Nobody downloaded yet

The Scottish Parliament Building - Book Report/Review Example

Comments (0) Cite this document
Summary
The Scottish Parliament Building was in its planning stages in 1997 when the submissions for accommodation where made. The earliest cost estimates, in April 997, of the building were between £24.5 million and £34 million…
Download full paperFile format: .doc, available for editing
GRAB THE BEST PAPER92.4% of users find it useful
The Scottish Parliament Building
Read TextPreview

Extract of sample
"The Scottish Parliament Building"

Download file to see previous pages There is question as to what the £10 million figure would have covered, as it was likely to cover “no more than the minimal refurbishment of the Old Royal High School….it would only have sufficient to provide temporary accommodation for the Scottish Parliament, and not a permanent home” (White, 2005). Moreover, the high number that was submitted in July of that year was unrealistic, as this number would only cover a very basic Parliament building, or it might have only covered the construction cost or professional fees (White, 2005). The eventual cost of the project was £431 million (Max’s Project Management Wisdom).
The cost estimation for the Holyrood site for just the construction was £49.5 million, with another £5 million for site acquisition, and a designer competition for the site was underway that same month (White, 2005).
Of these competitors, EMBT/RMJM was successful in getting the contract to design the building, and the ministers at the press conference announcing them as the winners estimated the building to cost around £50 million (White, 2005). By this time, the costs overrun were foreshadowed already, as the estimated size of the building grew by 700 metres, due to an anticipated staff increase in connection with the Official Report and the Public Information Service, which would require three entrances, instead of the originally planned two (White, 2005). Almost immediately, costs estimations were increased because of “increased requirement for space and budget; the expansion of costs due to the foyer roof and use of kemnay granite” and the cost overruns estimates were because an increase, from 17,500 to 23,000, of the briefed gross area in the design proposals, which was necessary because of more staff than was anticipated, because of more knowledge about Parliament operations; secondly, the gross/net proportions in the brief were overly optimistic, and the design proposals could not match them; thirdly, a formal entrance was needed because of increased space demands. Additionally, ?17 million was supposed to an allocation for risk allowance, but this allocation did not occur (White, 2005). This is a brief background to the project and the estimated costs. In the end, the cost overrun was significant, and the project went significantly over the time limitation that was initially sought. The reasons for these were many, not the least of which is that the initial costs were unrealistic to begin with (The Holyrood Inquiry: Conclusions and Recommendations). ...Download file to see next pagesRead More
Cite this document
  • APA
  • MLA
  • CHICAGO
(“The Scottish Parliament Building Book Report/Review”, n.d.)
Retrieved from https://studentshare.org/architecture/1407767-the-scottish-parliament-building
(The Scottish Parliament Building Book Report/Review)
https://studentshare.org/architecture/1407767-the-scottish-parliament-building.
“The Scottish Parliament Building Book Report/Review”, n.d. https://studentshare.org/architecture/1407767-the-scottish-parliament-building.
  • Cited: 0 times
Comments (0)
Click to create a comment or rate a document
CHECK THESE SAMPLES - THEY ALSO FIT YOUR TOPIC
The Scottish Parliament Building
Project management entails the various activities that are undertaken in order to achieve preset goals of a project. These activities include planning, organizing, securing, and effective management of financial and human resources (Paul et al 2005). A project is a temporary work with set purpose, with a defined beginning and end which is usually constrained by factors such as funds, time and other deliverables.
3 Pages(750 words)Essay
Building on Reflective Practice: Reflection on Our teachers want to be the best
Building on Reflective Practice: Reflection on “Our teachers want to be the best”. In my reading and in class this week I learned crucial elements that need to be incorporated in teaching as a profession like adherence to ethical and moral standards of practice.
2 Pages(500 words)Book Report/Review
Building on Reflective Practice: Becoming real Aboriginal teachers
The terms ‘intergenerational narrative reverberations’ were used repeatedly throughout the article to indicate stories told of each teacher’s cultural, historical, and social experiences that shaped their personal and professional development.
1 Pages(250 words)Book Report/Review
Scottish Nationality
The book includes some important events and issues within the history of Scotland that the author thinks need to be focused while describing the Scottish history. The book surveys the Scottish political identity and development of Scottish national feelings from the early period to the present times and also discusses the evolution and growth of Scottish national party.
4 Pages(1000 words)Book Report/Review
The Scottish Parliament Building
This process goes through five phases i.e. initiate, plan, execute, control and finally close the project. These processes can be applied to typically any type of project. With the view of managing time, a clear description and detailed analysis of the project should be done.
4 Pages(1000 words)Essay
The Scottish Parliament Building
One of the key roles of project management is to ensure that the costs of a project are minimized without jeopardizing the operations of the project. In addition, project management entails effective management of time. It is worth to note that one of the major aspect that depicts a project as successful is effective use of time.
4 Pages(1000 words)Assignment
Building Memories
In "A Passage of the Hands," Barry Lopez recounts scenes from his life from observing the nuances of his own two hands. Combined, these two pieces lend greater insight into the dynamics of how we store and retrieve information than either piece could do separately.
3 Pages(750 words)Book Report/Review
Global Warming Book Report/Review
Climate change is increasingly framed as an issue where the threats are severe, increasingly imminent and potentially catastrophic. If the worst predictions of scientists prove to be accurate, then no one will be able to escape the consequences of climate change.
125 Pages(31250 words)Book Report/Review
The Scottish Parliament Building
With a major building such as this, the government had to answer to the people. It is political, and as such can have negative conflictive views that can anger the public. The funding is on the taxpayers back, therefore control of cost is
12 Pages(3000 words)Book Report/Review
Wealth building
ility thus creating the mentality that they can only be able to generate more money, achieve their goals or become happier, if only they had a better opportunity, circumstance or environment than the one they have presently (Taylor, 110). Therefore, the major impediment of the
4 Pages(1000 words)Book Report/Review
sponsored ads
We use cookies to create the best experience for you. Keep on browsing if you are OK with that, or find out how to manage cookies.
Let us find you another Book Report/Review on topic The Scottish Parliament Building for FREE!
Contact us:
+16312120006
Contact Us Now
FREE Mobile Apps:
  • About StudentShare
  • Testimonials
  • FAQ
  • Blog
  • Free Essays
  • New Essays
  • Essays
  • Miscellaneous
  • The Newest Essay Topics
  • Index samples by all dates
Join us:
Contact Us