken not to recount any line, particularly in cases where the code is used several times in the application. It should be noted that project developers usually work on related number, thousands of KSOC, or SLOC, when estimating. The COCOMO (Constructive Cost Model) is the most common estimating metric used in such cases. A simplest estimate using this model requires the developer to first know the number of KSLOC to be written and the effort required for each KSLOC. These two variables are multiplied to get the person months of effort required by the project to come to its completion. Basically, this concept is central in the estimating models. The table below shows some common values identified by researchers that relate to this linier productivity feature. Project Type Linear Productivity Factor COCOMO II Default 3.13 E-Commerce development 3.08 Embedded development 3.60 Military development 3.97 Web development 2.51 Using this approach lets attempt building an e commerce entailing 15,000 Code lines. Here, computation of person’s months of efforts will be done using the following equation. Productivity x KSLOC = 3.08 x 15 = Effort = 46 Person-Months In cases where the projects are relatively small, this basic equation will be found handy. Past studies have however identified variation in productivity depending on project size. As a matter of fact, large projects have been significantly shown to be less productive as when compared to small projects. This has been explained citing a probable combination of increased communication and coordination time, in addition to more rework requirement caused by misunderstandings (Qi, 2013). The established productivity decrease following the increase in project size is solved by raising the figure of KSLOC to a figure bigger than 1.0. The exponential factor used is used to penalize large projects for reduced efficiency (Hill, 2011). The table below gives examples of well known size penalty of several project types. Project Type Exponential size penalty factor COCOMO II Default 1.072 E-Commerce development 1.030 Embedded development 1.111 Military development 1.072 Web development 1.030 Using our example of e commerce we can then compute the number of persons months of efforts required to complete our 15,000 lines of code. The computation will be as follows: Productivity x KSLOC Penalty = 3.08 * 15 1.030 = 3.08 x 16.27 = Effort = 50 Person-Months Up to this point we can see a straight forward flow of events; however, it will be important to ask the question as to whether the project gets to the 15000 SLOC. Two approaches namely “function points with backfiring” and direct estimation can help developers unfold this dilemma. In this approaches, the determination of the fundamental input variables follows an expert’s opinion, with developers functioning as the experts (Trendowicz, 2013). Typically, the initial stage of estimating number of code lines entails breaking of the project into modules. A good example of this process involving a high level breakdown is one which takes a front-end processes; data base code and middle-tier processes. The developers use their experience to build similar systems with their focus placed on estimating the number of lines of code required. It is strongly recommended that developers get three estimates for every input variable used i.e. Expected case; the best-case and worst-case estimates. These three estimates are then used to compute the mean and standard deviation as shown below: Mean= Standard Deviation= Standard Deviation measures how much deviation is possible in the final number. For instance, the mean + 3(standard deviation) ensures there is 99 percent probability that the project is under the estimate (Pfleeger, Wu, & Lewis, 2010). Estimating Function Points Another option is to begin with function points followed by a process called backfiring that helps convert the function points to SLOC. This method was first used by IBM to measure program volume. In this case, the program functionality (which translates to its cost) is considered based on the number of ways it must interact with users. Determination of function points begins with the estimation of the external interface files, external queries, external inputs, external outputs, and logical internal tables. Eternal inputs are basically the data entry screens. In the cases where the screen contain tabbed notebook or related metaphor then the tabs are considered as external input separately. External interfaces files arise from files which are based outputs or inputs. The entire record format in the file, or each data object type in the case of XML, would be taken separately as an interface file in all cases. The reports are taken as the External outputs and external functions or messages based communications going in or out of the application as external quarries. Lastly, logical internal tables constitute the number of the database tables (Boehm, 2000).Conversion of raw values into actual function point’s count entails multiplication of the raw numbers using a conversion factor drawn from the following table. Raw Type Function Point Conversion Factor External inputs 4 External interface files 7 External outputs 5 External queries 4 Logical internal tables 10 Taking a case in which 25 data entry screen, 15 reports, 5 interfaces, 20 logical internal table and 10 external queries are presented we can calculate functional points in the following g way. (25 x 4)+ (7 x5) + (15 x5) + (10 x 4) + (20 x 10) = 450 Function Points Now that the function points have been calculated, the only remaining step is to employ backfiring in converting points to SLOC. This is accomplished by using a language equivalencies table (Bennatan, 2009). The table below presents some of the common values: Language SLOC per Function Point C++ default 4 Cobol default 7 Delphi 5 5 HTML 4 4 Java 2 default 10 Let us take an example of an implementation which uses java to complete the above project (50 function points). Calculation of SLOC will be as follows: 450 x 46 = 20,700 SLOC Assuming this was an e commerce system, the project would require the following effort to implement. Productivity * KSLOC Penalty = 3.08 * 20.7 1.030 = 3.08 * 22.67 = Effort = 70 Person-Months References Bennatan, E. M. (2009). On time within budget: software project management practices and techniques (3rd ed.). New York: Wiley Boehm, B. W. (2000). Software cost estimation with Cocomo II. Upper Saddle River, NJ: Prentice Hall. Hill, P. R. (2011). Practical software project estimation a toolkit for estimating software development effort & duration. New York: McGraw-Hill. Londeix, B. (2008). Cost estimation for software development. Wokingham, England: Addison-Wesley. Pfleeger, S. L., Wu, F., & Lewis, R. (2010). Software cost estimation and sizing methods: issues, and guidelines. Santa Monica, CA: Rand Corp.. Qi, E. (2013). The 19th International Conference on Industrial Engineering and Engineering Management. Berlin: Springer. Sommerville, I. (2007). Software engineering (8th ed.). Harlow, England: Addison-Wesley. Trendowicz, A. (2013). Software cost estimation, benchmarking, and risk assessment the software decision-makers guide to predictable software development. Berlin: Springer. Read More
Cite this document
  • APA
  • MLA
  • CHICAGO
(Cost of Software Estimation Coursework Example | Topics and Well Written Essays - 1250 words, n.d.)
Cost of Software Estimation Coursework Example | Topics and Well Written Essays - 1250 words. https://studentshare.org/information-technology/1830565-how-do-you-estimate-the-cost-of-software-to-be-developed
(Cost of Software Estimation Coursework Example | Topics and Well Written Essays - 1250 Words)
Cost of Software Estimation Coursework Example | Topics and Well Written Essays - 1250 Words. https://studentshare.org/information-technology/1830565-how-do-you-estimate-the-cost-of-software-to-be-developed.
“Cost of Software Estimation Coursework Example | Topics and Well Written Essays - 1250 Words”. https://studentshare.org/information-technology/1830565-how-do-you-estimate-the-cost-of-software-to-be-developed.
  • Cited: 0 times

CHECK THESE SAMPLES OF Cost of Software Estimation

Project Management in IT Industry

The review of all the six areas of project management clearly defines significance of each area in the execution, delivery and implementation of the software project.... Product is the needs of the customers constituted into tasks and positioned for action by the software team.... Product is the needs of the customers constituted into tasks and positioned for action by the software team.... The first factor is time, second is cost and the third is performance....
10 Pages (2500 words) Essay

Planning and Design

It also enables to make assessment of the amount of time required to complete the project, so estimation can be made regarding the budget of the project and whether the project would require over-budgeting or not (Public Procurement Guide, 2008).... With this concern, Spencer Moneysworth consulted with Expert Industrial Developers (EID) regarding making an estimation of cash flow chart for the project.... Moreover, the cost planning of EID depicts an excessive use of capital along with making an estimation of longer schedule for the plan including professional services and construction works....
8 Pages (2000 words) Essay

Project Times and Cost

This will enable the manager to make informed decision on how much the cost of completing the construction would be without making any losses.... In fact, poorly managed project shows such symptoms majorly because of inaccuracies that existed during estimation or estimations were totally absent Project managers usually need to make good and informed decisions concerning the amount of the estimates that they require for the specific projects.... These are questions that can only be responded to well by carrying out accurate estimation of both costs and time....
5 Pages (1250 words) Assignment

Mini-Project (Third)

For example, software for the production train had to be rewritten and the building could not house the production train.... The project failures concerning financial planning, cash flow, cost control, costs incurred etc.... It could have been a more economical option than allowing the cost plus alternative that EID implemented with a high level of uncertainty....
4 Pages (1000 words) Essay

Estimation Techniques - Work Breakdown Structure

This paper under the headline "estimation Techniques - Work Breakdown Structure" focuses on the fact that work breakdown structure is used in planning effectively for a project by breaking down the key tasks or activities into smaller manageable units of work....   estimation techniques Insert Insert estimation techniques I.... High risk software project- Work breakdown structure because it effectively manages the risks involved in a project....
1 Pages (250 words) Essay

IT Project management

Since inaccuracies in estimation result in uncertainties, it is always good to work and reduce inaccuracies in the early stages of software development.... utsourcing most of the resources will cause lack of co-ordination between the contractors, time wastage and push up the cost of the project.... The aims of estimation are to determine the amount of effort required for the project, the cost and Hajes M Aldosari James Nowotarski IS 430 15 November Question Below is a WBS for introducing self-checkout registers in our school's bookstoreQuestion 4The first risk is the pressure on the project implementation team to deliver the project within a short period of time....
2 Pages (500 words) Essay

Contracting for IT Software

In essence, the SLOC (Sources Lines of Code) and Function Points are some of crucial methods applied in the estimation of software project development costs (Mislick and Nussbaum 9).... Elements of software Project Management.... Three types of SLOC methods are used in project costs estimation.... The physical SLOC is the most common in the development cost estimation process (Sudhakar 80).... It is vital to note that the use of function points is another crucial method used in the estimation of IT software project costs....
2 Pages (500 words) Case Study

Government Contracting Company

The paper “Government Contracting Company” explains estimation and it's relevance to the Government contract.... hellip; The author defines cost estimation as the iterative process of approximating and developing of the monetary resources which are needed to finish the project activities.... Government Contracting Company This is to explain estimation and it's relevant to the Government contract.... It's very important for every manager to be very keen and have knowledge on various industry technique and the needed tools in the execution and definition of project cost estimation....
2 Pages (500 words) Assignment
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Contact Us