Our website is a unique platform where students can share their papers in a matter of giving an example of the work to be done. If you find papers
matching your topic, you may use them only as an example of work. This is 100% legal. You may not submit downloaded papers as your own, that is cheating. Also you
should remember, that this work was alredy submitted once by a student who originally wrote it.
The paper “Capital Project Management” is a useful example of a finance & accounting report. Capital projects refer to those construction projects that promote the growth of a utility’s infrastructure or upgrade or reinstate the worn-out infrastructure. These projects require a considerable amount of financial investment or capital…
Download full paperFile format: .doc, available for editing
Name of Student
Course
Name of Instructor
Due Date
Capital Project Management
Introduction
Capital projects refer to those construction projects that promote the growth of a utility’s infrastructure or upgrade or reinstate the worn out infrastructure. These projects require a considerable amount of financial investment or capital. When they are completed, they are projected to service the utility and its customers for several years (Fight, 43). Hence, it is important that the delivery of project is realized. This assignment seeks to analyze a capital project at its preliminary phase. The assignment basically looks at the financial viability of the project in which case relevant computations of financial aspects of a project will be done.
Capital Cost of the Project.
Capital costs refer to costs that are realized during purchases. These include land, premises, construction and equipment procured in order to be employed in the production of goods or the provision of services (Fight, 47). In simple term capital cost is the overall cost required to move a project to a commercially functioning state. Nevertheless, capital costs are not narrowed to the preliminary construction of a manufacturing unit or other undertakings. For instance, the acquiring of a new device that will enhance production and have a long period of operation is a capital cost (Fight, 54). Additionally labor costs are not part of capital costs but construction labor is considered capital cost. It is vital to note that capital costs are expenses that are incurred only once but their payment may be stretched out for a given period of time in years as captured in financial statements and tax returns.
The following are the capital costs for this particular project;
Item Amount in £
The cost of major equipment in the tank farm 500,000
The cost of major equipment in the process area is 1,500,000
The total cost of installing the pipe rack 400,000
Additional capital requirement for support functions (25% of 2,400,000) 600,000
Total 3,000,000
Hence the total capital cost of this project is estimated to be £3 million; see attached excel spread sheet.
Product Sale Price
This is to be calculated in tonnes per year of production to achieve an internal rate of return of 30% over the ten years production life of the plant. Therefore, the basics of internal rate of returns will be highly useful in arriving at the exact sale price although this will not involve complex formulae and calculations. The basic concept is to consider all operational the cost incurred by the project per year and project a product sales price that will ensure an internal rate of return of 30% for the entire ten year operational period (Fight, 65).
Total capital cost 3,000,000
Fixed cost
Maintenance cost (2% of 2,000,000) 40,000
Insurance (1.5% of 2,000,000) 30,000
Wages and salaries 35,000
Indirect labor cost (40% of 35, 0000) 14,000
Total fixed Cost 119, 000
Variable cost
Raw materials 2,500,000
Utilities 1,000,000
Miscellaneous 250,000
Packaging and shipping 900,000
Total Variable cost 4,650,000
Total Fixed and variable cost 4,769,000
Capital cost will be repaid for a period of ten years hence payment per year will be 300,000 bringing the total project cost per year to be £5,069,000.
To realize an internal rate of return of 30%;
[(Y-5069000)/5069000] x 100 = 30%
When this is simplified and computed the value of Y is £5,084,207. This is thus the total product sales per year to realize IRR of 30% . This translates to £203.3 per ton.
Break Even Point in Years.
Breakeven point is arrived at by conducting a break even analysis. This is a computation of the volume of sales in a given units that is needed to merely cover costs (Fight, 88). When the volume of sales is low the result would be a loss while higher sales volume would lead to profitability. Therefore this analysis spotlights the correlation of fixed cost, cost per unit-variable cost, and selling price per unit (Fight, 89). Therefore, breakeven point for this project will be the point at which recovery of direct costs is realized, overhead costs have been engrossed and where profit commences. From economic and accounting perspective, the formula for arriving at a breakeven point is shown below;
Break-Even Point = FC/(1-VC/S)
Where: FC = Fixed Costs
VC = Variable Costs
S = Sales
From the previous computation;
Fixed Costs 119, 000
Variable Costs 4,650,000
Sales 5,069,000
Therefore,
BEP= 119000/(1-4650000/5069000)
BEP = 1,439,644.39
The projected was hence operated at 5,069,000/1,439,644.39 = 352% break even during the period.
Net Present Value (NPV) for the Project
Net present value abbreviated as NPV is the distinction between current value of cash inflows and the current value of cash outflows and the formula is as given below (Fight, 101).
For this project, this formula will not be used but instead an excel spread sheet will be employed in determining the net present value as well as profitability for the project, and the prototype is as shown below; (the actual excel spread sheet is attached)
The calculation on the spread sheet is based on the initial investment of 3 million euro and the project is envisaged to be generating an income of approximately 1.4 million euro every year. This value will be treated as the cash inflow or net income and the depreciation value of 0.2 million euro per year. The net present value at 15% rate is as shown below where by the initial invested amount is subtracted from the present value of the inflows gotten from the spread sheet.
Rate
15%
£3,094,222.22
year 1
1400000
year 2
1600000
year 3
1800000
year 4
2000000
year 5
2200000
year 6
2400000
year 7
2600000
year 8
2800000
year 9
3000000
year 10
3200000
NPV
94,222.22
Number of Design resource required in subsequent phases
Phases two and three of the project according to the timetable is envisaged to take 6 months. Six months has a total of 24 weeks and since working hours per week are 37.5, the total number of hours worked for 24 weeks (six months) will be;
24 x 37.5 = 900
Average cost per hour is estimated at £75
Therefore, to obtain the approximate number of design resources the average cost per hour will be multiplied by number of hours worked for the six months duration;
Design resources = 900 x 75 = £67,500
The Project’s Corporation Tax Liability
In the fourth year of production, the project will be generating an inflow of 2million euro with a profitability index of 1.5 %. This indicates that the project will have generated a profit before tax of:
(1.5 x 5,069,000) – 5,069,000 = 2,534,500
Corporation tax liability at 26% is
0.26 x 2,534,500 = 658 970
Summary Answer Sheet
Requirement
Answer
Total Capital Cost of Project £
3,000,000
Sales Price First Production Year £
5,084,207
Break-even point Years
1,439,644.39
NPV at discount rate of 15%, £
94,222.22
Design resource required
Number of people
67,500
Tax liability fourth production year £
658 970
Total
10,344,543.61
Works Cited
Fight, Andrew. Introduction to Project Finance. Oxford: Butterworth Heinemann, 2006. Print.
Read
More
… The paper “Fab Laundry Products Company's Results” is an engrossing example of a finance & accounting case study.... nbsp; Critical analysis of the cost of the two proposals over the period of 5 years will enable one to identify the less costly company on which the equipment and facilities should be purchased....
… The paper 'Engineering project management - Wembley Stadium" is a great example of a management case study.... The paper 'Engineering project management - Wembley Stadium" is a great example of a management case study.... or this reason, guidelines such as the project management Body of Knowledge (PMBK) and PRINCE2 have been developed to ensure projects are implemented based on best practice.... Managing projects have advanced to planning, coordinating and controlling the intricate and varied activities of contemporary industrial, management and commercial changes....
However, this may lead to shadow pricing which may have a significant impact on the social wellbeing of the community served by the water project.... In the water project, the viability of the project is evaluated in comparison with the internal return rate for the financial costs of the capital required in the water project.... Therefore, sensitivity and risk analysis in a water project is done to evaluate the changes in the most salient variables that determine the water project worthiness....
… The paper "project management for Business: Wembley National Stadium" is a great example of a case study on business.... The paper "project management for Business: Wembley National Stadium" is a great example of a case study on business.... A project is usually undertaken under the guidance of the principles of scope, time, quality, and cost (Lester 1).... For the project of constructing the new Wembley Stadium, these principles were used to guide all the activities that were carried out in the course of the project....
… The paper 'Risk management and Capital Structure and Lending at Banks' is a wonderful example of a management Assignment.... The paper 'Risk management and Capital Structure and Lending at Banks' is a wonderful example of a management Assignment.... The production design focuses on the production line and the plant layout for the project....
… The paper “EGCM Company- Project Screening Methods and Selection, Decision-Making over the Project Life Cycle” is a great variant of case study on management.... The paper “EGCM Company- Project Screening Methods and Selection, Decision-Making over the Project Life Cycle” is a great variant of case study on management.... pproaches to project Screening and SelectionAccording to Brown and Eisenhardt (1997)project screening is a process of evaluating various options in order to acquire useful information that can then be used in making a decision among the many available options on the way forward (Saaty, 1996)....
usinessThe author is a business management professional.... Fusion cuisine using organic ingredients constitutes a gap which this project seeks to fill.... Fusion cuisine using organic ingredients constitutes a gap which this project seeks to fill.... The project requires a capital outlay of $500 thousand.... The project aims to list on a stock exchange after five years.... roduct and ServiceThe project seeks to provide business clients with superior dining and entertainment experiences....
6 Pages(1500 words)Essay
sponsored ads
Save Your Time for More Important Things
Let us write or edit the report on your topic
"Capital Project Management"
with a personal 20% discount.