Our website is a unique platform where students can share their papers in a matter of giving an example of the work to be done. If you find papers
matching your topic, you may use them only as an example of work. This is 100% legal. You may not submit downloaded papers as your own, that is cheating. Also you
should remember, that this work was alredy submitted once by a student who originally wrote it.
"Risk and Safety Engineering" paper lists 5 possible hazards and carries out a hazard analysis bases on a checklist and describes how you might use the FMECA approach to identify system hazards and produce a fragment of the FMECA table of the system. …
Download full paperFile format: .doc, available for editing
Task a
a) List 5 possible hazards and carry out a hazard analysis bases on a check list
Hazard associated with the systems include
Spilling of the gas mixture due along the pipe work
Explosion of the tank due to failure of relieve valve
Pump failure
Rupture at heat exchanger
Check list
Is the relief valve (RV) in good working condition?
Is Level Indicator (LI) in working condition?
Is low level indicator (LLA) in good working condition?
Is the pump in good working condition?
Is pump of the appropriate size?
Is Flow Recorder Controller (FRC) in good working condition?
Task b
Use of HAZOP technique in identification of causal events and hazards
HAZOP means is important as it entails detailed hazard and operability problem identification process which is undertaken in teamwork and this definition is a clear indicator of how the process is important in identifying the causal events and hazards. Use of HAZOP will involve identifying potential deviation in the design intent, the possible cause of deviation is examined and a consequence of the same is also assessed. The main features associated with HAZOP are
The process of examination is creative and it proceeds in a system way where a series of guide words are used in identification of any likely deviation in the design. The deviations are used to trigger team members discern the way the deviations are likely to happen and the consequences of the same.
The examination is to be undertaken with guidance being offered by a study leader who is trained and who will ensure that the system is covered comprehensively where there will be logical and analytical thinking. All the proceedings are recorded by recorder who is assigned to help the study leader with this task and the and this makes it possible for further evaluation to be done on the hazards and operational disturbances
Specialists from relevant fields are relied upon for examination and this ensures that intuition and good judgment as they have the required skills and experience.
The examination is carried in an atmosphere of positive thinking and free discussion and any problem identified is recorded so that it can undergo further assessment and resolution
HAZOP is based on a “guide word examination” where there is deliberation to search for deviations in design intent. Examination is facilitated by putting the system into parts in a manner that will make it possible for design intent for the parts can be defined adequately. The choice of the size part is dependant on how complex the system and severity of the hazard. The design intent for a part of a system will be composed of items that convey the important features the part and this will enable the part to be divided naturally.
The HAZOP studies have a lot of importance attached to the such that if a nominated team member happens to fail to attend any session, this would be regarded as being a very serious breach of plant safety management procedures. This failure to attend means that the other attendees would have put their time to waste as they wait input from the absent team member. After the assembling of the data and drawings, the team leader would be in a position to plan review meetings with estimation of meeting time for the study being the first priority. The role of the thumb is that a process section would be expected to last 20-30 minutes. For examp application of the rule would require a vessel having two inlets and two exits and a vent to take a total of two hours. This makes it possible for the leader to be able to make an approximation HAZOP meeting time requirement by putting into consideration the process sections that are to be dealt with. Allowing two to three hours for major equipment is another way of making an approximation. The leader goes on to make arrangements for review meeting upon making estimations for meeting time. Carrying on too long in a sitting or taking too many hours in a day or having many days in a week are considered undesirable. Thus the desire is an individual meeting not going beyond three hours non stop and two sessions per day preferably one in the morning and the second in the afternoon. If the HAZOP studies are require about six hours it is recommended that time per week should not go beyond three or four days a week.
No
Guide
word
Element
Deviation
Possible
causes
Consequences
Safeguards
Comments
Actions
required
1
LESS
TRANSFER
PRODUCT
LESS PRODUCT
TRANSFERED
Wrong pump
Fitted
FRC fail
Rupture in heat exchanger
None
unacceptable
Check pump
2
MORE
TRANSFER
PRESSURE
More pressure
RV fail
Tank bursts
None
Unacceptable
Check pump
Check RV
3
AS WELL AS
Valves /pipes
As well as to valve
Valves/pipe leaks
Environmental contamination
Possible explosion
Use accepted piping standard
Use flow sensor
4
NO
Transfer material
No transfer of material
Pump fails
Explosion
Unacceptable
Check pump
5
NO
Transfer material
No transfer of material
Valve fail
Explosion
Unacceptable
Check valve
Task c
Describe how you might use the FMECA approach to identify system hazards and produce a fragment of the FMECA table of the system described above (include about 5 items).
FMECA approach is useful in the identification of system. In this approach all failure modes for each level of assembly or function analyzed is identified a description given and analysis done. Which the chance of a failure mode having more than one cause, all likely causes at lower assembly levels or what is regarded as subordinate functions are usually put into consideration. In the FMECA approach failure modes such as premature operation; intermittent operation, operation not taking place at the expected time etc. the failure focuses on specific assembly or function that is being affected by the mode of failure under consideration. The approach takes note of the fact that failure modes are likely to effects on other levels assemblies or functions and thus each failure mode is established in terms of local effect, effect on next higher level of function and the effect on the system in totality. It is also a requirement that FMECA be conducted by reliability engineers, design staff and any other party who may be interested.
FAILURE MODE EFFECT AND CRITICALITY ANALYSIS
System
Assessor
Date assessed
Subsystem
Sheet
Date reviewed
Reference
Or Item No
Function
Process
Function
Potential
Failure mode
Potential effect
Potential cost
Risk rating
Corrective
action
Revised risk
OCC
SEV
DET
RPN
OCC
SEV
DET
RPN
1
TRANSFER
PRODUCT
Wrong pump
Fitted
FRC fail
Rupture in heat exchanger
3
10
3
90
2
TRANSFER
PRESSURE
RV fail
Tank bursts
2
10
2
40
3
Valves /pipes
Valves/pipe leaks
Environmental contamination
Possible explosion
3
10
3
90
4
Transfer material
Pump fails
Explosion
2
10
3
50
5
Transfer material
Valve fail
Explosion
2
10
3
50
Task d
Task e (1)
Tolerable Risk Criteria
There are a number of methods which may be used in expressing risk tolerability where there is variation from one operator to another, variation in cultural setting as well as regulatory environment in the setting of the project. In qualitative criteria there will be use of descriptive words such us remote, probable, frequent unlikely in describing likelihood that the event will occur and the consequences of occurrence will be described by words like catastrophic, major or minor. In order to ensure that there is consistency in application of the criteria quantitative numbers are introduced so as to provide a definition on how the words are to be interpreted unlikely may mean occurrence that is may be witnessed once in 10 to 100 years. Qualitative interpretation is involved because the numerical predictions that are made have some level of uncertainty.
Task e (2)
E is consequence parameter for this case E4 (catastrophic) = 1
P is possibility of failing to avoid hazard parameter =P2 = 0.01
Therefore SIL = 1x0.01= 0.01
References
Dean S. (1999) IEC 61508 – Understanding Functional Safety Assessment.
Sauf Consulting Ltd
Read
More
Share:
CHECK THESE SAMPLES OF Risk and Safety Engineering
safety engineering tries to lower the occurrence of failures, and make sure that when failures do happen, the results are not life-threatening.... This research is being carried out to evaluate and present health and safety risk assessment in civil engineering projects.... Health and safety in the field are about measures designed to protect the health and safety of workers, visitors and the general public who may be affected by workplace activities....
The paper 'System safety engineering and Risk Assessment' presents accident investigation which is the analysis of an accident so as to identify the causes and prevent any possible occurrence in the future.... Accident investigation encompasses three key steps.... ... ... ... Accident reporting involves filling in two kinds of forms within 24 hours of the occurrence of the incident....
The paper "Health, Safety, and Risk Assessment in an Engineering Workshop" underlines that Health and safety managers have a significant role in making sure that a balance between health initiatives in the organization and initiatives that lead to the generation of profits.... The contractor does not have legal authority not to comply with provisions in the health and safety management schedule.... This regulation ties the contractor to abide by all approved codes and carry out his duties as described in the health and safety legislation....
It is very important to understand fire safety engineering along with its effects on the design, planning as well as construction of building structures.... Fire safety engineering is the application of scientific as well as engineering principles to the effects of fire so as to minimize losses of life and destruction to the property by quantifying the dangers and risks incurred along with providing an optimal solution to the application of protective measures....
"Risk and Safety Engineering, Operability Technique, FMECA Approach in the Identification Hazards" paper is concerned with the identification and elimination of hazards whose inherent existence in the system may be brought about with other failures.... The adoption of a quantitative approach with regard to the fault tree analysis of this system involves a series of development safety considerations.... Further, it involves the application of a Quantitative Risk Analysis, which simplifies the application of IEC 61508 for the safety requirement standards for the Equipment under Control....
This assignment "Fire safety engineering and Fire Services Engineering" discusses the safety levels of a fire system that is done in five main stages which are: the preparations of the fire engineering stage, the analysis stage the data collection and evaluation stage, and finally the report writing stage.... (Horasan et al 1994) Difference between fire safety engineering and fire services engineeringFire safety engineering is the process of using fire engineering information to be able to design or do an evaluation of a fire safety strategy whereas fire services engineering refers to the designing of fire detection and suppression systems....
The assignment 'Health, Safety And Risk Assessment In Engineering' is devoted to occupational health and safety at the workplace.... Task 1: Identify industrial work areas where current regulations would arise and describe the role of the HSE inspectorateYou are monitoring for health and safety purposes a team of welders who have to undertake welding repairs to a coastal tanker.... There are specific pieces of health and safety legislation that is applicable to all employees, undertaking welding on board a coastal tanker....
It is also done to comply with health and safety authority regulations, which demand that organizations undertake a risk assessment to reduce employees' risk exposure.... he rationale for health risk assessment at the workplace is to help manage the health and safety of a business and to control the inherent risks.... There is sufficient evidence that specifies the existence of risks, as indicated by the Health and safety Statistics Annual Report for Great Britain for 2014/2015....
13 Pages(3250 words)Coursework
sponsored ads
Save Your Time for More Important Things
Let us write or edit the assignment on your topic
"Risk and Safety Engineering"
with a personal 20% discount.